KALiNA: Alsike Energy Park

Latest Podcast NW-30-49-3-W5M
Withdrawn
Project cancelled before construction
Operated by:

KALiNA: Alsike Energy Park

Year Planned: 2028
Utility Provider: FortisAlberta
Lot Size: 160 acres

Site History

  • October 2024: KALiNA files grid applications for the Alsike gas plant and data centre load.
  • November 2024: KALiNA and Crusoe sign a framework to build AI data centres at KALiNA's Alberta energy parks.
  • 2026: KALiNA withdraws the data centre load application and re-files the gas plant on its own.

Project Profile

  • Developer: KALiNA Distributed Power (Alsike Energy Park Inc.)
  • Land: about 160 acres in Leduc County
  • Status: Data centre withdrawn; gas plant in development

Map and Nearby Locations

NW-30-49-3-W5M ( Alsike Energy Park )
KALiNA Distributed Power Limited Sites
Nearby Facilities

KALiNA: Alsike Energy Park Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of KALiNA: Alsike Energy Park

Distance Site About
9.45 miles Capital Power: Genesee DC2
The second phase of Capital Power's proposed data centre beside the Genesee Generating Station in Leduc County, west of Edmonton.
9.70 miles Capital Power: Genesee DC1
Capital Power has proposed a hyperscale data centre on land it owns beside the Genesee Generating Station in Leduc County, west of Edmonton. The company says it is not advancing the project immediately.
11.78 miles TransAlta: Keephills Campus
Boreal Technology Hub is a planned AI data centre campus directly south of TransAlta's Keephills Generating Station in Parkland County, west of Edmonton. BGRE is developing it for Brookfield and CPP Investments, with TransAlta providing the site and power.
18.68 miles TransAlta: Sundance
TransAlta has rezoned land beside its Sundance Generating Station on Lake Wabamun in Parkland County for a data centre campus, west of Edmonton.

Operating Company

Operated by:

KALiNA Power Limited (“KPO”) is an ASX listed company dedicated to delivering cost effective power projects that incorporate technologies that generate constant baseload electricity with a low carbon footprint.

0
Facilities
0
Markets

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?