Trusted-Colo: Alsbach-Hähnlein

Latest Podcast Sandwiesenstraße 34
Operational
Fully operational facility
Operated by:

Trusted-Colo: Alsbach-Hähnlein

Year Built: 2020
PUE: 1.2
Ownership: Trusted-Colo owns the building.
░░░ Request Dataset MW
Operational Power

Trusted-Colo built its data center in the commercial area of Alsbach-Hähnlein, beside the A5 between Darmstadt and Heidelberg. It relies on indirect free cooling, feeds each rack on A and B supplies that each have their own generator, and carries a solar array on the roof. Wavelengths and dark fiber run to Frankfurt.

Site History

  • 2023: solar array added on the roof.
  • 2020: the data center is finished and the first customers move in.
  • 2018: construction begins.

Map and Nearby Locations

Sandwiesenstraße 34
Trusted-Colo Sites
Nearby Facilities

Trusted-Colo: Alsbach-Hähnlein Power Growth Over Time

+0% since 2022
Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Trusted-Colo: Alsbach-Hähnlein

Distance Site
5.04 miles Real Estate Data CenterInterested in this information?Contact us
8.79 miles Education Data CenterInterested in this information?Contact us
9.21 miles DARZ: Darmstadt
12.11 miles Vantage: FRA55
12.15 miles Vantage: FRA54
12.17 miles Vantage: FRA53
12.21 miles Vantage: FRA52
12.25 miles Vantage: Frankfurt FRA51
13.22 miles GSI: Green IT Cube, Darmstadt
15.48 miles NTT: Nierstein
16.47 miles Goodman: FRA I Bldg1
16.47 miles Hyperscale Data CenterInterested in this information?Contact us
16.53 miles Hyperscale Data CenterInterested in this information?Contact us
16.53 miles Goodman: FRA I Bldg2
16.61 miles China Mobile Frankfurt
16.83 miles DATIS: Mannheim
17.17 miles NTT Frankfurt 3
17.18 miles Campus BetaInterested in this information?Contact us
17.72 miles Carrier-Neutral Data CenterInterested in this information?Contact us
17.81 miles Mainova: Langen
18.66 miles BASF: Ludwigshafen J650
19.04 miles Education Data CenterInterested in this information?Contact us
19.40 miles VANTAGE: FRA II Bldg 2
19.46 miles Vantage FRA II
19.59 miles Carrier-Neutral Data CenterInterested in this information?Contact us
19.71 miles TWL-KOM: Datacenter II Ludwigshafen
19.75 miles Vantage: FRA31
19.88 miles Vantage: FRA32

Operating Company

Operated by:

Trusted-Colo GmbH & Co. KG is a family business led by Heinz-Dieter and Fabian Elbracht. It sells colocation by the rack unit, rack and cage, with network transport to Frankfurt, from a data center it built itself in the commercial area of Alsbach-Hähnlein.

Trusted-Colo History:

  • In 2023, Trusted-Colo added a solar array to the roof of its data center.
  • In 2020, the data center was finished and the first customers moved in.
  • In 2018, construction began.
  • Founded in 2014.
0
Facilities
0
Markets

News See all

Read Amazon Pledges €16B For Germany In 2027, Including €4.8B For AWS Frankfurt
Amazon plans to invest more than €16 billion ($18 billion) in Germany in 2027, including €4.8 billion to expand the [AWS Europe (Frankfurt) region](https://press.aboutamazon.com/de/2026/10/invest-i...

Amazon Pledges €16B For Germany In 2027, Including €4.8B For AWS Frankfurt

October 21, 2026 Amazon AWS

Amazon plans to invest more than €16 billion ($18 billion) in Germany in 2027, including €4.8 billion to expand the AWS Europe (Frankfurt) region, the company said on Oct. 20. Chancellor Friedrich Merz and federal economy and energy minister Katherina Reiche appeared with Amazon chief global...

Read more
Read Telehouse Adds Sixth Data Center Building To Frankfurt Campus
Telehouse has opened Building N, its sixth data center facility in Frankfurt, Germany, adding 5.4MW of capacity. The four-story facility spans 9,300 sqm (100,104 sq ft), including 2,165 sqm (23,304...

Telehouse Adds Sixth Data Center Building To Frankfurt Campus

September 01, 2026 Frankfurt

Telehouse has opened Building N, its sixth data center facility in Frankfurt, Germany, adding 5.4MW of capacity. The four-story facility spans 9,300 sqm (100,104 sq ft), including 2,165 sqm (23,304 sq ft) of technical space. It uses air cooling, with Telehouse exploring liquid cooling to support...

Read more
Read Mainova Ventures into Data Centers With 30MW Facility in Frankfurt
Baxtel

Mainova Ventures into Data Centers With 30MW Facility in Frankfurt

October 27, 2022 Frankfurt

German energy company Mainova is moving into the data center business. The company broke ground on the new facility in Frankfurt, Germany. Mainova WebHouse, a subsidiary of the energy company, announced that a groundbreaking ceremony for the facility took place earlier in the month. The new data...

Read more
Read Frankfurt: Plans for environmental data center zoning updated
Frankfurt: Plans for environmental data center zoning updated

Frankfurt: Plans for environmental data center zoning updated

August 08, 2022 Frankfurt

Frankfurt recently announced an updated plan for commercial developments in the city, which will place a limitation on cloud and colocation data center buildings. This comes as a response to concerns around their land and energy usage. Alongside this announcement, the city also outlined its...

Read more
Read Alibaba Opens Data Center in Frankfurt, Germany
Baxtel

Alibaba Opens Data Center in Frankfurt, Germany

May 17, 2022 Frankfurt

Alibaba has announced that it opened a data center in Frankfurt, Germany. The new data center is the company’s third facility in the country. According to the company, the new data center will help support the increasing needs for digital transformation from customers across the European...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Quotes
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.