PNK Group: Wisconsin Rapids

Latest Podcast 950 4th Ave N
Withdrawn
Project cancelled before construction
Operated by:

PNK Group: Wisconsin Rapids

Year Built: 2026
Utility Provider: Consolidated Water Power Co.
Lot Size: 209 acres

PNK Group proposed a data center campus on about 209 acres of the former Verso paper mill in Wisconsin Rapids. The plan reused an existing mill building and added new ones, about 1.2 million square feet in all.

The Plan Commission recommended denial in September 2026. The city adopted a 12-month data center moratorium in October, and the Common Council denied the conditional use permit 7-0 on October 20, 2026.

Site History

  • October 2026: The Common Council denies the conditional use permit.
  • October 2026: Wisconsin Rapids adopts a 12-month data center moratorium.
  • September 2026: The Plan Commission recommends denial.
  • April 2026: The developer applies for a conditional use permit.

Map and Nearby Locations

950 4th Ave N
PNK Group Sites
Nearby Facilities

PNK Group: Wisconsin Rapids Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of PNK Group: Wisconsin Rapids

Distance Site About
1.89 miles DPO: Wisconsin Rapids
Digital Power Optimization (DPO) has officially withdrawn from this project.
4.99 miles Cloudnium: Port Edwards
Cloudnium operates a small colocation data center in Port Edwards, Wisconsin, one of its three campuses alongside Dallas and San Angelo.

Operating Company

Operated by:

PNK Group is a privately held industrial real estate company owned by Andrey Sharkov. Its U.S. business, PNK Group USA, is headquartered in New York City and has operated in the United States since 2017.

The company acts as investor, developer, engineer, manufacturer and general contractor on its own projects. It builds with a proprietary prefabricated system called the Building Assembly Set and produces large building components at its own plants in Georgia and Pennsylvania. Its U.S. portfolio includes industrial parks and build-to-suit sites in Pennsylvania, New Jersey, New York, Connecticut, Virginia, Georgia and Texas. The company reports more than 20 years of experience, with earlier work across Central and Eastern Europe and Central Asia.

PNK Group History:

  • In October 2026, the Wisconsin Rapids Common Council denied the company's conditional use permit for a data center campus at the former paper mill site in Wisconsin Rapids, Wisconsin.
  • In 2026, PNK Group proposed a data center campus on about 210 acres of the former Verso paper mill site in Wisconsin Rapids.
  • In 2022 and 2023, PNK Group opened production facilities in Georgia and Pennsylvania.
  • In 2017, PNK Group began operating in the United States.
0
Facilities
0
Markets

News See all

Read Data Center Development in Wisconsin delayed
Data Center Development in Wisconsin delayed

Data Center Development in Wisconsin delayed

September 26, 2025 Wisconsin

A data center development in Menomonie, Wisconsin, has been delayed. In a meeting on September 22, Mayor Randy Knaack said that he had drafted a memo to developer Balloonist LLC stating that the city was no longer interested in pursuing the project.“I’m not thrilled about the data center coming...

Read more
Read Northwestern Mutual Abandons Franklin, Wisconsin Facility And On-site Data Center
Northwestern Mutual Abandons Franklin, Wisconsin Facility And On-site Data Center

Northwestern Mutual Abandons Franklin, Wisconsin Facility And On-site Data Center

February 22, 2023 Wisconsin

Northwestern Mutual is abandoning its campus in Franklin, Wisconsin, on the outskirts of Milwaukee, as part of a $500 million effort to relocate to an office complex in downtown Milwaukee. Per the Milwaukee Journal Sentinel, this is partially due to the fact that the corporation no longer needs...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.