Western Hospitality: New Carlisle

Latest Podcast 52505 Spruce Rd
Withdrawn
Project cancelled before construction

Western Hospitality: New Carlisle

Lot Size: 1,057 acres

In December 2025, the St. Joseph County Council officially cancelled the proposal for a massive $12 billion data center campus in New Carlisle, Indiana. Following a marathon 10-hour public hearing, the council voted 7-2 to deny the necessary rezoning of more than 1,000 acres of prime farmland along Chicago Trail.

The ambitious plan called for the construction of 14 industrial shells, each roughly the size of a football stadium, with an estimated power capacity exceeding 1 gigawatt.

The project, led by Western Hospitality Partners, was defeated due to overwhelming community opposition focused on the depletion of the Kankakee Aquifer, potential spikes in energy costs, and the desire to preserve the rural, agricultural character of the town.

Map and Nearby Locations

52505 Spruce Rd
Western Hospitality Partners Sites
Nearby Facilities

Sites within 15 miles of Western Hospitality: New Carlisle

Distance Site About
2.29 miles Park PlusInterested in this information?Contact us
This facility is part of Amazon's New Carlisle I Campus in Indiana.
2.33 miles Central ParkInterested in this information?Contact us
This facility is part of Amazon's New Carlisle I Campus in Indiana.
2.34 miles Global CampusInterested in this information?Contact us
Amazon AWS is building a $11bn data center campus in Indiana. Amazon acquired more than 600 acres of agricultural land around New Carlisle in St. Joseph County in 2023 using the shell company Razor5.
2.35 miles PrimeInterested in this information?Contact us
This facility is part of Amazon's New Carlisle I Campus in Indiana.
2.36 miles Plaza ThreeInterested in this information?Contact us
This facility is part of Amazon's New Carlisle I Campus in Indiana.
2.39 miles SouthInterested in this information?Contact us
This facility is part of Amazon's New Carlisle I Campus in Indiana.
2.41 miles Ridge PlusInterested in this information?Contact us
This facility is part of Amazon's New Carlisle I Campus in Indiana.
3.55 miles Hub ThreeInterested in this information?Contact us
Amazon AWS is building $11 billion data center campuses in Indiana. The company plans to build up to 30 buildings on different campuses. New Carlisle II is the second campus of Amazon in New Carlisle, Indiana.
3.65 miles Plaza MaxInterested in this information?Contact us
This facility is part of Amazon's New Carlisle II Campus in Indiana.
3.66 miles RidgeInterested in this information?Contact us
This facility is part of Amazon's New Carlisle II Campus in Indiana.
3.68 miles North HubInterested in this information?Contact us
This facility is part of Amazon's New Carlisle II Campus in Indiana.
3.73 miles East ParkInterested in this information?Contact us
This facility is part of Amazon's New Carlisle II Campus in Indiana.
3.75 miles Core CampusInterested in this information?Contact us
This facility is part of Amazon's New Carlisle II Campus in Indiana.
3.78 miles Global CenterInterested in this information?Contact us
This facility is part of Amazon's New Carlisle II Campus in Indiana.
3.84 miles PrimeInterested in this information?Contact us
This facility is part of Amazon's New Carlisle II Campus in Indiana.
3.90 miles PrimeInterested in this information?Contact us
This facility is part of Amazon's New Carlisle II Campus in Indiana.
4.04 miles South StationInterested in this information?Contact us
This facility will be part of Amazon's New Carlisle II Campus in Indiana.
4.13 miles Point BetaInterested in this information?Contact us
This facility will be part of Amazon's New Carlisle II Campus in Indiana.
4.17 miles East CampusInterested in this information?Contact us
This facility will be part of Amazon's New Carlisle II Campus in Indiana.
4.27 miles Point OneInterested in this information?Contact us
This facility will be part of Amazon's New Carlisle II Campus in Indiana.
4.30 miles Global StationInterested in this information?Contact us
This facility will be part of Amazon's New Carlisle II Campus in Indiana.
4.40 miles Valley MaxInterested in this information?Contact us
This facility will be part of Amazon's New Carlisle II Campus in Indiana.
8.10 miles CyrusOne Indiana - Blackthorn
11.00 miles Western Hospitality: South Bend Campus
Western Hospitality Partners is moving forward with a 300-acre, 10-shell data center campus in South Bend.
12.49 miles 1547 CSR: SBIN1
Fifteenfortyseven Critical Systems Realty (1547) and Harrison Street have acquired a carrier hotel data center located in Union Station, South Bend, Indiana.
12.49 miles US Signal South Bend
This is one of two data centers in Indiana for US Signal
12.67 miles Lumen South Bend 1
12.90 miles CyrusOne Indiana - Monroe
13.10 miles Metro CenterInterested in this information?Contact us
This facility is part of Microsoft's La Porte campus in Indiana.
13.21 miles South CenterInterested in this information?Contact us
This facility is part of Microsoft's La Porte campus in Indiana.
13.23 miles Core HubInterested in this information?Contact us
This facility is part of Microsoft's La Porte campus in Indiana.
13.31 miles Campus PlusInterested in this information?Contact us
This facility is part of Microsoft's La Porte campus in Indiana.
13.33 miles Central PlazaInterested in this information?Contact us
This facility is part of Microsoft's La Porte campus in Indiana.
13.41 miles Edge TowerInterested in this information?Contact us
This facility is part of Microsoft's La Porte campus in Indiana.
13.43 miles Park MaxInterested in this information?Contact us
This facility is part of Microsoft's La Porte campus in Indiana.
13.43 miles South CampusInterested in this information?Contact us
This facility is part of Microsoft's La Porte campus in Indiana.
13.52 miles PrimeInterested in this information?Contact us
This facility is part of Microsoft's La Porte campus in Indiana.
13.66 miles SouthInterested in this information?Contact us
This facility is part of Microsoft's La Porte campus in Indiana.
13.89 miles Center PlusInterested in this information?Contact us
This facility is part of Microsoft's La Porte campus in Indiana.
14.24 miles ThreeInterested in this information?Contact us
This facility is part of Microsoft's La Porte campus in Indiana.
14.24 miles Cloud ParkInterested in this information?Contact us
Microsoft is preparing the first data center building at its La Porte campus, with site grading underway and vertical construction scheduled to follow. The facility is planned as the first completed structure in the six-building initial phase.
14.30 miles Central CampusInterested in this information?Contact us
This facility is part of Microsoft's La Porte campus in Indiana.
14.39 miles Hub MaxInterested in this information?Contact us
This facility is part of Microsoft's La Porte campus in Indiana.
14.42 miles PlusInterested in this information?Contact us
Microsoft plans to develop the second data center in the initial La Porte construction sequence. The building is included in the active site-development program and is scheduled for completion shortly after Building 1.
14.56 miles Hub PlusInterested in this information?Contact us
Microsoft is preparing a third data center building within the first La Porte development program. The facility is planned as the last of the initial three buildings to be completed.
18.33 miles South PointInterested in this information?Contact us
Phoenix Investors, the Milwaukee-headquartered industrial real-estate firm, is redeveloping the former ANCO windshield-wiper plant into a 70-acre, grid-connected data-center campus.
18.35 miles Prime PointInterested in this information?Contact us
Microsoft is seeking to rezone a 40-acre parcel southwest of the Cleveland Road and Currant Road intersection.
18.45 miles Station AlphaInterested in this information?Contact us
This facility is part of Google's Project Maize in Indiana.
18.61 miles West HubInterested in this information?Contact us

Western Hospitality: New Carlisle Data Center Photos See all

Area to be rezoned is shown in crosshatch.
Source: St. Joseph County council

Operating Company

0
Facilities
0
Markets

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?