A2A plans a data center on about 4 hectares of the former railway yard in Cassano d'Adda, beside its gas-fired power station. The site would take power directly from the combined-cycle plant, with the station's existing gas peakers as backup. The design targets AI workloads and modular densification. A2A has a preliminary agreement to buy the land but does not yet own it. It plans a design study, about a year of permitting and 12 to 18 months of construction.

Site History

  • 2026-09: A2A presents the project to Cassano d'Adda's town council.
  • 2026-07: A2A lists Cassano as its second data center project, targeting operation in 2028.
  • 2026-05: Cassano's mayor says A2A's interest is preliminary, with no defined project.

Map and Nearby Locations

Ex scalo ferroviario
A2A Sites
Nearby Facilities

A2A: Cassano d'Adda Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of A2A: Cassano d'Adda

Distance Site About
2.93 miles Echelon: LIN10 Bldg-2
LIN10 Bldg-2 is a proposed second, larger data center building on Echelon's LIN10 campus in Treviglio, east of Milan.
3.03 miles Echelon: LIN10 Bldg-1
LIN10 Bldg-1 is the first phase of Echelon's LIN10 campus, a planned conversion of a former printing plant at Via della Costa 2, Treviglio.
3.41 miles Real Estate Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
4.74 miles Stack: MIL09A
MIL09 is STACK's planned single-building data center campus in Melzo, east of Milan, on a former printing plant site.
5.07 miles Stack: MIL06A
MIL06A is the larger of two buildings on STACK's MIL06 campus in Liscate, east of Milan.
5.10 miles Stack: MIL10
MIL10 is a STACK data center campus planned in Liscate, east of Milan.
5.12 miles Stack: MIL06B
MIL06B is the smaller of two buildings on STACK's MIL06 campus in Liscate, east of Milan.
6.20 miles Vitali: Arcene Innovation Hub
The Vitali group plans a data center on farmland between the railway halt and the Terna substation in Arcene, south of Bergamo.
6.57 miles Stack: MIL05A
MIL05A is the larger of two buildings on STACK's MIL05 campus in Vignate, east of Milan.
6.73 miles Stack: MIL05B
MIL05B is the smaller of two buildings on STACK's MIL05 campus in Vignate, east of Milan.
7.55 miles Noovle: Cassina de' Pecchi
Noovle's Milano Est data center in Cassina de' Pecchi, east of Milan, hosts one of the zones of Google Cloud's Milan region.
7.55 miles TI Sparkle: Milan Cassina de' Pecchi
Sparkle's Milan data center sits on TIM's Malpaga campus at Cassina de' Pecchi, east of Milan, and hosts its international network node and colocation.
7.56 miles Tower UltraInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
8.27 miles ProInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
8.32 miles Prime CampusInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
8.57 miles Real Estate Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
10.11 miles North ParkInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
10.48 miles QTS: Vimercate, Milan
QTS plans a three-building data center campus on the former IBM plant in Vimercate, north-east of Milan.
11.74 miles CyrusOne: Milan MIL1
CyrusOne is building MIL1, its first Italian data center, on the former CISE research site at Via Reggio Emilia in Segrate, east of Milan.
12.08 miles CyrusOne: MIL2
CyrusOne is expanding its presence in Milan, Italy, with a second data center.
12.60 miles Equinix Milan ML4
Former Telecity data center in Milan's Cascia area that Equinix acquired in January 2016. Equinix closed ML4 in the fourth quarter of 2022.
12.65 miles Greenfield: Milan
UK infrastructure developer Greenfield has partnered with Irish specialist investor Finsbury Infrastructure to construct a €360 million ($418 million) data center east of Milan, Italy.
13.07 miles Carrier-Neutral Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
13.32 miles Real Estate Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
13.59 miles Aruba: IT3 DC-B
13.59 miles Aruba: IT3 DC-D
DC-D is the fourth building on Aruba's IT3 campus in Ponte San Pietro, under construction in the last unconverted Legler mill shed (about 15,000 m²) at the south-west of the site.
13.72 miles Aruba: IT3 DC-C
13.73 miles Retelit: Bergamo
Retelit runs a small data center in the Centro Galassia business park on Via Bellafino in Bergamo.
13.78 miles Aruba: IT3 DC-A
First data center on Aruba's IT3 campus in Ponte San Pietro: a converted Legler mill shed at the north end of the site with 10 data rooms, groundwater cooling and rooftop solar.
13.90 miles Aruba: IT3 DC-E
DC-E was a fifth data center building that Aruba planned for its IT3 campus in Ponte San Pietro. Aruba dropped it, and the campus's approved final layout has four data center buildings.
14.65 miles Carrier-Neutral Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
14.66 miles Vantage: MXP13
MXP13 is one of four data centers on Vantage's MXP1 campus in Melegnano, south-east of Milan, in the campus's first building.
14.67 miles Vantage: MXP11
Once fully developed, the MXP1 campus will offer 517,000 square foot (48,000 square meters) of data center space with 300W/SF (3.2kW/M²) average density.
14.73 miles Vantage: MXP14
MXP14 is one of four data centers on Vantage's MXP1 campus in Melegnano, south-east of Milan, in the campus's second building.
14.75 miles Vantage: MXP12
MXP12 is one of four data centers on Vantage's MXP1 campus in Melegnano, south-east of Milan, in the campus's second building.
14.75 miles NTT: Milan
NTT DATA plans a data center on the former San Carlo plot beside the A1 motorway in Melegnano, south-east of Milan.
15.59 miles Real Estate Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
15.66 miles Carrier-Neutral Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
15.66 miles Poste Italiane: Lombardy
Poste Italiane plans an AI data center in Lombardy for model training and inference, on land it says it has already identified.
15.76 miles Unidata: Milan
This facility became part of Unidata's infrastructure portfolio following its 100% acquisition of the TWT Group, which was agreed upon in November 2022 and finalized in February 2023.
15.84 miles Templus: Milan MIL01
Templus MIL01 is a carrier-neutral colocation data center on Viale Vincenzo Lancetti in north Milan, built by Colt and later run by AtlasEdge.
16.78 miles Fastweb: Milan Caracciolo
Fastweb's Tier IV data center on Via Francesco Caracciolo in north-west Milan opened in 2015.
17.25 miles Level3 Milan (Via Tortona)
Former Global Crossing carrier facility at Via Tortona 35 in Milan, later part of Level 3 and Lumen. The complex has since been redeveloped as a hotel, offices and showrooms.
17.60 miles hscale: MXP2 Bldg3
This facility is part of hscale's MXP2 Campus in Milan.
17.63 miles hscale: MXP2 Bldg2
This facility is part of hscale's MXP2 Campus in Milan.
17.65 miles hscale: MXP2 Bldg1
hscale's MXP2 is a planned three-building, AI-ready data center campus in Bollate, north-west of Milan.
17.82 miles EdgeConneX: Milan 01
EdgeConneX plans a data center on a disused transport depot at Via Vigentina 2 in Opera, south of Milan.
17.92 miles Equinix Milan ML2
The site was a Telecity managed datacenter before Equinix acquired Telecity in January 2016.
18.18 miles EdgeConneX: Milan 02
EdgeConneX plans a data center at Fizzonasco in Pieve Emanuele, south of Milan, as part of EdgeConneX Campus Italia.
18.83 miles Noovle: Rozzano DC4
Rozzano DC4 is the newest data center on the TIM Group's Rozzano campus south of Milan, and its only LEED Platinum data center.
18.84 miles Noovle: Rozzano Campus
The TIM Group's Rozzano campus south of Milan holds five Noovle data centers; this site covers DC1, DC2, DC3 and Rozzano 5.
18.87 miles Content Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
18.95 miles Carrier Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
19.16 miles Stack: MIL03A
STACK's MIL03A is a single-building data center in Siziano, south of Milan, between its MIL01 and MIL08 campuses.
19.18 miles Retelit: Avalon 3
A carrier-neutral, Tier IV-designed colocation data center within Retelit's virtualized Milan campus.
19.23 miles Keppel Milan
Keppel DC REIT owns this freehold data center on Via Bisceglie in west Milan, leased in full to a single telecommunications operator.
19.23 miles Stack: MIL01C
STACK's MIL01C is the smallest of three buildings on the MIL01 campus in Siziano, south of Milan, with solar panels on its roof. STACK built it from 2023.
19.31 miles Vaultica: Siziano MIL01
Vaultica sells carrier-neutral enterprise colocation on STACK's MIL01 campus in Siziano, south of Milan. The business was part of STACK until Apollo-managed funds bought it in 2025.
19.31 miles Stack: MIL01A
STACK's MIL01A is the first building on the MIL01 campus in Siziano, south of Milan. SUPERNAP Italia opened it in 2016 and it became STACK in 2022. Vaultica also sells colocation on the campus.
19.33 miles Stack: MIL07
MIL07 is a planned STACK data center in Siziano, south of Milan, near STACK's MIL01 campus.
19.36 miles Stack: MIL08B
STACK's MIL08B is the smaller of two buildings on its MIL08 campus in Siziano, south of Milan, near the MIL01 campus.
19.39 miles Stack: MIL01B
STACK's MIL01B is the second building on the MIL01 campus in Siziano, south of Milan, with two independent data halls. SUPERNAP Italia completed it in 2021 and it became STACK in 2022.
19.42 miles Stack: MIL08A
MIL08A is the larger of two buildings on STACK's MIL08 campus in Siziano, south of Milan.
19.49 miles Rai Way: Milan
Rai Way's Milan edge data center sits in the former RAI Siziano medium-wave transmitter centre in Lacchiarella, south of Milan.
19.52 miles Seeweb: Milan Caldera
Seeweb's Milan data center occupies about 1,000 m² in Building B of the Caldera business park in west Milan.
19.54 miles STACK: MIL02A
Stack Infrastructure's MIL02A data center sits adjacent to the MIL01 campus and is served by 100% renewable power. This is Stack's third data center in Siziano.
19.55 miles Fastweb: Milan Lorenteggio
Fastweb + Vodafone runs a data center in a building on Via Kuliscioff in south-west Milan, first built for Omnitel in 1997.
19.56 miles EXA: Edge DC Milan
EXA Edge DC Milan is a small network edge facility in the Caldera business park in west Milan, formerly run by Interoute and GTT.
19.59 miles Telnet: Milan Caldera
Telnet runs a data center room in Building F (Easy Point) of the Caldera business park in west Milan.
19.60 miles Retelit: Avalon 1 Milan
A carrier-neutral network hub and colocation facility located within the Caldera Business Park in Milan, serving as the core connectivity point for the virtualized Avalon Campus.
19.62 miles MIX: Milan Caldera
MIX, Italy's main internet exchange, runs its own data center in Building D of the Caldera business park in west Milan.
19.65 miles CDLAN C21 Milan
C21 is CDLAN's Tier IV compliant data center in Milan's Caldera Park, paired with its E100 site in Rome.

Operating Company

Operated by:

A2A S.p.A. is a public company listed on Euronext Milan under the ticker A2A and a member of the FTSE MIB index. The municipalities of Milan and Brescia each hold 25% of its shares. It was formed on 1 January 2008 through the merger of AEM of Milan and ASM of Brescia, and its registered office is at Via Lamarmora 230 in Brescia. Renato Mazzoncini is CEO, and the group reported revenue of €14.06 billion in 2025.

A2A, branded A2A Life Company, generates and sells electricity and gas and runs electricity and gas networks, district heating, water services and waste collection and treatment, mainly in northern Italy. Its November 2025 strategic plan update set out a data center platform that develops sites next to its own power plants. Its first two projects are in Brescia, connected to its waste-to-energy plant, and in Cassano d'Adda, connected to its gas-fired power station.

A2A History:

  • In July 2026, A2A said it had secured the sites for its first two data center projects and was starting the permitting process.
  • In July 2026, A2A and Equinix agreed to recover heat from Equinix's Settimo Milanese campus for Milan's district heating network.
  • In November 2025, A2A added a data center development platform to its strategic plan to 2035.
  • Founded in 2008 in Brescia.
0
Facilities
0
Markets

News See all

Read CBRE Forecasts Milan Will Add 255MW and Pass Dublin as Europe's Fifth Market
CBRE forecasts 255MW of new data center capacity in Milan by 2028, which would move the city ahead of Dublin as Europe's fifth-largest market. The forecast appears in CBRE's [Q3 2026 European Data ...

CBRE Forecasts Milan Will Add 255MW and Pass Dublin as Europe's Fifth Market

November 17, 2026 Milan

CBRE forecasts 255MW of new data center capacity in Milan by 2028, which would move the city ahead of Dublin as Europe's fifth-largest market. The forecast appears in CBRE's Q3 2026 European Data Centres report, which puts Milan and Dublin about 100MW of operational capacity apart at the...

Read more
Read Milan Data Center Protest Draws Over 1,000 As Lombardy Plans Stricter Law
More than 1,000 people gathered in Piazza della Scala in Milan on Oct. 10 to oppose new data center construction in Lombardy, [Il Giorno](https://www.ilgiorno.it/milano/cronaca/data-center-protesta...

Milan Data Center Protest Draws Over 1,000 As Lombardy Plans Stricter Law

November 10, 2026 Milan

More than 1,000 people gathered in Piazza della Scala in Milan on Oct. 10 to oppose new data center construction in Lombardy, Il Giorno reported. The rally was the first national demonstration called by the National Network of Stop Data Center Committees. Organizers want the national government...

Read more
Read Greenfield And Finsbury Infrastructure To Invest €360M In Milan Data Center
UK infrastructure developer Greenfield and Finsbury Infrastructure plan to invest up to €360 million ($418m) to develop a 36MW data center east of Milan, Italy. Greenfield has already secured 80MW ...

Greenfield And Finsbury Infrastructure To Invest €360M In Milan Data Center

September 08, 2026 Milan

UK infrastructure developer Greenfield and Finsbury Infrastructure plan to invest up to €360 million ($418m) to develop a 36MW data center east of Milan, Italy. Greenfield has already secured 80MW of power capacity for the site, which will support AI, cloud, and enterprise workloads while...

Read more
Read Magnora Secures Milan-Area Land for 30 MW Data Center, Its Second Italy Project
Magnora Secures Milan-Area Land for 30 MW Data Center, Its Second Italy Project

Magnora Secures Milan-Area Land for 30 MW Data Center, Its Second Italy Project

May 18, 2026 Magnora

Norwegian renewables and data center developer Magnora ASA has secured land for a new 30 MW data center project in the Milan area, the company announced on Monday. The wholly owned project is Magnora's second in Italy and brings its data center development portfolio to 585 MW gross and 460 MW...

Read more
Read Irideos is expanding its Avalon campus in Milan
Irideos is expanding its Avalon campus in Milan

Irideos is expanding its Avalon campus in Milan

October 01, 2021 Milan

Italian data center company Irideos has begun work on a new data center at its Avalon campus in the city of Milan. The new facility named Avalon 3 will have space for 500 racks across 37,700 square feet (3,500 square meters). It will also have 3.2MW of capacity. Irideos is building the new data...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Quotes
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.