Enlight Renewable Energy and Shemen Yielding Real Estate agreed on Nov. 16 to develop a 150MW data center on Shemen land in Haifa. The companies announced the cooperation agreement in a joint [pres...

Enlight and Shemen Sign 25-Year Lease for 150MW Haifa Data Center

Abdul-Rahman Oladimeji

Abdul-Rahman Oladimeji

November 17, 2026

Enlight Renewable Energy and Shemen Yielding Real Estate agreed on Nov. 16 to develop a 150MW data center on Shemen land in Haifa. The companies announced the cooperation agreement in a joint press release. Enlight leads development, consenlightenergy.comFeatured: Wide landscape photograph of an Enlight Renewable Energy utility-scale power and infrastructure installation.truction and operations of the project. Shemen, a Tel Aviv-listed landowner, supplies the land under a long-term lease.

The site covers roughly 82 dunams, or 20 acres, in the Hof Shemen area near the Haifa port, and the planned power capacity is up to 150MW. The project company will be owned 50% by each company, and the two firms share project costs equally. The area allocated will be 41 to 57 dunams (about 10 to 14 acres) or the full 82 dunams, depending on approved grid capacity and planning considerations.

The lease runs approximately 25 years, with annual rent of NIS 433,000 per dunam linked to the Israeli Consumer Price Index from signing. Aggregate lease payments over the term are expected to exceed NIS 500 million. Ctech reported that rent starts at NIS 27,000 per dunam during development and reaches the full amount once the data center operates, and that Enlight holds an option to buy a 50% interest in the allocated land at a minimum of NIS 6.3 million per dunam, exercisable 30 months after signing.

A 150MW grid connection application has been submitted for the site, and the companies say the application documentation is complete. Both parties committed equal shares of bank guarantees currently estimated at NIS 334 million in aggregate to meet proposed regulatory requirements. Advancement depends on the Israel Electricity Authority issuing a binding final decision and on other required approvals, and the announcement gives no date for that decision.

"Our strategy focuses on advancing data centers in locations that bring together suitable land, power infrastructure and proven execution capabilities," said Adi Leviatan, CEO of Enlight Renewable Energy.

"The agreement to develop the data center in partnership allows us to realize the site's full potential," said Dan Sheffi, CEO of Shemen Yielding Real Estate.

Ctech reported that about 1,000MW of the capacity earmarked for data centers in Israel remains contested, out of roughly 3,000MW the Electricity Authority expects to allocate to the sector by 2030. About 2,000MW of that total is already approved. Baxtel reported in July that the authority paused processing of new data centre grid requests of 8MW or more for 140 days.

The Haifa agreement is Enlight's second data center effort in Israel. The company won an Israel Land Authority tender in March 2025 for an integrated data center and solar complex on a 50-acre site at Ashalim in the Negev, with planned investment of up to $1.1 billion and 100MW of AC consumption capacity, as Baxtel reported. The Nov. 16 release does not name a customer for the capacity or set a construction budget, Mugglehead noted.

Baxtel tracks 28 data center facilities in Israel, operated by 8 providers, with MedOne leading at 7 sites. The largest is Amazon's Hartov site at 16MW.