TeraWulf plans to redevelop the Morgantown Generating Station, a GenOn power plant on the Potomac River, as the Chesapeake Data campus. The plan pairs data center halls with new on-site gas generation and battery storage, so the campus stays a net generator on the PJM grid. TeraWulf targets initial data center operations in 2030.
FERC approved the purchase in July 2026, but other closing conditions remain open. Charles County does not yet permit data centers: in July 2026 the county commissioners withdrew a zoning amendment that would have allowed them. Maryland also reviews large data centers that seek state approvals, under an executive order Gov. Wes Moore signed in September 2026.
Site History
-
November 2026: TeraWulf reported that closing conditions and consents for the purchase remain outstanding.
-
September 2026: Gov. Moore ordered a state task-force review of large data centers that seek state action.
-
August 2026: TeraWulf said initial data center operations are contemplated for 2030.
-
July 2026: FERC approved the sale. Charles County commissioners withdrew the data center zoning amendment.
-
February 2026: TeraWulf announced its agreement to buy the station from GenOn.