The City of Rockford named [Microsoft](https://baxtel.com/data-centers/microsoft-azure) on Nov. 13 as the company evaluating a Monarch Energy-controlled pro![msblogs.thesourcemediaassets.com](/rail...

Microsoft Eyes 1.4GW Data Center Campus on Monarch Land in Rockford, Illinois

Mike Bavto

Mike Bavto

November 16, 2026

The City of Rockford named Microsoft on Nov. 13 as the company evaluating a Monarch Energy-controlled promsblogs.thesourcemediaassets.comFeatured: Expansive landscape aerial view of a large-scale Microsoft data center campus.perty in south Rockford for a data center campus. Microsoft is conducting due diligence on the land and has not submitted a proposal, the city said in its announcement.

The land sits along Edson and Friday roads near the Ogle and Winnebago county line. Monarch Rock Air, an affiliate of California-based Monarch Energy, holds a memorandum of understanding with the Illinois Department of Commerce and Economic Opportunity for a multibuilding campus with a 1,400MW phased data center, according to the Rock River Current. Monarch controls the land. Microsoft would develop and operate the facility if the project advances.


Monarch signed the agreement on June 5, 2026, and the state signed on June 11. Under its terms, Monarch must invest at least $250 million over five years, employ at least 100 full-time workers and pay wages above 120% of the average full-time pay in Winnebago County, listed at $59,400. The deal predates Gov. JB Pritzker's July 1 pause on processing new applications under the Data Center Investment Program, which honors earlier agreements.

Power remains unsettled. ComEd canceled its transmission security agreement with Monarch Rock Air in late July, a filing with the Federal Energy Regulatory Commission showed, and Monarch is now in a later ComEd study process.

"We are continuing to work with ComEd to provide power to our planned industrial site on a revised timeline," said Charles Koontz, chief operating officer and co-founder of Monarch Energy, in a statement to the Rock River Current.

The Rockford City Council approved a six-month data center moratorium on Aug. 3, but city staff say it does not cover the Monarch land because of a pre-existing annexation agreement. The Zoning Board of Appeals holds a public hearing on proposed data center rules at 6 p.m. Tuesday, Nov. 17, at City Hall. Microsoft says it intends to meet those standards, Data Center Dynamics reported.

Microsoft's information packet says the company operates 17 data centers in Illinois, and Microsoft also plans a campus in Cherry Valley, where Baxtel lists a planned site. The packet says Microsoft campuses typically employ 100 to 250 full-time workers and vendors, starting with about 50 at the first building, Rockford News First reported.

Baxtel tracks 238 data center facilities across Illinois, operated by 83 providers, with Meta and Microsoft Azure the leading operators at five sites each. The largest is Microsoft's Chicago Northlake site, at 158MW.

Microsoft has not submitted site plans, and the city says the dates for community open houses will be announced later.