ChronoScale Holdings is taking a 50% stake in STN's AI data center campus in Odessa, Texas, under a development partnership announced Nov. 18. Each company will contribute $390 million in value to the 50/50 venture, which is plFeatured: Editorial photograph illustrating the planned ChronoScale and STN AI computing campus in Odessa.anned to house compute for an unnamed frontier AI lab across three phases of up to 350 megawatts. ChronoScale, based in Menlo Park, California, described the agreement in a Nov. 18 statement.
STN, a Pleasanton, California developer of AI data centers, built the Odessa campus and leads its construction. ChronoScale manages the partnership and supplies the compute, while the frontier AI lab is the customer. STN announced its side of the deal in a separate release the same day. The partnership and an up-to-$750 million financing are expected to close Nov. 18, subject to antitrust clearance.
The unnamed customer has ordered the first 65 megawatts, scheduled for deployment in the first half of 2027. ChronoScale holds a right of first offer on the remaining 285 megawatts if the second and third phases are ordered. The agreement carries a total contract value of up to $7.5 billion over six years, or about $20.8 million in annual revenue per megawatt on a blended basis. The release says a substantial portion of the first phase is backstopped by credit support from an investment-grade technology company.
The financing consists of $250 million in equity and up to $500 million in convertible preferred stock with a minimum conversion price of $12 a share, which ChronoScale may draw over four years. Four strategic investors are taking part: a leading frontier AI lab, Nutanix, Empery Digital Inc., and a storage infrastructure company. Goldman Sachs is the lead placement agent.
Construction at the Odessa campus began in May 2026 on a former industrial site in Ector County. STN placed its first factory-built Elemental Data Center on June 11 and commissioned it on July 31. That unit is designed for 2 megawatts and 1,024 Nvidia Blackwell Ultra B300 GPUs. The campus uses on-site power generation and battery storage alongside a utility connection, and sealed, closed-loop cooling with no process water discharge, STN says.
"The companies building frontier AI need infrastructure that can responsibly deliver at scale and on schedule," said Sabur Mian, founder and CEO of STN. "We've built our business around meeting that demand by controlling the land, power and data centers needed to support advanced AI computing."
"We continue to see frontier AI moving beyond incremental compute expansion toward infrastructure commitments measured in hundreds of megawatts," said Cenly Chen, chief executive of ChronoScale.
ChronoScale was formed by combining Applied Digital's cloud business with Ekso Bionics, and the spin-out closed on May 5, 2026, Data Center Dynamics reported. Baxtel tracks 81 data centers in the Permian Basin, operated by 39 providers, and lists STN's Project Landman site at 400 megawatts of tracked capacity in Odessa.