DC12 is building 1C in the second phase of Amazon Web Services' south New Carlisle campus, one of 14 buildings planned on the land south of the first nine. The layout mixes single-story and two-story buildings, and Amazon has said the final count can change. Site work and permitting started in 2026. The county expects building construction to make little progress before spring 2027.
Site History
-
November 2026: Amazon prepares to start construction on the final phase. Site work and permitting are under way.
-
July 2026: Indiana holds a public hearing on Amazon's refiled wetlands permit for the phase.
-
August 2025: Amazon withdraws its first wetlands application after a contractor filled about an acre of wetland without a permit.
-
January 2025: Amazon applies to fill wetlands for a 14-building layout.
-
March 2024: The county council rezones about 640 acres for the south campus.