Applied Digital: PF3 Bldg1

Under Construction
New facility under construction
Operated by:

Applied Digital: PF3 Bldg1

Short Code: Building 1
Year Planned: 2027
Utility Provider: Montana-Dakota Utilities
Lot Size: 640 acres

PF3 Bldg1 is building 1 of 2 on Applied Digital's Polaris Forge 3 AI campus, on farmland between Hannover and Center in Oliver County. Applied Digital leased both buildings to a high investment-grade U.S. hyperscaler under two 15-year leases in May 2026 and reports both under construction. It expects initial operations in the second half of 2027 and full capacity in the second half of 2028.

A new 345 kV switching substation on the property will take service from the transmission line along its north edge. Roughrider Electric Cooperative has protested the service filings at the North Dakota Public Service Commission. County conditions bar wastewater discharge into the aquifer, require cooling water to be trucked in at first, and limit generator testing to daytime hours.

Site History

  • October 2026: Applied Digital reports both buildings under construction and signs a 15-year power purchase agreement with Base Electron for a planned gas plant in Center.
  • September 2026: Roughrider Electric Cooperative protests the utility service filings and asks for a hearing.
  • July 2026: Oliver County approves the building permit and signs a road use agreement with the Applied Digital subsidiary.
  • June 2026: Applied Digital signs an electric service agreement for the campus, subject to state approval.
  • May 2026: Applied Digital signs two 15-year leases with a high investment-grade hyperscaler and applies to rezone the farmland for industrial use.
  • April 2026: Oliver County repeals its 180-day data center moratorium.

Map and Nearby Locations

Applied Digital Sites
Nearby Facilities

Applied Digital: PF3 Bldg1 Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Applied Digital: PF3 Bldg1

Distance Site
0.42 miles Applied Digital: PF3 Bldg2

Operating Company

Operated by:

Applied Digital (APLD) is a U.S.-based operator of next-generation digital infrastructure, providing solutions to the fields of High-Performance Computing (HPC) and Artificial Intelligence (AI). APLD has two business segments: next-generation datacenter colocation services and AI GPU cloud services (under Sai Computing).

History:

  • In May 2023, it formed a new subsidiary called Sai Computing to provide cloud service for AI compute customers
  • In April 2022, the company rebranded to Applied Digital from Applied Blockchain
0
Facilities
0
Markets

News See all

Read ChronoScale Takes 50% Stake In STN's 350MW Odessa AI Campus
ChronoScale Holdings is taking a 50% stake in STN's AI data center campus in Odessa, Texas, under a development partnership announced Nov. 18. Each company will contribute $390 million in value to ...

ChronoScale Takes 50% Stake In STN's 350MW Odessa AI Campus

November 19, 2026 STN

ChronoScale Holdings is taking a 50% stake in STN's AI data center campus in Odessa, Texas, under a development partnership announced Nov. 18. Each company will contribute $390 million in value to the 50/50 venture, which is planned to house compute for an unnamed frontier AI lab across three...

Read more
Read Applied Digital Plans 1GW Data Center Campus in Finland
Applied Digital is expanding into Europe with plans for a 1GW-scale data center campus in Finland.The Nasdaq-listed company has secured access to up to 1GW of potential power capacity, with initial...

Applied Digital Plans 1GW Data Center Campus in Finland

October 07, 2026 Applied Digital

Applied Digital is expanding into Europe with plans for a 1GW-scale data center campus in Finland.The Nasdaq-listed company has secured access to up to 1GW of potential power capacity, with initial availability expected from 2028. The project is Applied Digital’s first outside the US. Details...

Read more
Read Applied Digital Secures 1 GW Of Finnish Power For First Campus Outside US
[Applied Digital](https://baxtel.com/data-centers/applied-digital) (NASDAQ: APLD) has secured access to as much as 1 GW of potential power capacity in Finland, its first development opportunity out...

Applied Digital Secures 1 GW Of Finnish Power For First Campus Outside US

October 06, 2026 Applied Digital

Applied Digital (NASDAQ: APLD) has secured access to as much as 1 GW of potential power capacity in Finland, its first development opportunity outside the United States, the Dallas-based AI data center developer said on October 6. The planned AI Factory campus can scale to 1 GW, with initial...

Read more
Read Applied Digital Adds 75MW to Ellendale Data Center Campus in North Dakota
Applied Digital has completed the second phase of Building 2 at its Polaris Forge 1 campus in Ellendale, North Dakota, adding 75MW of IT capacity across three 25MW data halls. The 150MW Building 2 ...

Applied Digital Adds 75MW to Ellendale Data Center Campus in North Dakota

October 05, 2026 Applied Digital

Applied Digital has completed the second phase of Building 2 at its Polaris Forge 1 campus in Ellendale, North Dakota, adding 75MW of IT capacity across three 25MW data halls. The 150MW Building 2 is now fully operational, bringing the campus to 250MW. The site is fully leased to CoreWeave and is...

Read more
Read Applied Digital Picks Brookwood, Alabama For $3.2bn, 210MW Delta Forge 2 Campus
Applied Digital has confirmed Brookwood, Alabama, as the location of Delta Forge 2, its fifth AI Factory campus. The $3.2 billion project in Tuscaloosa County will deliver 210MW of critical IT load...

Applied Digital Picks Brookwood, Alabama For $3.2bn, 210MW Delta Forge 2 Campus

September 26, 2026 Applied Digital

Applied Digital has confirmed Brookwood, Alabama, as the location of Delta Forge 2, its fifth AI Factory campus. The $3.2 billion project in Tuscaloosa County will deliver 210MW of critical IT load under a long-term lease with a US-based, investment-grade hyperscaler. Operations are targeted for...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.