The EngineNode campus was proposed in 2019 to the north of the Facebook Clonee data center and south of the Bracetown Business Park. Irish data center firm EngineNode was granted permission to build the data center campus in Bracetown and Gunnocks in July 2022. This came after An Bord Pleanála dismissed complaints from a number of local and environmental groups trying to prevent the development, as well as the company's own attempts to remove certain conditions around development.

  • The facility will be built on the condition that the company contributes €1.85 million ($2.2m) towards a new road, and pays €2.29 million ($2.7m) towards the financing of phase 1 (Clonsilla to Dunboyne) of the Navan to Dublin rail line.
  • The company first submitted plans to build four two-story data centers with a combined gross floor area of ~92,100 sqm (990,000 sq ft) and a substation on the 24.5-hectare site in 2019. The on-site "energy center" has since been removed from the plans.

Map and Nearby Locations

Paddingstown
EngineNode Sites
Nearby Facilities

Sites within 15 miles of EngineNode Meath

Distance Site About
0.26 miles EngineNode: Meath DC2
The EngineNode campus was proposed in 2019 to the north of the Facebook Clonee data center and south of the Bracetown Business Park.
0.39 miles EngineNode: Meath DC3
The EngineNode campus was proposed in 2019 to the north of the Facebook Clonee data center and south of the Bracetown Business Park.
0.49 miles EngineNode: Meath DC4
The EngineNode campus was proposed in 2019 to the north of the Facebook Clonee data center and south of the Bracetown Business Park.
0.72 miles Edge CampusInterested in this information?Contact us
This data center is a part of Meta's Clonee Campus in Ireland.
0.84 miles Valley AlphaInterested in this information?Contact us
This data center is a part of Meta's Clonee Campus in Ireland.
1.07 miles Hub OneInterested in this information?Contact us
This data center is a part of Meta's Clonee Campus in Ireland.
1.25 miles RidgeInterested in this information?Contact us
This data center is a part of Meta's Clonee Campus in Ireland.
1.26 miles BetaInterested in this information?Contact us
Facebook broke ground on the Clonee data centre in 2016 and the first building became operational in December 2017. The centre is built on a 250-acre site that was formerly two farms adjoining the headquarters of the Kepak meat business.
2.62 miles Kyndryl: Dublin
3.15 miles WestInterested in this information?Contact us
Amazon's Dublin Mulhuddart Campus is located on a 26-acre piece of land owned by the Irish Industrial Development Authority, close to Facebook's facility at Clonee.
3.17 miles GlobalInterested in this information?Contact us
Amazon's Dublin Mulhuddart Campus is located on a 26-acre piece of land owned by the Irish Industrial Development Authority, close to Facebook's facility at Clonee.
3.23 miles Global StationInterested in this information?Contact us
Amazon's Dublin Mulhuddart Campus is located on a 26-acre piece of land owned by the Irish Industrial Development Authority, close to Facebook's facility at Clonee.
3.24 miles EastInterested in this information?Contact us
Amazon's Dublin Mulhuddart Campus is located on a 26-acre piece of land owned by the Irish Industrial Development Authority, close to Facebook's facility at Clonee.
3.25 miles South PlazaInterested in this information?Contact us
Amazon's Dublin Mulhuddart Campus is located on a 26-acre piece of land owned by the Irish Industrial Development Authority, close to Facebook's facility at Clonee.
3.32 miles AlphaInterested in this information?Contact us
Amazon's Dublin Mulhuddart Campus is located on a 26-acre piece of land owned by the Irish Industrial Development Authority, close to Facebook's facility at Clonee.
3.34 miles Center TwoInterested in this information?Contact us
Amazon's Dublin Mulhuddart Campus is located on a 26-acre piece of land owned by the Irish Industrial Development Authority, close to Facebook's facility at Clonee.
3.71 miles Equinix: Ballycoolin
The Ballycoolin data center is a 40,000 sq ft (3,716 sqm) facility on Dublin's north side. It has 7,000 sq ft (650 sqm) of fully allocated data halls.
3.71 miles EdgeInterested in this information?Contact us
3.73 miles Blanchardstown Dublin - Digital Realty
Digital Realty’s Blanchardstown Data Centre is a Tier Ill designed building, the two-story building is 120,000sqft. The facility also hosts Servecentric Blanchardstown in the building.
3.80 miles Servecentric Blanchardstown
3.84 miles Equinix: DB5x
Equinix's fifth data center in Ireland opened in Q4 2022, located in the former Clyde House in Blanchardstown.
3.88 miles Equinix: DB6x
DB6x is part of a three-building campus(DB5x, DB6x, DB7x) proposed in a 2020 planning application.
3.92 miles Equinix: DB7x
Equinix has begun construction of its DB7x data center at its Blanchardstown campus in Profile Park, Grange Castle Business Park, Clondalkin, Dublin, Ireland, with the facility expected to deliver initial capacity by early 2028. Based on cost benchmarks, the project is estimated to provide 9MW of IT load, serving as a retail IBX expansion leveraging existing campus infrastructure.
4.09 miles Ridge TwoInterested in this information?Contact us
4.09 miles K2: DUB 5
K2 Data Centres is building two more three-story data centers in Ballycoolin in Northwest Dublin.
4.09 miles OneInterested in this information?Contact us
4.15 miles K2: DUB 4
K2 Data Centres is building two more three-story data centers in Ballycoolin in Northwest Dublin.
4.23 miles Center AlphaInterested in this information?Contact us
4.25 miles Core RidgeInterested in this information?Contact us
4.32 miles K2 Dublin 1
4.35 miles Keppel Dublin 2
Built in 2013, Keppel acquired the Ballycoolin site – previously owned by Dataplex – in 2017.
4.47 miles Equinix Dublin DB4
Equinix has 4 colocation data centers in Dublin that were acquired from Telecity in 2016. Equinix operates DB3 and DB4 as a campus.
4.59 miles Pure DC: DUB 01
Pure Data Centers is developing a campus with three data centers in Blanchardstown, Dublin.
4.66 miles Pure DC: DUB 02
Pure Data Centers is developing a campus with three data centers in Blanchardstown, Dublin.
4.69 miles Equinix Dublin DB3
Equinix has 4 colocation data centers in Dublin that were acquired from Telecity in 2016. Equinix operates DB3 and DB4 as a campus.
4.70 miles Pure DC: DUB 03
Pure Data Centers is developing a campus with three data centers in Blanchardstown, Dublin.
5.70 miles Energia: Huntstown, Dublin
Energia Group subsidiary Huntstown Power Company has been granted planning permission by Fingal County Council to build two data centers adjacent to the Huntstown Power Station in Dublin, Ireland.
5.79 miles Energia: Huntstown 2
Energia Group subsidiary Huntstown Power Company has been granted planning permission by Fingal County Council to build two data centers adjacent to the Huntstown Power Station in Dublin, Ireland.
6.83 miles Edgeconnex: DUB03
6.85 miles Digital Realty: DUB3
Located in the Grange Castle data centre cluster, the DUB3 data center offers 59,202 sqft of space and power densities of up to 2kW per square meter, with 4.6MW available for the entire data center.
6.88 miles Edgeconnex: DUB02
6.90 miles Digital Realty: DUB4
Digital Realty's DUB4 data center is situated in Grand Castle Park, Dublin, next to its DUB3 facility.
6.91 miles EdgeConnex DUB05
Ireland's national planning board, An Coimisiun Pleanala, has given the green light for two data centers in Dublin, overturning a 2023 decision by the local council to refuse permission.
6.94 miles CyrusOne Dublin Grange Castle
Approved in October 2018, CyrusOne is building a three building campus with 74 MW of power.
6.95 miles Edgeconnex Dublin
EdgeConnex initially built a 4,500sqm data centre (DUB01) in 2016 and later extended that facility further before adding a new 1,500sqm data hall in 2017.
7.00 miles Echelon: DUB 40
Echelon Data Centres’ DUB40 is planned to be located outside of Dublin, in a data center cluster known as Grange Castle.
7.06 miles EdgeConnex DUB04
Ireland's national planning board, An Coimisiun Pleanala, has given the green light for two data centers in Dublin, overturning a 2023 decision by the local council to refuse permission.
7.19 miles Campus GammaInterested in this information?Contact us
7.29 miles Station AlphaInterested in this information?Contact us
7.29 miles East RidgeInterested in this information?Contact us
7.29 miles Point BetaInterested in this information?Contact us
Commissioned in 2009, the site was Microsoft's first data center outside of the United States.
7.36 miles Echelon Clondalkin
Echelon’s DUB10 campus will provide 90MW+ of IT load and includes a grid substation as well as on-site power generation.
7.37 miles Campus OneInterested in this information?Contact us
7.37 miles Global HubInterested in this information?Contact us
The two new facilities, DUB14 & DUB15, are located west of the company's DUB9, DUB10, DUB12, and DUB13 data centers on the Microsoft Dublin Grange Castle campus.
7.37 miles ThreeInterested in this information?Contact us
7.39 miles PointInterested in this information?Contact us
7.43 miles Echelon: DUB11
Echelon's DUB11 marks the second building of its Clondalkin campus, following the energization of the first building in Q4 2023.
7.44 miles Hub MaxInterested in this information?Contact us
The two new facilities, DUB14 & DUB15, are located west of the company's DUB9, DUB10, DUB12, and DUB13 data centers on the Microsoft Dublin Grange Castle campus.
7.45 miles CampusInterested in this information?Contact us
7.47 miles Echelon: DUB13
Echelon Data Centres has challenged a South Dublin County Council (SDCC) ruling to block the expansion of its DUB10 data center campus in Clondalkin, Dublin, Ireland.
7.51 miles Echelon: DUB12
Echelon's DUB12 marks the third building of its Clondalkin campus.
7.52 miles Digital Realty: Dublin 1
7.54 miles East StationInterested in this information?Contact us
7.58 miles PointInterested in this information?Contact us
Amazon is building a campus with three two-storey data centers (Buildings A, B, and C) with mezzanine floors at each level, having a gross floor area of 78,871 sqm.
7.61 miles Global ParkInterested in this information?Contact us
Amazon is building a campus with three two-storey data centers (Buildings A, B, and C) with mezzanine floors at each level, having a gross floor area of 78,871 sqm.
7.62 miles Equinix Dublin DB2
Located in Grange Castle business park, DB2 is a former Telecity site that was acquired by Equinix in January 2016.
7.63 miles Cloud ParkInterested in this information?Contact us
Amazon is building a campus with three two-storey data centers (Buildings A, B, and C) with mezzanine floors at each level, having a gross floor area of 78,871 sqm.
7.70 miles Vantage: Dublin DUB1
Vantage is constructing a campus with three data centers outside Dublin, Ireland.
7.70 miles Vantage: DUB 13
Vantage is constructing a campus with three data centers outside Dublin, Ireland.
7.70 miles Equinix: DB8
Equinix was planning to construct a facility at Profile Park, Nangor Road, Clondalkin in Dublin. The site was originally planned to be powered by the electric grid, but after failing to secure a permanent supply, Equinix adjusted the proposal to use gas power.
7.73 miles CyrusOne Dublin I
Strategically located in Dublin, one of Europe’s premier data centre locations, CyrusOne DUB1 campus will ultimately deliver 360,000 sq ft) of technical space in three separate buildings of two storeys.
7.75 miles CyrusOne : DUB I Bldg 2
Strategically located in Dublin, one of Europe’s premier data centre locations, CyrusOne DUB1 campus will ultimately deliver 360,000 sq ft) of technical space in three separate buildings of two storeys.
7.76 miles Vantage: DUB 12
This facility is part of Vantage's DUB1 Campus in Dublin, Ireland.
7.78 miles Digital Realty: Dublin 2
7.82 miles CyrusOne : DUB I Bldg 3
Strategically located in Dublin, one of Europe’s premier data centre locations, CyrusOne DUB1 campus will ultimately deliver 360,000 sq ft) of technical space in three separate buildings of two storeys.
7.85 miles GlobalInterested in this information?Contact us
Google's second data center in Dublin is located at Google's Profile Park data center campus in Grange Castle.
7.94 miles Digital Profile Park Dublin
Digital Realty owns the 10 acre site at Profile Park and will have access to both power and fiber. The company has secured planning approval to construct 193,384 gross sq ft in two phases and over four buildings.
7.94 miles StationInterested in this information?Contact us
Google opened its first Irish data center in Dublin at Profile Park, Grange Castle in 2012.
7.97 miles Digital Realty: DUB14
Digital Realty opened its second data center on the Profile Park campus in Dublin, Ireland in 2019.
8.01 miles Digital Realty: DUB15
Digital Realty seeks 10-year permission to build two data center buildings, known as DUB15 and DUB16, next to the company’s existing facilities on Profile Park’s Nangor Road, Clondalkin.
8.01 miles RidgeInterested in this information?Contact us
In June 2024, Google submitted a planning application to build a 72,400 sqm (779,310 sq ft) data center on a 50-acre site adjacent to its existing two facilities at Grange Castle Business Park in South Dublin.
8.04 miles Digital Realty: DUB16
Digital Realty seeks 10-year permission to build two data center buildings, known as DUB15 and DUB16, next to the company’s existing facilities on Profile Park’s Nangor Road, Clondalkin.
9.27 miles Equinix: Citywest Dublin
The BT data centre is adjacent to Equinix's DB1 site.
9.27 miles Equinix Dublin DB1
9.49 miles K2: DUB 6
K2 Data Centers completed the purchase of a 4.6-acre site in Citywest Business Park, Dublin, in July 2020 for approximately €3 million.
9.56 miles Tower OneInterested in this information?Contact us
9.60 miles Valley OneInterested in this information?Contact us
9.61 miles Plaza PrimeInterested in this information?Contact us
9.67 miles PlusInterested in this information?Contact us
9.67 miles Keppel DC Dublin1
9.67 miles Ridge ProInterested in this information?Contact us
9.72 miles PrimeInterested in this information?Contact us
9.76 miles Vodafone Dublin
9.83 miles East PlazaInterested in this information?Contact us
9.86 miles Verizon Dublin
9.91 miles Hyperscale Data CenterInterested in this information?Contact us
9.91 miles Hyperscale Data CenterInterested in this information?Contact us
9.93 miles Hyperscale Data CenterInterested in this information?Contact us
9.93 miles AlphaInterested in this information?Contact us
9.95 miles Valley OneInterested in this information?Contact us
9.98 miles Digital Realty: Clonshaugh
Located within easy access of Dublin Airport, via city’s many transport links, Digital Realty’s Clonshaugh data centers (DUB11 and DUB12) provide 10,219m2(110,000f 2) of highly-connected premium customer space.
10.02 miles CoreInterested in this information?Contact us
10.05 miles West ParkInterested in this information?Contact us
AWS demolished the existing former Ricoh building and constructed two data center buildings – Data Centre A and Data Centre B – with gross floor areas of c. 12,875 sqm (138,500 sq ft) and c. 1,455 sqm (15,600 sq ft) respectively, on the 3.75-hectare site.
10.07 miles Plaza AlphaInterested in this information?Contact us
AWS demolished the existing former Ricoh building and constructed two data center buildings – Data Centre A and Data Centre B – with gross floor areas of c. 12,875 sqm (138,500 sq ft) and c. 1,455 sqm (15,600 sq ft) respectively, on the 3.75-hectare site.
10.12 miles TowerInterested in this information?Contact us
The Amazon AWS site is a former Tesco storage facility at Greenhills Industrial Estate in Dublin 24.
10.13 miles GTT Dublin International Exchange Center
10.19 miles ParkInterested in this information?Contact us
10.30 miles Park PlusInterested in this information?Contact us
17.60 miles Metro TowerInterested in this information?Contact us
The facility will be part of Microsoft's Herbata Campus in County Kildare, southwest of Dublin.
17.61 miles Hub ProInterested in this information?Contact us
The facility will be part of Microsoft's Herbata Campus in County Kildare, southwest of Dublin.
17.69 miles Valley UltraInterested in this information?Contact us
The facility will be part of Microsoft's Herbata Campus in County Kildare, southwest of Dublin.
17.74 miles Hub UltraInterested in this information?Contact us
The facility will be part of Microsoft's Herbata Campus in County Kildare, southwest of Dublin.
17.75 miles Ridge GammaInterested in this information?Contact us
The facility will be part of Microsoft's Herbata Campus in County Kildare, southwest of Dublin.
17.79 miles Edge CenterInterested in this information?Contact us
Microsoft is expanding its Irish data center footprint with a new campus in County Kildare, southwest of Dublin.
19.28 miles Cloud PlazaInterested in this information?Contact us
The facility is located in the IDA Business and Technology Park, Donore Road, Drogheda, Co Meath.
19.34 miles WestInterested in this information?Contact us
Amazon is constructing a two-story data center spanning 28,566 square meters (307,400 square feet) at the Drogheda IDA Business & Technology Park.

EngineNode Meath Data Center Photos See all

EngineNode Meath Campus Layout Final
Source: EngineNode
EngineNode Meath Campus Layout Final
Source: EngineNode
EngineNode Meath Campus Layout Final
Source: EngineNode
EngineNode campus layout
Source: Baxtel
EngineNode Meath Campus Layout Final
Source: EngineNode

Operating Company

Operated by:

EngineNode is a Irish data centre firm based in Dublin

4
Facilities
1
Markets

News See all

Read ABB Buys Premium Power to Strengthen Data Center Advisory Services
ABB Buys Premium Power to Strengthen Data Center Advisory Services

ABB Buys Premium Power to Strengthen Data Center Advisory Services

February 16, 2026 Dublin

Global electrification firm ABB has acquired Irish electrical engineering consultancy Premium Power to expand its advisory capabilities within the data center market.“For more than two decades, Premium Power has built its reputation by helping customers solve complex electrical challenges with...

Read more
Read RackNerd expands offerings to Dublin, Ireland
RackNerd expands offerings to Dublin, Ireland

RackNerd expands offerings to Dublin, Ireland

November 21, 2024 Dublin

Infrastructure-as-a-Service (IaaS) provider RackNerd has expanded its offering to Dublin, Ireland and will be offering its IaaS from the Digital Realty DU10 data center located in Dublin, Ireland."Our expansion into Dublin represents a strategic response to the growing demand for high-performance...

Read more
Read Data center proposal for SDC Piperstown in Dublin, Ireland, pulled
Data center proposal for SDC Piperstown in Dublin, Ireland, pulled

Data center proposal for SDC Piperstown in Dublin, Ireland, pulled

April 30, 2023 Dublin

The Dublin, Ireland, two-story data center developing application has been retracted. SDC Piperstown II Ltd submitted a request to Fingal County Council on January 17, 2023, for permission to build a data center on a 20-acre site in Piperstown, Dublin. But this has since been dropped, for no...

Read more
Read More applications for data centers in the greater Dublin area as grid capacity concerns continue
More applications for data centers in the greater Dublin area as grid capacity concerns continue

More applications for data centers in the greater Dublin area as grid capacity concerns continue

January 01, 2023 Dublin

According to reports, in the wake of the Dublin data center moratorium over grid issues, 21 new data centers are planned outside of the greater Dublin area. Sixteen of these facilities are large-scale data centers, while a further five smaller-scale data center projects are being discussed with...

Read more
Read Irish government confirms terms and conditions for ORESS 1
Irish government confirms terms and conditions for ORESS 1

Irish government confirms terms and conditions for ORESS 1

November 25, 2022 Dublin

Following the Irish government's approval of the terms and conditions of ORESS 1, a huge auction for offshore wind, 2.5GW of renewable energy could be added to the grid, enough to power 2.5 million Irish homes with green electricity. According to reports, at least three offshore energy auctions...

Read more
Read More News

Podcasts See all

See More Podcasts

Documents See all

Ready to Level up Your
Data Center Strategy?