Overview
Southwest Finland is the coastal region around Turku in Finland. Its data center market is small, and Elisa's underground Raisio center is the main colocation site. Two large campus plans aim to change that.
The Market Today
atNorth took over developer Regant's project at Kärkkä in Salo in October 2026 and plans its first phase for 2028. Fingrid is adding a second transformer at its Salo substation for the project. In Raisio, the city board reserved land in December 2025 for a campus by ecogrid.energy. That plan depends on a new Fingrid 400 kV line.
Advantages
-
Grid investment. Fingrid is reinforcing its Salo substation for new data center load.
-
Ports and talent. Turku and Naantali ports link the region to Sweden, and Turku's universities supply technical staff.
Challenges
-
Connection limits. Fingrid restricted new main-grid connections here in 2025 until its reinforcements finish.
-
Long timelines. The first large campus phase is not due before 2028.
Power and Policy
Fingrid connects large loads at 110 kV or 400 kV. It expects connection limits in southern Finland to ease in 2027 and 2028.