CBRE forecasts 255MW of new data center capacity in Milan by 2028, which would move the city ahead of Dublin as Europe's fifth-largest market. The forecast appears in CBRE's [Q3 2026 European Data ...

CBRE Forecasts Milan Will Add 255MW and Pass Dublin as Europe's Fifth Market

Abdul-Rahman Oladimeji

Abdul-Rahman Oladimeji

November 17, 2026

CBRE forecasts 255MW of new data center capacity in Milan by 2028, which would move the city ahead of Dublin as Europe's fifth-largest market. The forecast appears in CBRE's Q3 2026 European Data Centres report, which puts Milstackinfra.comFeatured: Editorial photograph showing the exterior architecture of the MIL03 data center facility in the Milan metro area.an and Dublin about 100MW of operational capacity apart at the end of the third quarter.

CBRE, a real estate services and advisory firm, tracks the capacity rather than owning it. The 255MW is pipeline that international operators are developing in and around the city, and CBRE said the vast majority of it is designed to support hyperscale and neocloud deployments. Hyperscalers expanding cloud regions and accelerating AI work across Europe are driving the requirement, according to the report.

Most of Milan's development activity is concentrated to the west of the city. CBRE said major projects are also under way in Siziano and across the wider metropolitan area.

Milan recorded the highest take-up among the ten secondary markets CBRE tracks, a group that includes Berlin, Brussels, Madrid, Munich, Oslo, Stockholm, Warsaw, Vienna and Zurich, Data Center Dynamics reported. CBRE read the demand as a sign that occupiers are looking beyond core markets for power availability and price.

"Milan's accelerated development trajectory highlights the city's transition from a secondary market into a top European data centre hub," said Andrew Jay, head of Data Centre Solutions, Europe, at CBRE.

Dublin remains the market Milan would displace. Its third-quarter take-up was the highest of any core market, driven by a hyperscaler taking vacant space on a single campus, which CBRE called unusual given operator caution about the city. Supply growth in Dublin has declined in four of the five years since Ireland declared a de facto moratorium on new data center grid connections in late 2021, CBRE said. Ireland replaced that ban last year with rules requiring on-site generation and batteries sized to a facility's full demand, and environmental groups are challenging the rules in the High Court, DCD reported.

Italy's colocation market has expanded sixfold since 2020, CBRE said, as international operators built large facilities for hyperscale customers.

Across Europe, CBRE expects 1.26GW of new colocation supply against 1.34GW of take-up this year, the first time take-up has exceeded deliveries on the continent. The vacancy rate in Frankfurt, London, Amsterdam, Paris and Dublin fell to an all-time low of 5.8% in the third quarter, and CBRE expects the European rate to close 2026 at 10.3%, down from 12.3%, according to the firm's figures summary.

Power remains the binding constraint. CBRE said connection lead times in the region are lengthening as demand for infrastructure intensifies. In November, Baxtel reported that Terna, Italy's transmission system operator, lists 553 pending data center connection applications totaling 101.36GW.

Baxtel counts 139 data center facilities in Milan, operated by 48 providers, with 23 under construction. Baxtel ranks Milan as the largest data center market in Italy and seventh in EMEA.