Overview
Albany is the capital of New York State and the center of the Capital Region, which takes in Schenectady, Troy and Saratoga County. The market is made up of carrier colocation rooms downtown, a few retail colocation buildings in the suburbs, and enterprise, state and university data centers. In 2026 a developer proposed a large campus in the city.
History
MetLife has run its data center in North Greenbush since 1992. Local fiber companies built the early colocation base. Tech Valley Communications, founded in 1999, became FirstLight in 2013. INOC, formed in 2000 by four upstate telephone companies, began selling colocation in 2001 and added a second data center in 2016. TurnKey Internet opened its Latham data center in 2012, and that building now runs as Hivelocity ALB1. The State University of New York added a campus data center in 2014, and the state began moving agency computing to a shared site at Albany's nanotechnology campus. Lightower bought Fibertech in 2015, Crown Castle bought Lightower in 2017, and Zayo bought Crown Castle's fiber business in May 2026.
The Market Today
Downtown Albany holds the region's network hubs. INOC and Zayo share an office tower at 80 State Street, and FirstLight and Lumen have space at 11 North Pearl Street. Lumen also runs sites on North Pearl Street, Washington Avenue and Airline Drive.
Retail colocation extends to the suburbs, with INOC at Tower Place, Hivelocity in Latham, HostRocket in Clifton Park and Cogent in a former Sprint building in Glenmont. The University at Albany unveiled an artificial intelligence supercomputer in its campus data center in 2024.
Guild Ventures proposes the Kenwood Tech Center, a technology campus with a data center on the former Kenwood Academy grounds in Albany. The developer had filed no application with the city by August 2026.
Advantages
-
Network position. Fiber routes connect Albany to New York City, Boston and Montreal, and the downtown rooms host several carriers.
-
Public demand. State agencies and universities need local capacity, and both run their own data centers here.
-
Technology base. The nanotechnology campus and the chip plant in Malta anchor a local engineering workforce.
Challenges
-
State pause. Executive Order 62, signed in July 2026, pauses environmental permits for data centers of 50 MW or more.
-
Local zoning. City zoning does not allow a data center on the Kenwood site, and the Common Council backed a statewide pause in July 2026.
-
Local opposition. Neighborhood groups oppose the Kenwood plan over power use and property taxes.
-
Scale. Most facilities are single rooms or small buildings, which leaves little space for a large tenant.
Trends
-
Fiber owners change hands. The downtown carrier rooms have moved between national fiber companies three times since 2015.
-
Towns act early. Perth in Fulton County adopted a one-year moratorium in June 2026.
Power and Policy
National Grid is the main utility, and the New York Independent System Operator (NYISO) runs the grid. NYISO's queue shows one active data center request in its Capital zone, the Kenwood project. The state legislature passed a separate moratorium bill in June 2026 for data centers of 20 MW or more.