atNorth: FIN05, Salo

Latest Podcast Merikulmantie
PlannedProspective Expansion
Future facility in planning stagefacility with prospective expansion planned
Operated by:

atNorth: FIN05, Salo

Short Code: FIN05
Year Planned: 2028
Utility Provider: Fingrid Salo substation (second transformer being added); two 110 kV cables
Lot Size: 71 acres

The data center is being developed on a 28.6-hectare site between the former sugar factory and the Salo police station, fronting Merikulmantie. Land, zoning and permitting were secured by Finnish developer Regant Oy, which assembled the site through its project company Regant DC1 Oy and is building the facility for atNorth. The building permit was granted in December 2025 and is now legally final, and the project is proceeding without an environmental impact assessment.

Map and Nearby Locations

Merikulmantie
atNorth Sites
Nearby Facilities

atNorth: FIN05, Salo Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Operating Company

Operated by:

atNorth is a leading Nordic data center services company that offers sustainable, cost-effective, scalable colocation and high-performance computing services trusted by industry-leading organizations.

Advania Data Centers was rebranded as atNorth in late 2020. The business acquired leading High Performance Computing (HPC) provider, Gompute, in 2023 enabling a compelling full stack offering tailored to AI and other critical high performance workloads.

With sustainability at its core, atNorth's data centers run on renewable energy resources and support circular economy principles. All atNorth sites leverage innovative design, power efficiency, and intelligent operations to provide long-term infrastructure and flexible colocation deployments. The tailor-made solutions enable businesses to calculate, simulate, train and visualize data workloads in an efficient, cost-optimized way.

atNorth is headquartered in Reykjavik, Iceland and operates seven data centers in strategic locations across the Nordics, with additional sites to open in Helsinki, Finland in and Ballerup, Denmark in early 2025, as well as its tenth under construction in Kouvola, Finland and its eleventh site in Ølgod, Denmark.

0
Facilities
0
Markets
0MW
Megawatts

News See all

Read CoreWeave Brings 22.5MW Online at atNorth's Copenhagen Data Center
CoreWeave has brought most of its planned 22.5MW of IT capacity online at [atNorth](https://baxtel.com/data-centers/atnorth)'s [DEN01](https://baxtel.com/data-center/atnorth-den01) data center in t...

CoreWeave Brings 22.5MW Online at atNorth's Copenhagen Data Center

October 27, 2026 CoreWeave

CoreWeave has brought most of its planned 22.5MW of IT capacity online at atNorth's DEN01 data center in the Copenhagen metro, its first deployment in Denmark. The company announced the activation from London on October 27. atNorth owns and operates DEN01, a colocation site in Ballerup, Greater...

Read more
Read atNorth Plans 75MW Data Center in Salo, Finland
Nordic data center operator atNorth is expanding its presence in Finland with a new facility in Salo. The FIN05 campus will occupy 28.6 hectares, with 75MW secured for its first phase and expansion...

atNorth Plans 75MW Data Center in Salo, Finland

October 06, 2026 atNorth

Nordic data center operator atNorth is expanding its presence in Finland with a new facility in Salo. The FIN05 campus will occupy 28.6 hectares, with 75MW secured for its first phase and expansion potential of up to 230MW, including 160MW of IT capacity. AtNorth plans to invest €2 billion...

Read more
Read atNorth Plans €2B Salo Data Center With 75MW First Phase, 230MW Path
atNorth will develop a €2 billion data center, FIN05, in Salo, [Finland](https://baxtel.com/regions/finland), on a 28.6-hectare site, with 75 MW of power secured for the first phase and a path to a...

atNorth Plans €2B Salo Data Center With 75MW First Phase, 230MW Path

October 05, 2026 atNorth

atNorth will develop a €2 billion data center, FIN05, in Salo, Finland, on a 28.6-hectare site, with 75 MW of power secured for the first phase and a path to as much as 230 MW. The Nordic operator announced the plan on October 5. Power will arrive through a new Fingrid substation.The first phase...

Read more
Read atNorth Plans 30MW Data Center in Stockholm, Sweden
atNorth Plans 30MW Data Center in Stockholm, Sweden

atNorth Plans 30MW Data Center in Stockholm, Sweden

January 30, 2026 atNorth

Nordic data center firm atNorth is to develop a second data center in Stockholm, Sweden. It plans to build an additional data center in Stockholm, known as SWE02. The site is scheduled to go live in Q4 2027.“The expansion of our presence in Stockholm is a clear reflection of the growing demand...

Read more
Read AlphaTon Leases 2.2MW IT Capacity from atNorth Data Center in Sweden
AlphaTon Leases 2.2MW IT Capacity from atNorth Data Center in Sweden

AlphaTon Leases 2.2MW IT Capacity from atNorth Data Center in Sweden

December 19, 2025 atNorth

AlphaTon Capital Corp has signed a data center leasing agreement for 2.2MW of capacity from atNorth for a data center in Sweden. AlphaTon is a technology company that says it "bridges institutional capital with the Telegram-based crypto ecosystem." However, it seems to be seeking to launch a...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?