Data Center Campus
Google is building a 1.4-million-square-foot data center campus in Haskell County.
In 2024, Google acquired the former Musselman Tech campus and joined the West Texas Flywheel project. The site features at least one 345-kilovolt, 250-megavolt-ampere (MVA) substation and is expected to be energized within 2026.
Buildings
| Site | Operator | Status | Operational | Building Size | Built |
|---|---|---|---|---|---|
| Center ProInterested in this information?Contact us |
Under Construction
|
— | — | 2027 | |
| NorthInterested in this information?Contact us |
Planned
|
— | — | 2027 | |
| Point UltraInterested in this information?Contact us |
Planned
|
— | — | 2028 | |
| AlphaInterested in this information?Contact us |
Planned
|
— | — | 2029 | |
| Park BetaInterested in this information?Contact us |
Planned
|
— | — | 2029 |