Overview
Leeds is the largest data centre market in Yorkshire and the main interconnection point in the north of England between Manchester and the North East. For two decades it served regional businesses, public bodies and banks from small facilities in the city and along the M62 and M1 near Wakefield. Since 2024 the market has turned toward hyperscale. Microsoft and other developers now plan large campuses on former coal power station land east of the city, where the old grid connections remain.
History
Leeds-based aql opened its first data centre halls on Hunslet Road in 2006. In 2011 it converted the neighbouring Salem Chapel into a third hall, which became the home of IXLeeds, the city's internet exchange. Another colocation site opened in 2002 in Cornelius House, a former bullion vault in Armley. Operators around Wakefield, Halifax and Birstall built disaster recovery and colocation sites for enterprise customers through the 2000s.
The last few years brought a run of sales and closures. Asanti bought Daisy's Birstall data centre in 2022. Redcentric closed its Harrogate facility in 2024 and later sold its remaining sites, including Elland, to Stellanor. Lloyds Banking Group left its Copley data centre near Halifax in 2025. In May 2026 Templus completed its purchase of Cornelius House from AtlasEdge.
The Market Today
aql, Templus, Asanti, Stellanor, Node4 and nLighten run the main colocation sites, each a small facility serving regional customers. aql's Hunslet Road campus remains the city's interconnection hub. Banks and telecom carriers run their own sites, including HSBC's group data centre at Normanton and Virgin Media's communications hub in Seacroft.
The hyperscale pipeline sits east of the city. Microsoft plans a three-building campus at Skelton Grange in Leeds, which councillors resolved to approve in April 2026. It also holds approval for a two-building campus at the former Eggborough power station. Bowmer & Kirkland has approval for four buildings on the former Ferrybridge coal yard. Drax plans a gigawatt-scale campus at its power station near Selby with Brookfield and Radiant. In Bradford, Deep Green won permission in May 2026 for a small data centre next to the Bradford Energy Centre.
Advantages
-
Legacy grid connections. Former coal plants at Skelton Grange, Ferrybridge, Eggborough and Drax sit on National Grid's 275 kV and 400 kV network.
-
Central location. Leeds sits at the junction of the M1 and M62, with fibre routes to London, Manchester, Scotland and the North East.
-
Demand base. Banking, health, public sector and retail headquarters in Leeds need regional capacity and disaster recovery sites.
-
Land. Brownfield power station sites offer large, flat plots already zoned for industry.
Challenges
-
Grid queues. New connections wait on the national connections reform led by the National Energy System Operator (NESO).
-
Slow approvals. Large schemes take years to clear planning, and several approvals still wait on legal agreements or a start on site.
-
Small colocation stock. Most operating facilities are small, so large enterprise and AI deployments find little ready capacity.
-
Older buildings. Many sites are conversions of offices, chapels and industrial units from the early 2000s.
Trends
-
Ownership is consolidating. Templus, Asanti and Stellanor have bought local sites from earlier operators.
-
Power stations become data centres. Every large project in the pipeline reuses a former coal plant's land and grid connection.
-
Enterprise sites are closing. Banks and managed service firms are leaving older buildings, as at Copley and Harrogate.
Power and Policy
Northern Powergrid distributes electricity across West and North Yorkshire, and National Grid Electricity Transmission owns the high-voltage network. NESO runs the connection queue, which it reordered under the 2025 connections reform. Ofgem regulates both. Leeds City Council, Wakefield, Bradford and North Yorkshire Council decide planning, with the West Yorkshire Combined Authority setting regional growth policy. A bid to make the Drax site an AI Growth Zone was dropped in October 2026.