Nebius will lease another 134MW of IT capacity in Israel from Mega Or's Mega DC subsidiary, the third capacity agreement between the two companies. Mega Or announced the deal on Nov. 19, as CTech reported. Both facilities are due for completion by the end of the second quarter of 2028.
Featured: Editorial photograph illustrating the Nebius and Mega Or Israeli data center lease agreement.
Mega Or develops and operates the two data centers through Mega DC. Nebius leases the IT capacity and runs its AI cloud workloads inside. The contract runs for seven years from delivery, with an option for Nebius to extend it by five more years on the same terms.
The Beit Shemesh facility, designated MDCIL-4, is under construction and holds grid connection approval. It is rated for up to 135MW of IT capacity, and the Nebius agreement covers about half of that. Beit Shemesh is the second phase of Mega DC's campus there; the first phase, at 58MW, is already leased to Nebius under a January agreement and is due for handover for fit-out this quarter. The second site, Masmiya, designated MDCIL-7, is planned within the Yoav Regional Council.
Mega Or expects the new facilities to generate average annual net operating income of NIS 550 million ($164.74 million) once fully occupied. That sits on top of NIS 740 million ($221.65 million) in annual net operating income from data center contracts already signed, according to Data Center Dynamics. Construction of the two sites is estimated at about $1.6 billion, or roughly $12 million per megawatt of IT capacity.
The agreement extends a relationship that began in May 2025 with 8MW at a Mega Or data center in Modi'in. A second contract in January covered 80MW across Beit Shemesh and Masmiya, split 58MW and 22MW. Nebius is an Amsterdam-based AI cloud company listed on Nasdaq and valued at about $31 billion.
One condition remains open. Masmiya's grid connection application is frozen at the Israel Electricity Authority, and approval is a prerequisite for finalizing that portion of the agreement. Mega Or expects construction of both facilities to finish by the end of the second quarter of 2028.
Baxtel tracks 28 data center sites in Israel, led by MedOne with seven. The largest tracked facility is Amazon's Hartov site at 16MW, and the Tel Aviv metro holds 20 sites, seven of them under construction.