EdgeConneX SCL04

Latest Podcast Carretera General San Martín 8400
Planned
Future facility in planning stage
Operated by:

EdgeConneX SCL04

Short Code: SCL04
Year Planned: 2029
Lot Size: 16 acres
░░░░░░░ Interested in this information? Contact us SqFt
Total Building Size

SCL04 is the largest planned building on EdgeConneX's Santiago campus in Colina. The new build of about 34,200 m² will hold six data halls plus a two-storey office block.

Site History

  • 2024-07: environmental approval
  • 2023-08: environmental filing

Project Profile

  • Design: chilled-water cooling; N+1 power with diesel generators and 48 hours of fuel
  • Delivery: three construction stages

Map and Nearby Locations

Carretera General San Martín 8400
EdgeConneX Sites
Nearby Facilities

EdgeConneX SCL04 Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of EdgeConneX SCL04

Distance Site
0.06 miles EdgeConneX SCL03
0.09 miles EdgeConneX SCL02
0.32 miles Edgeconnex Santiago SCL01
1.97 miles Scala: Lampa Expansion
2.01 miles ODATA Chile ST01
2.03 miles Scala: SSCLLP01
2.10 miles Scala: SSCLLP02
2.53 miles Ascenty: Santiago 1
2.64 miles Ascenty: Santiago 3
2.69 miles Ascenty: Santiago 2
2.78 miles East RidgeInterested in this information?Contact us
4.05 miles SONDA: Kudos
4.06 miles SONDA Quilicura
4.12 miles Cirion SAN2
4.22 miles OneInterested in this information?Contact us
4.29 miles Claro: Liray
4.50 miles EdgeUno Santiago
4.50 miles Cirion Santiago SAN1
4.99 miles Scala: Huechuraba Expansion
5.06 miles Scala: SSCLHB02
5.07 miles Scala: Huechuraba SSCLHB01
5.85 miles West CenterInterested in this information?Contact us
5.88 miles CenterInterested in this information?Contact us
7.00 miles GTD: Panamericana
8.05 miles IFX: Magnus I
10.05 miles GTD: Lídice II
10.05 miles GTD: Lídice I
10.07 miles SONDA: Teatinos
10.18 miles IFX Phillips
10.27 miles GTD: Huerfanos
10.28 miles GTD: Holanda
10.32 miles Ufinet: Santiago (Barrio El Golf)
10.35 miles IFX: Elbosque
10.46 miles NextStream: San Martin
10.48 miles GTD: Moneda
10.52 miles Equinix: ST3
10.57 miles GTD: Providencia
10.78 miles Equinix: ST5
11.04 miles Ufinet: Santiago (Los Leones)
11.48 miles NextStream: Apoquindo
13.33 miles Equinix: ST2-2
13.34 miles Equinix: ST2-1
13.36 miles Equinix: ST1
15.42 miles Cloud CenterInterested in this information?Contact us
16.08 miles ODATA STO2
17.62 miles Kyndryl: Santiago (San Bernardo)
18.87 miles Global StationInterested in this information?Contact us
18.92 miles GammaInterested in this information?Contact us

Operating Company

Operated by:

EdgeConneX is a data center provider specializing in providing colocation facilities to host content at the edge of the network. The company provide Space, Power & Connectivity for content, network, colocation, CDNs and service providers, as well as wireless carriers, telecommunications companies, and commercial property owners. EdgeConneX has created a new Edge for traditional networks offering superior performance and economics.

0
Facilities
0
Markets

News See all

Read EdgeConneX Proposes twin 730,000 sq ft Data Centers in Bastrop County
EdgeConneX Proposes twin 730,000 sq ft Data Centers in Bastrop County

EdgeConneX Proposes twin 730,000 sq ft Data Centers in Bastrop County

June 03, 2026 EdgeConneX

US operator EdgeConneX has filed plans to construct two 730,000-square-foot (67,820 sqm) data centers in Bastrop County, Texas. Named EDCAUS11 and EDCAUS12, the projects are planned for a 180-acre site at 6682 FM 535 in Cedar Creek, which the company acquired in November 2025. The parcel is...

Read more
Read EdgeConneX Plans a €3 Billion Investment in Data Centers in Italy
EdgeConneX Plans a €3 Billion Investment in Data Centers in Italy

EdgeConneX Plans a €3 Billion Investment in Data Centers in Italy

May 23, 2026 EdgeConneX

The government of Italy has described EdgeConneX’s €3 billion investment as being of “national strategic interest.” The EdgeConneX Campus Italia program, announced on May 14 during a council of ministers chaired by Prime Minister Giorgia Meloni, will develop three data center campuses in the...

Read more
Read EdgeConneX Begins Construction on a New Data Center in Osaka, Japan
EdgeConneX Begins Construction on a New Data Center in Osaka, Japan

EdgeConneX Begins Construction on a New Data Center in Osaka, Japan

March 19, 2026 EdgeConneX

EdgeConneX has begun construction on a new data center outside Osaka, Japan. The company announced this week that it is developing its first 200MW, AI-ready campus in Greater Osaka in partnership with Kagoya Asset Management.The Kyotanabe campus will cover 130,000 sqm (1.4 million sq ft), with...

Read more
Read EdgeConneX Partners with Ral Estate Firm Stockland
EdgeConneX Partners with Ral Estate Firm Stockland

EdgeConneX Partners with Ral Estate Firm Stockland

September 16, 2025 EdgeConneX

ASX-listed real estate firm Stockland announced it had formed an exclusive arrangement with EdgeConneX to establish a partnership to develop, own, and operate a data center portfolio, and was “exploring opportunities across Stockland’s logistics pipeline.”This partnership will combine...

Read more
Read EdgeConneX to Develop Second Facility in Japan
EdgeConneX to Develop Second Facility in Japan

EdgeConneX to Develop Second Facility in Japan

August 28, 2025 EdgeConneX

Data center firm EdgeConneX this week announced the acquisition of its second data center site in the Greater Osaka and Yawata areas of Japan. The new site will provide an additional 150MW upon completion, bringing EdgeConneX's total data center capacity in Japan to 350MW of utility power at...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Quotes
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.