Year Planned: 2029

Red Wolf DCD Properties LLC has unveiled plans for Project Splice, a massive $6 billion technology campus in Crisp County, south-central Georgia, just outside Cordele. The proposed "technology campus" will feature multiple buildings, a dedicated substation, and comprehensive utility infrastructure. The expansive project includes seven individual buildings, each measuring 300,000 square feet (27,870 sqm), resulting in a total footprint of 2.1 million square feet (195,096 sqm).

The construction is anticipated to roll out in three stages: Phase I is targeted for completion in 2029, Phase II in 2031, and the final Phase III in 2033.

Map and Nearby Locations

Red Wolf DCD Properties LLC Sites
Nearby Facilities

Red Wolf DCD: Project Splice Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Operating Company

0
Facilities
0
Markets

News See all

Read OpenAI Rebrands Data Centers as Compute Campuses After Midterm Rebuke
[OpenAI](https://baxtel.com/data-centers/openai) is now calling its data centers compute campuses, a change that arrived with a policy package published two days after the midterms. The company rel...

OpenAI Rebrands Data Centers as Compute Campuses After Midterm Rebuke

November 04, 2026 OpenAI

OpenAI is now calling its data centers compute campuses, a change that arrived with a policy package published two days after the midterms. The company released a National Community Compact and a Compute Campus Policy Blueprint on Nov. 5. The compact covers future campuses that OpenAI owns and...

Read more
Read OpenAI Seeks Permit To Fill 72 Acres Of Wetlands At Project Camellia
OpenAI has applied for a federal permit to fill 72 acres of wetlands at its Project Camellia data center campus in Georgia. The U.S. Army Corps of Engineers' Savannah District is taking public comm...

OpenAI Seeks Permit To Fill 72 Acres Of Wetlands At Project Camellia

October 26, 2026 OpenAI

OpenAI has applied for a federal permit to fill 72 acres of wetlands at its Project Camellia data center campus in Georgia. The U.S. Army Corps of Engineers' Savannah District is taking public comments on the application through Nov. 4, the Savannah Morning News reported. The campus is...

Read more
Read Five-Building Data Center Planned in Metter, Georgia
A five-building data center campus has been proposed in Georgia.
Canoochee River RV Resort, LLC has filed an application with the Georgia Department of Community Affairs for the proposed Canoochee...

Five-Building Data Center Planned in Metter, Georgia

October 12, 2026 Georgia

A five-building data center campus has been proposed in Georgia. Canoochee River RV Resort, LLC has filed an application with the Georgia Department of Community Affairs for the proposed Canoochee River RV Resort Data Center Project. The development is planned for a 470-acre site at 2700 Airport...

Read more
Read Gigawatt-Scale Data Centre Campus Planned Near Atlanta, Georgia
A gigawatt-scale data centre campus is planned near Atlanta, Georgia. Developer Stillwater Development has filed a Development of Regional Impact application for the Stillwater Technology Park in L...

Gigawatt-Scale Data Centre Campus Planned Near Atlanta, Georgia

July 27, 2026 Georgia

A gigawatt-scale data centre campus is planned near Atlanta, Georgia. Developer Stillwater Development has filed a Development of Regional Impact application for the Stillwater Technology Park in Lovejoy, around 25 miles (40km) south of downtown Atlanta. The proposed campus at 11760 Panhandle...

Read more
Read Plans Filed for 1.2GW Data Center Campus in Irwin County, Georgia
Plans Filed for 1.2GW Data Center Campus in Irwin County, Georgia

Plans Filed for 1.2GW Data Center Campus in Irwin County, Georgia

April 14, 2026 Georgia

A gigawatt-scale data center campus has been proposed in Georgia. A Development of Regional Impact (DRI) application has been filed with the Georgia Department of Community Affairs for a project in Irwin County, in south-central Georgia. Premier Data Center Development, LLC plans to build a...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.