EdgeConneX is building a campus of six data center buildings on the Molandsmoen industrial area in Fyresdal, Telemark, through its Norwegian company EdgeConneX MCN Norway. Fyresdal granted the frame permit in August 2025, and construction started in 2026, with piling for all six buildings and steel up on the first. Statnett has reserved grid capacity for the first phase, and Lede is building a new 132 kV switching station at Molandsmoen; Tnett supplies interim power. EdgeConneX expects the first building in 2027 and the last in 2029. The campus still needs NVE's licence for its own transformer station and an emission permit for its backup generators.
Site History
- 2026: Construction started.
- Late 2025: EdgeConneX bought the site.
- August 2025: Fyresdal granted the frame permit for six buildings.