1606 Corp. plans to turn the former Aspen Power plant in north Lufkin into a powered site for AI computing. The wood-waste biomass plant began running in 2011, went through foreclosure and has been idle since 2015. 1606 would restart it to power a data center in a climate-controlled warehouse on the property. It has signed a letter of intent with EthosEnergy to operate and maintain the plant, and hired MDM Group to market the site to AI users. 1606 has warned that the plant may need substantial repair or replacement first.
The purchase has not closed. 1606 agreed in March 2026 to buy the property from Jefferson Enterprise Energy for about $11.2 million: $7 million in cash plus an assumed lien. Four amendments moved closing to 31 October 2026. That date passed with the cash portion unfunded and $488,000 in extension fees already paid and nonrefundable.
Site History
-
November 2026: 1606 reported that the 31 October closing date had passed, that the cash portion remained unfunded and that the seller may exercise its remedies.
-
September 2026: 1606 signed a letter of intent with EthosEnergy to operate and maintain the plant.
-
August 2026: 1606 hired MDM Group to market the site to AI users.
-
April to July 2026: Four amendments extended the closing date, the last to 31 October 2026.
-
March 2026: 1606 signed a purchase agreement with Jefferson Enterprise Energy for the plant, the warehouse and the surrounding land.
-
February 2026: 1606 signed a term sheet to buy the property.
-
2021 to 2023: Jefferson Enterprise Energy planned a pulp, sodium chlorate and molded-fiber complex on the site, supplied by an upgraded plant. It did not go ahead.
-
October 2020: Jefferson Enterprise Energy bought the plant.
-
November 2016: The plant was sold at a sheriff's sale after foreclosure.
-
September 2015: The plant was retired.
-
September 2011: The plant began commercial operation.