University of Toledo: Computer Center

Year Built: 2013
░░░░ Request Dataset MW
Operational Power

The University of Toledo's main data center sits in the Computer Center on East Rocket Drive on the main campus. In December 2013 the university opened a green data center there, with four natural-gas microturbines that supply power and act as a hybrid UPS.

Site History

  • In December 2013, the university opened its green data center with four Capstone microturbines.

Map and Nearby Locations

2750 E Rocket Dr
University of Toledo Sites
Nearby Facilities

University of Toledo: Computer Center Power Growth Over Time

+0% since 2022
Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of University of Toledo: Computer Center

Distance Site
3.20 miles Telesystem Toledo
3.45 miles Lumen: Toledo
3.66 miles AT&T: 121 N Huron St, Toledo
4.36 miles CISP Yocolo
5.00 miles Verizon: Sylvania McCord, OH
6.42 miles Verizon: Sylvania, OH
7.11 miles QLevr: Rossford
9.05 miles Vantage: Oregon, Ohio
13.09 miles Valley TwoInterested in this information?Contact us
14.59 miles Amplex: Luckey, OH
18.92 miles Connect Data Centers: Bowling Green
19.55 miles Verizon: Bowling Green, OH

Operating Company

The University of Toledo is a public research university in Toledo, Ohio, founded in 1872. It operates a main campus in west Toledo and a Health Science Campus in south Toledo.

The university's information technology division runs its data center facilities in the Computer Center on the main campus.

0
Facilities
0
Markets

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Quotes
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.