Read Georgia Residents File RICO Suit Against OpenAI Over 3.2GW Project Camellia
Three residents of Effingham County, [Georgia](https://baxtel.com/regions/georgia), sued [OpenAI](https://baxtel.com/data-centers/openai) and county officials on Nov. 6 over a 3.2-gigawatt data cen...

Georgia Residents File RICO Suit Against OpenAI Over 3.2GW Project Camellia

November 12, 2026 Georgia

Three residents of Effingham County, Georgia, sued OpenAI and county officials on Nov. 6 over a 3.2-gigawatt data center project. The 44-page complaint, filed in Effingham County State Court, seeks compensatory and punitive damages and three times actual damages from the defendants named in its...

Read more
Read Dade County Approves 90-Day Data Center Moratorium After 300MW Proposal
Dade County commissioners in Georgia approved a 90-day moratorium on new data center development after an Atlanta company explored a 300-megawatt project there. The [Chattanooga Times Free Press](h...

Dade County Approves 90-Day Data Center Moratorium After 300MW Proposal

November 10, 2026 Georgia

Dade County commissioners in Georgia approved a 90-day moratorium on new data center development after an Atlanta company explored a 300-megawatt project there. The Chattanooga Times Free Press reported that the board acted unanimously on Nov. 5 and that the pause gives officials time to draft...

Read more
Read OpenAI Rebrands Data Centers as Compute Campuses After Midterm Rebuke
[OpenAI](https://baxtel.com/data-centers/openai) is now calling its data centers compute campuses, a change that arrived with a policy package published two days after the midterms. The company rel...

OpenAI Rebrands Data Centers as Compute Campuses After Midterm Rebuke

November 04, 2026 Georgia

OpenAI is now calling its data centers compute campuses, a change that arrived with a policy package published two days after the midterms. The company released a National Community Compact and a Compute Campus Policy Blueprint on Nov. 5. The compact covers future campuses that OpenAI owns and...

Read more
Read OpenAI Seeks Permit To Fill 72 Acres Of Wetlands At Project Camellia
OpenAI has applied for a federal permit to fill 72 acres of wetlands at its Project Camellia data center campus in Georgia. The U.S. Army Corps of Engineers' Savannah District is taking public comm...

OpenAI Seeks Permit To Fill 72 Acres Of Wetlands At Project Camellia

October 26, 2026 Georgia

OpenAI has applied for a federal permit to fill 72 acres of wetlands at its Project Camellia data center campus in Georgia. The U.S. Army Corps of Engineers' Savannah District is taking public comments on the application through Nov. 4, the Savannah Morning News reported. The campus is...

Read more
Read Five-Building Data Center Planned in Metter, Georgia
A five-building data center campus has been proposed in Georgia.
Canoochee River RV Resort, LLC has filed an application with the Georgia Department of Community Affairs for the proposed Canoochee...

Five-Building Data Center Planned in Metter, Georgia

October 12, 2026 Georgia

A five-building data center campus has been proposed in Georgia. Canoochee River RV Resort, LLC has filed an application with the Georgia Department of Community Affairs for the proposed Canoochee River RV Resort Data Center Project. The development is planned for a 470-acre site at 2700 Airport...

Read more
Read Gigawatt-Scale Data Centre Campus Planned Near Atlanta, Georgia
A gigawatt-scale data centre campus is planned near Atlanta, Georgia. Developer Stillwater Development has filed a Development of Regional Impact application for the Stillwater Technology Park in L...

Gigawatt-Scale Data Centre Campus Planned Near Atlanta, Georgia

July 27, 2026 Georgia

A gigawatt-scale data centre campus is planned near Atlanta, Georgia. Developer Stillwater Development has filed a Development of Regional Impact application for the Stillwater Technology Park in Lovejoy, around 25 miles (40km) south of downtown Atlanta. The proposed campus at 11760 Panhandle...

Read more
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.