Karis: DeKalb 1

Short Code: Building 1
Year Planned: 2027
Utility Provider: ComEd
Floors: 2
Lot Size: 132 acres

Karis Critical is investing to build a huge data center campus in DeKalb, Illinois. The plan is for seven two-story data center buildings, each spanning 250,000 sq ft (23,226 sq m). In addition, ComEd plans to construct a 20-acre substation on the site to provide power to the campus and other portions of the region. It would be DeKalb's second data center campus. The project is expected to bring around 75 to 100 new jobs per building.

Map and Nearby Locations

Toll Plaza 65 Ramp K
Karis Critical Sites
Nearby Facilities

Karis: DeKalb 1 Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Karis: DeKalb 1

Distance Site About
0.09 miles Karis: DeKalb 2
This data center is a part of Karis' DeKalb Campus in Illinois.
0.19 miles Karis: DeKalb 7
This data center is a part of Karis' DeKalb Campus in Illinois.
0.23 miles Karis: DeKalb 3
This data center is a part of Karis' DeKalb Campus in Illinois.
0.32 miles Karis: DeKalb 4
This data center is a part of Karis' DeKalb Campus in Illinois.
0.32 miles Karis: DeKalb 6
This data center is a part of Karis' DeKalb Campus in Illinois.
0.40 miles Karis: DeKalb 5
This data center is a part of Karis' DeKalb Campus in Illinois.
0.71 miles CampusInterested in this information?Contact us
DeKalb 1 is one half of the first H-shaped building on Meta's DeKalb, Illinois campus, which opened in November 2023.
0.73 miles AlphaInterested in this information?Contact us
DeKalb 3 is the third building on Meta's DeKalb, Illinois campus, part of the expansion beyond the first H-shaped building.
0.73 miles East CenterInterested in this information?Contact us
DeKalb 2 is the second half of the first H-shaped building on Meta's DeKalb, Illinois campus, which opened in November 2023.
0.89 miles StationInterested in this information?Contact us
DeKalb 4 is the fourth building on Meta's DeKalb, Illinois campus, part of the expansion beyond the first H-shaped building.
0.95 miles Park PrimeInterested in this information?Contact us
DeKalb 5 is the fifth building on Meta's DeKalb, Illinois campus, part of the expansion beyond the first H-shaped building.
17.67 miles Savion: Plano Expansion
17.85 miles Savion: Plano 1
Plano 1 is the first building in Savion's proposed data center campus beside the Plano Skies Energy Center north of Plano, Illinois.
17.97 miles Prologis: Project Steel Expansion
Future Phases 2 and 3 of Prologis's Project Steel campus in Yorkville, Illinois: twelve two-story buildings and two substations at Galena and Eldamain roads, planned over the 2030s and 2040s.
18.14 miles Pioneer: Project Cardinal 1
First building of the northeast phase of Pioneer Development's Project Cardinal campus in Yorkville, Illinois. Planned as a two-story data center of about 1.36 million sq ft beside the campus ComEd switchyard and customer substation.
18.17 miles Edge PlazaInterested in this information?Contact us
Microsoft owns about 506 acres west of Eldamain Road at Corneils Road in Plano, Illinois, bought from three landowners in April 2024. Plano annexed and rezoned the land for a data center campus in 2024. Microsoft paused the project in June 2025.
18.24 miles Green Door: Yorkville Hagemann
Green Door Capital land-bank data center tract of about 138 acres on Eldamain Road in Yorkville, Illinois, held by Yorkville Nexus III LLC. Annexed and rezoned M-2 in 2024; no end user or site plan has been filed. Borders Prologis Project Steel near ComEd's Plano substation.
18.45 miles Pioneer: Project Cardinal Expansion
The other 13 planned buildings of Pioneer Development's Project Cardinal campus in Yorkville, Illinois, built in northeast, south and west phases after the first building.
18.86 miles Green Door: Yorkville 50 Acres
Green Door Capital land-bank data center tract of about 50 acres at Eldamain and Corneils roads in Yorkville, Illinois, held by Yorkville Nexus LLC. Zoned M-2 for data center use; no end user or site plan has been filed. Lies just north of CyrusOne's Yorkville campus.
18.88 miles Prologis: Project Steel 1
Phase 1 of Prologis's Project Steel campus in Yorkville: four two-story data center buildings of about 425,000 sq ft each and two substations, east of the ComEd corridor off Corneils and Beecher roads. Construction is planned to start in 2027.
19.12 miles CyrusOne: Yorkville 1
Building 11A of CyrusOne's Yorkville Technology Campus (CHI11) at Eldamain and Faxon roads in Yorkville, Illinois. A planned single-story data center of about 246,000 sq ft in the campus's northwest section. CyrusOne plans to build it first.
19.22 miles CyrusOne: Yorkville 2
Building 11B of CyrusOne's Yorkville Technology Campus (CHI11) at Eldamain and Faxon roads in Yorkville, Illinois. A planned single-story data center of about 129,000 sq ft, the campus's smallest building, beside Building 11A in the northwest section.
19.32 miles CyrusOne: Yorkville 3
Building 11C of CyrusOne's Yorkville Technology Campus (CHI11) at Eldamain and Faxon roads in Yorkville, Illinois. A planned single-story data center of about 246,000 sq ft at the west end of the campus's middle row.
19.41 miles CyrusOne: Yorkville 5
Building 11E of CyrusOne's Yorkville Technology Campus (CHI11) at Eldamain and Faxon roads in Yorkville, Illinois. A planned single-story data center of about 246,000 sq ft at the west end of the campus's south row, near Faxon Road.
19.44 miles CyrusOne: Yorkville 4
Building 11D of CyrusOne's Yorkville Technology Campus (CHI11) at Eldamain and Faxon roads in Yorkville, Illinois. A planned single-story data center of about 246,000 sq ft in the campus's middle row, just west of the on-site substation.
19.53 miles CyrusOne: Yorkville 6
Building 11F of CyrusOne's Yorkville Technology Campus (CHI11) at Eldamain and Faxon roads in Yorkville, Illinois. A planned single-story data center of about 246,000 sq ft in the middle of the campus's south row.
19.68 miles CyrusOne: Yorkville 7
Building 11G of CyrusOne's Yorkville Technology Campus (CHI11) at Eldamain and Faxon roads in Yorkville, Illinois. A planned single-story data center of about 246,000 sq ft at the east end of the south row, south of the on-site substation.
19.74 miles CyrusOne: Yorkville 9
Former ninth building of CyrusOne's 2024 Yorkville Technology Campus plan in Yorkville, Illinois. CyrusOne cut the campus to eight buildings in 2026, so this building is no longer planned.
19.74 miles CyrusOne: Yorkville 8
Building 11H of CyrusOne's Yorkville Technology Campus (CHI11) at Eldamain and Faxon roads in Yorkville, Illinois. A planned single-story data center of about 246,000 sq ft on the campus's east edge along Beecher Road.
19.95 miles Green Door: Yorkville Kelaka
Green Door Capital land-bank data center tract of about 154 acres south of Faxon Road in Yorkville, Illinois, held by Yorkville Nexus IV LLC. Yorkville approved its annexation and rezoning; no end user or site plan has been filed. Lies just south of CyrusOne's Yorkville campus.

Operating Company

Operated by:

Karis Critical invests in the land, energy & ​infrastructure behind the world's data ​center ecosystem.

0
Facilities
0
Markets

News See all

Read Karis Plans Potential Data Center Project in Central Ohio
Karis Plans Potential Data Center Project in Central Ohio

Karis Plans Potential Data Center Project in Central Ohio

April 14, 2026 Karis Critical

Data center developer Karis is looking to build a data center on the Big Darby Watershed in central Ohio. In a letter penned by Karis and published by Prairie Township authorities, the company said that it was in the “preliminary stages of evaluating this property for potential development.”“The...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?