Thor Equities plans the Urbana Technology Hub, a $1 billion data center campus on farmland beside the Rittal factory, southwest of downtown Urbana. The first phase is a single-story building of about 460,000 sq ft with closed-loop cooling, and Thor offered to fund the grid upgrades privately. Thor affiliates began buying the land in August 2025.
The project has stalled in a fight with the city. The zoning board rejected Thor's site plan in February 2026. City council adopted a moratorium in March and repealed the zoning that allowed data centers in June. Thor sued the city in federal court on June 19, 2026, and later offered a $50 million settlement that would cap the campus at 2 million sq ft. On November 3, 2026, Urbana voters approved a ban on data centers larger than 7.5 MW.
Site History
-
November 3, 2026: Urbana voters approve a ban on data centers over 7.5 MW.
-
June 19, 2026: Thor sues the City of Urbana in federal court.
-
June 16, 2026: City council repeals the zoning that allowed data centers.
-
March 3, 2026: City council adopts a data center moratorium.
-
February 2026: The zoning board rejects Thor's site plan.
-
August 2025: A Thor affiliate buys the first parcel.