0.03 miles
|
Digital Realty: DUB14
|
Digital Realty opened its second data center on the Profile Park campus in Dublin, Ireland in 2019.
|
|
0.07 miles
|
Digital Realty: DUB15
|
Digital Realty seeks 10-year permission to build two data center buildings, known as DUB15 and DUB16, next to the company’s existing facilities on Profile Park’s Nangor Road, Clondalkin.
|
|
0.11 miles
|
Digital Realty: DUB16
|
Digital Realty seeks 10-year permission to build two data center buildings, known as DUB15 and DUB16, next to the company’s existing facilities on Profile Park’s Nangor Road, Clondalkin.
|
|
0.20 miles
|
Vantage: DUB 12
|
This facility is part of Vantage's DUB1 Campus in Dublin, Ireland.
|
|
0.22 miles
|
RidgeInterested in this information?Contact us
|
Google opened its first Irish data center in Dublin at Profile Park, Grange Castle in 2012.
|
|
0.24 miles
|
Vantage: DUB 13
|
Vantage is constructing a campus with three data centers outside Dublin, Ireland.
|
|
0.26 miles
|
Vantage: DUB11
|
Vantage is constructing a campus with three data centers outside Dublin, Ireland.
|
|
0.28 miles
|
Equinix: DB8
|
Equinix was planning to construct a facility at Profile Park, Nangor Road, Clondalkin in Dublin. The site was originally planned to be powered by the electric grid, but after failing to secure a permanent supply, Equinix adjusted the proposal to use gas power.
|
|
0.33 miles
|
ProInterested in this information?Contact us
|
In June 2024, Google submitted a planning application to build a 72,400 sqm (779,310 sq ft) data center on a 50-acre site adjacent to its existing two facilities at Grange Castle Business Park in South Dublin.
|
|
0.34 miles
|
Equinix Dublin DB2
|
Located in Grange Castle business park, DB2 is a former Telecity site that was acquired by Equinix in January 2016.
|
|
0.39 miles
|
Edge HubInterested in this information?Contact us
|
Google's second data center in Dublin is located at Google's Profile Park data center campus in Grange Castle.
|
|
0.44 miles
|
Global StationInterested in this information?Contact us
|
The last of four single-storey Microsoft data centres (DUB09, DUB10, DUB12, DUB13) at Grange Castle in west Dublin, completed in 2021.
|
|
0.47 miles
|
GlobalInterested in this information?Contact us
|
A stand-alone Microsoft data centre in its own compound on the Grange Castle campus in west Dublin, about 81,900 sq ft, running by 2022.
|
|
0.49 miles
|
Ridge TwoInterested in this information?Contact us
|
Amazon is building a campus with three two-storey data centers (Buildings A, B, and C) with mezzanine floors at each level, having a gross floor area of 78,871 sqm.
|
|
0.52 miles
|
CyrusOne : DUB I Bldg 2
|
Strategically located in Dublin, one of Europe’s premier data centre locations, CyrusOne DUB1 campus will ultimately deliver 360,000 sq ft) of technical space in three separate buildings of two storeys.
|
|
0.52 miles
|
StationInterested in this information?Contact us
|
One of four identical single-storey Microsoft data centres (DUB09, DUB10, DUB12, DUB13) at Grange Castle in west Dublin, operating by 2020.
|
|
0.54 miles
|
CyrusOne : DUB I Bldg 3
|
Strategically located in Dublin, one of Europe’s premier data centre locations, CyrusOne DUB1 campus will ultimately deliver 360,000 sq ft) of technical space in three separate buildings of two storeys.
|
|
0.55 miles
|
Park BetaInterested in this information?Contact us
|
One of a pair of identical single-storey Microsoft data centres, with DUB07, on the second Grange Castle campus in west Dublin, built in 2017 and 2018.
|
|
0.57 miles
|
East StationInterested in this information?Contact us
|
Amazon is building a campus with three two-storey data centers (Buildings A, B, and C) with mezzanine floors at each level, having a gross floor area of 78,871 sqm.
|
|
0.57 miles
|
Metro StationInterested in this information?Contact us
|
Amazon is building a campus with three two-storey data centers (Buildings A, B, and C) with mezzanine floors at each level, having a gross floor area of 78,871 sqm.
|
|
0.59 miles
|
Edge TowerInterested in this information?Contact us
|
One of four identical single-storey Microsoft data centres (DUB09, DUB10, DUB12, DUB13) at Grange Castle in west Dublin, operating by 2020.
|
|
0.59 miles
|
Cloud HubInterested in this information?Contact us
|
The first building on Microsoft's second Grange Castle campus in west Dublin, a 229,800 sq ft single-storey data centre completed in 2015.
|
|
0.61 miles
|
CyrusOne Dublin I
|
Strategically located in Dublin, one of Europe’s premier data centre locations, CyrusOne DUB1 campus will ultimately deliver 360,000 sq ft) of technical space in three separate buildings of two storeys.
|
|
0.62 miles
|
PrimeInterested in this information?Contact us
|
One of two two-storey Microsoft data centres, with DUB14, at the west end of the Grange Castle campus in Dublin, supported by an on-site gas generation compound.
|
|
0.65 miles
|
PlazaInterested in this information?Contact us
|
One of a pair of identical single-storey Microsoft data centres, with DUB08, on the second Grange Castle campus in west Dublin, built in 2017 and 2018.
|
|
0.66 miles
|
Point ProInterested in this information?Contact us
|
One of two two-storey Microsoft data centres, with DUB15, at the west end of the Grange Castle campus in Dublin. Its first of five data halls went live in July 2023.
|
|
0.68 miles
|
North TowerInterested in this information?Contact us
|
One of four identical single-storey Microsoft data centres (DUB09, DUB10, DUB12, DUB13) at Grange Castle in west Dublin, operating by 2020.
|
|
0.87 miles
|
PrimeInterested in this information?Contact us
|
Microsoft's first data centre outside the US, a 303,000 sq ft two-storey building at Grange Castle in west Dublin, opened July 2009.
|
|
0.92 miles
|
PlazaInterested in this information?Contact us
|
Microsoft's third data centre on its original Grange Castle campus in west Dublin, a 169,000 sq ft single-storey building completed in spring 2014.
|
|
0.96 miles
|
PrimeInterested in this information?Contact us
|
Microsoft's second Dublin data centre, a 112,000 sq ft single-storey Gen 4 modular building joined to the west end of DUB03 at Grange Castle, online at the end of 2012.
|
|
1.02 miles
|
CyrusOne Dublin Grange Castle
|
Approved in October 2018, CyrusOne is building a three building campus with 74 MW of power.
|
|
1.03 miles
|
Echelon: DUB 40
|
Echelon Data Centres’ DUB40 is planned to be located outside of Dublin, in a data center cluster known as Grange Castle.
|
|
1.04 miles
|
Digital Realty: DUB4
|
Digital Realty's DUB4 data center sits in Grange Castle Business Park, Dublin, next to its DUB3 facility.
|
|
1.09 miles
|
Digital Realty: DUB3
|
Located in the Grange Castle data centre cluster, the DUB3 data center offers 59,202 sqft of space and power densities of up to 2 kW per square meter.
|
|
1.09 miles
|
EdgeConnex DUB01
|
EdgeConnex initially built a 4,500sqm data centre (DUB01) in 2016 and later extended that facility further before adding a new 1,500sqm data hall in 2017.
|
|
1.11 miles
|
EdgeConnex DUB04
|
Ireland's national planning board, An Coimisiun Pleanala, has given the green light for two data centers in Dublin, overturning a 2023 decision by the local council to refuse permission.
|
|
1.15 miles
|
Edgeconnex: DUB02
|
|
|
1.19 miles
|
Edgeconnex: DUB03
|
|
|
1.29 miles
|
EdgeConnex DUB05
|
Ireland's national planning board, An Coimisiun Pleanala, has given the green light for two data centers in Dublin, overturning a 2023 decision by the local council to refuse permission.
|
|
1.55 miles
|
Equinix Dublin DB1
|
|
|
1.55 miles
|
Equinix: Citywest Dublin
|
The BT data centre is adjacent to Equinix's DB1 site.
|
|
1.83 miles
|
K2: DUB 6
|
K2 Data Centers completed the purchase of a 4.6-acre site in Citywest Business Park, Dublin, in July 2020 for approximately €3 million.
|
|
1.93 miles
|
Keppel DC Dublin1
|
|
|
1.93 miles
|
Cloud CenterInterested in this information?Contact us
|
|
|
2.63 miles
|
Echelon: DUB13
|
Echelon Data Centres has challenged a South Dublin County Council (SDCC) ruling to block the expansion of its DUB10 data center campus in Clondalkin, Dublin, Ireland.
|
|
2.72 miles
|
Echelon: DUB10
|
Echelon’s DUB10 campus will provide 90MW+ of IT load and includes a grid substation as well as on-site power generation.
|
|
2.73 miles
|
Echelon: DUB11
|
Echelon's DUB11 marks the second building of its Clondalkin campus, following the energization of the first building in Q4 2023.
|
|
2.74 miles
|
Echelon: DUB12
|
Echelon's DUB12 marks the third building of its Clondalkin campus.
|
|
3.31 miles
|
South ValleyInterested in this information?Contact us
|
|
|
3.37 miles
|
BetaInterested in this information?Contact us
|
|
|
3.43 miles
|
Digital Realty: Dublin 2
|
|
|
3.46 miles
|
Digital Realty: Dublin 1
|
|
|
3.97 miles
|
HubInterested in this information?Contact us
|
|
|
3.99 miles
|
Plaza GammaInterested in this information?Contact us
|
The Amazon AWS site is a former Tesco storage facility at Greenhills Industrial Estate in Dublin 24.
|
|
4.08 miles
|
Center MaxInterested in this information?Contact us
|
|
|
6.90 miles
|
Kyndryl: Dublin
|
|
|
6.94 miles
|
ProInterested in this information?Contact us
|
|
|
6.95 miles
|
Edge TowerInterested in this information?Contact us
|
|
|
6.96 miles
|
Equinix: DB5x
|
Equinix's fifth data center in Ireland opened in Q4 2022, located in the former Clyde House in Blanchardstown.
|
|
6.96 miles
|
Equinix: DB6x
|
DB6x is part of a three-building campus(DB5x, DB6x, DB7x) proposed in a 2020 planning application.
|
|
6.98 miles
|
Equinix: DB7x
|
Equinix has begun construction of its DB7x data center at its Blanchardstown campus in Profile Park, Grange Castle Business Park, Clondalkin, Dublin, Ireland, with the facility expected to deliver initial capacity by early 2028. Based on cost benchmarks, the project is estimated to provide 9MW of IT load, serving as a retail IBX expansion leveraging existing campus infrastructure.
|
|
7.03 miles
|
Central CenterInterested in this information?Contact us
|
|
|
7.03 miles
|
PlusInterested in this information?Contact us
|
|
|
7.12 miles
|
Hub ProInterested in this information?Contact us
|
Facebook broke ground on the Clonee data centre in 2016 and the first building became operational in December 2017. The centre is built on a 250-acre site that was formerly two farms adjoining the headquarters of the Kepak meat business.
|
|
7.15 miles
|
Keppel Dublin 2
|
Built in 2013, Keppel acquired the Ballycoolin site – previously owned by Dataplex – in 2017.
|
|
7.19 miles
|
Central PlazaInterested in this information?Contact us
|
This data center is a part of Meta's Clonee Campus in Ireland.
|
|
7.20 miles
|
PlazaInterested in this information?Contact us
|
This data center is a part of Meta's Clonee Campus in Ireland.
|
|
7.22 miles
|
K2: DUB 4
|
K2 Data Centres is building two more three-story data centers in Ballycoolin in Northwest Dublin.
|
|
7.23 miles
|
South PlazaInterested in this information?Contact us
|
This data center is a part of Meta's Clonee Campus in Ireland.
|
|
7.25 miles
|
Servecentric Blanchardstown
|
|
|
7.26 miles
|
K2: DUB 5
|
K2 Data Centres is building two more three-story data centers in Ballycoolin in Northwest Dublin.
|
|
7.27 miles
|
K2 Dublin 1
|
|
|
7.30 miles
|
Equinix: Ballycoolin
|
The Ballycoolin data center is a 40,000 sq ft (3,716 sqm) facility on Dublin's north side. It has 7,000 sq ft (650 sqm) of fully allocated data halls.
|
|
7.30 miles
|
East HubInterested in this information?Contact us
|
This data center is a part of Meta's Clonee Campus in Ireland.
|
|
7.30 miles
|
HubInterested in this information?Contact us
|
Amazon's Dublin Mulhuddart Campus is located on a 26-acre piece of land owned by the Irish Industrial Development Authority, close to Facebook's facility at Clonee.
|
|
7.39 miles
|
Center BetaInterested in this information?Contact us
|
Amazon's Dublin Mulhuddart Campus is located on a 26-acre piece of land owned by the Irish Industrial Development Authority, close to Facebook's facility at Clonee.
|
|
7.40 miles
|
Blanchardstown Dublin - Digital Realty
|
Digital Realty’s Blanchardstown Data Centre is a Tier Ill designed building, the two-story building is 120,000sqft. The facility also hosts Servecentric Blanchardstown in the building.
|
|
7.41 miles
|
Core PlazaInterested in this information?Contact us
|
|
|
7.42 miles
|
West TowerInterested in this information?Contact us
|
Amazon's Dublin Mulhuddart Campus is located on a 26-acre piece of land owned by the Irish Industrial Development Authority, close to Facebook's facility at Clonee.
|
|
7.46 miles
|
SouthInterested in this information?Contact us
|
Amazon's Dublin Mulhuddart Campus is located on a 26-acre piece of land owned by the Irish Industrial Development Authority, close to Facebook's facility at Clonee.
|
|
7.49 miles
|
Pure DC: DUB 01
|
Pure Data Centers is developing a campus with three data centers in Blanchardstown, Dublin.
|
|
7.53 miles
|
Pure DC: DUB 02
|
Pure Data Centers is developing a campus with three data centers in Blanchardstown, Dublin.
|
|
7.53 miles
|
Core StationInterested in this information?Contact us
|
Amazon's Dublin Mulhuddart Campus is located on a 26-acre piece of land owned by the Irish Industrial Development Authority, close to Facebook's facility at Clonee.
|
|
7.56 miles
|
Cloud ValleyInterested in this information?Contact us
|
Amazon's Dublin Mulhuddart Campus is located on a 26-acre piece of land owned by the Irish Industrial Development Authority, close to Facebook's facility at Clonee.
|
|
7.57 miles
|
Pure DC: DUB 03
|
Pure Data Centers is developing a campus with three data centers in Blanchardstown, Dublin.
|
|
7.58 miles
|
Valley ProInterested in this information?Contact us
|
Amazon's Dublin Mulhuddart Campus is located on a 26-acre piece of land owned by the Irish Industrial Development Authority, close to Facebook's facility at Clonee.
|
|
7.74 miles
|
Equinix Dublin DB4
|
Equinix has 4 colocation data centers in Dublin that were acquired from Telecity in 2016. Equinix operates DB3 and DB4 as a campus.
|
|
7.79 miles
|
Equinix Dublin DB3
|
Equinix has 4 colocation data centers in Dublin that were acquired from Telecity in 2016. Equinix operates DB3 and DB4 as a campus.
|
|
7.82 miles
|
EngineNode: Meath DC4
|
The EngineNode campus was proposed in 2019 to the north of the Facebook Clonee data center and south of the Bracetown Business Park.
|
|
7.86 miles
|
EngineNode: Meath DC3
|
The EngineNode campus was proposed in 2019 to the north of the Facebook Clonee data center and south of the Bracetown Business Park.
|
|
7.91 miles
|
EngineNode: Meath DC2
|
The EngineNode campus was proposed in 2019 to the north of the Facebook Clonee data center and south of the Bracetown Business Park.
|
|
7.94 miles
|
EngineNode Meath
|
The EngineNode campus was proposed in 2019 to the north of the Facebook Clonee data center and south of the Bracetown Business Park.
|
|
8.35 miles
|
Energia: Huntstown 1
|
Huntstown 1 (Building A) is the first of two three-story data centers beside Energia's Huntstown Power Station in north Dublin.
|
|
8.39 miles
|
Energia: Huntstown 2
|
Huntstown 2 (Building B) is the second of two three-story data centers beside Energia's Huntstown Power Station in north Dublin.
|
|
10.86 miles
|
Station TwoInterested in this information?Contact us
|
|
|
10.91 miles
|
Hyperscale Data CenterInterested in this information?Contact us
|
|
|
10.94 miles
|
PlazaInterested in this information?Contact us
|
|
|
10.95 miles
|
Metro CenterInterested in this information?Contact us
|
AWS demolished the existing former Ricoh building and constructed two data center buildings – Data Centre A and Data Centre B – with gross floor areas of c. 12,875 sqm (138,500 sq ft) and c. 1,455 sqm (15,600 sq ft) respectively, on the 3.75-hectare site.
|
|
10.95 miles
|
Park PlusInterested in this information?Contact us
|
|
|
10.96 miles
|
Digital Realty: Clonshaugh
|
Located within easy access of Dublin Airport, via city’s many transport links, Digital Realty’s Clonshaugh data centers (DUB11 and DUB12) provide 10,219m2(110,000f 2) of highly-connected premium customer space.
|
|
10.96 miles
|
Global CampusInterested in this information?Contact us
|
AWS demolished the existing former Ricoh building and constructed two data center buildings – Data Centre A and Data Centre B – with gross floor areas of c. 12,875 sqm (138,500 sq ft) and c. 1,455 sqm (15,600 sq ft) respectively, on the 3.75-hectare site.
|
|
10.99 miles
|
Edge RidgeInterested in this information?Contact us
|
|
|
11.01 miles
|
Campus PrimeInterested in this information?Contact us
|
|
|
11.01 miles
|
Hyperscale Data CenterInterested in this information?Contact us
|
|
|
11.04 miles
|
Hyperscale Data CenterInterested in this information?Contact us
|
|
|
11.07 miles
|
GTT Dublin International Exchange Center
|
|
|
11.14 miles
|
Vodafone Dublin
|
|
|
11.17 miles
|
Verizon Dublin
|
|
|
11.19 miles
|
East PointInterested in this information?Contact us
|
|
|
11.25 miles
|
TowerInterested in this information?Contact us
|
|
|
12.58 miles
|
South RidgeInterested in this information?Contact us
|
The facility will be part of Microsoft's Herbata Campus in County Kildare, southwest of Dublin.
|
|
12.64 miles
|
Core TowerInterested in this information?Contact us
|
The facility will be part of Microsoft's Herbata Campus in County Kildare, southwest of Dublin.
|
|
12.69 miles
|
East PlazaInterested in this information?Contact us
|
The facility will be part of Microsoft's Herbata Campus in County Kildare, southwest of Dublin.
|
|
12.74 miles
|
West ParkInterested in this information?Contact us
|
The facility will be part of Microsoft's Herbata Campus in County Kildare, southwest of Dublin.
|
|
12.74 miles
|
ThreeInterested in this information?Contact us
|
The facility will be part of Microsoft's Herbata Campus in County Kildare, southwest of Dublin.
|
|
12.83 miles
|
North TowerInterested in this information?Contact us
|
Microsoft is expanding its Irish data center footprint with a new campus in County Kildare, southwest of Dublin.
|