Park AlphaInterested in this information?Contact us
Riot Platforms initiated a large-scale, 1 gigawatt (“GW”) development to expand its Bitcoin mining and hosting capabilities (“the Expansion”) in Corsicana, Navarro County, Texas.
Riot Platforms (NASDAQ: RIOT), headquartered in Castle Rock, Colorado, is a large-scale North American Bitcoin miner operating two flagship campuses in Texas: Rockdale (700 MW) and Corsicana (400 MW). CEO Jason Les leads the company.
On the Q1 2026 earnings release (April 30, 2026), Les described the quarter as "a definitive inflection point for Riot, as we officially transitioned into an active, revenue-generating data center operator."
Key developments:
New capital is flowing to AI/HPC buildout at Corsicana and exploratory nuclear-AI development with Terrestrial Energy. Bitcoin mining is being treated as a cash flow source to fund the data center transition rather than a growth area for incremental hashrate.
Riot Platforms initiated a large-scale, 1 gigawatt (“GW”) development to expand its Bitcoin mining and hosting capabilities (“the Expansion”) in Corsicana, Navarro County, Texas.
The Blue Steel site, an air-cooled Bitcoin mining facility in Calvert City's industrial corridor east of Paducah, Kentucky. Energized by Block Mining in early 2024 and acquired by Riot Platforms that July, it operates in a leased building and complements Riot's two Paducah-area sites.
Air-cooled Bitcoin mining data center in Paducah's Industrial Park West, western Kentucky. Built out by Blockware/Block Mining beginning in 2022 and acquired by Riot Platforms in July 2024, it anchors Riot's Kentucky campus alongside the Coleman Road and Calvert City sites. The facility supports both self-mining and client hosting.
Greenfield expansion site on Coleman Road in west Paducah, Kentucky, adjacent to an existing substation. Acquired with Block Mining in July 2024, it is the growth leg of Riot Platforms' Kentucky campus and is being developed for air-cooled Bitcoin mining.
This facility is part of Corsicana Campus.
This facility is part of Corsicana Campus.
This facility is part of Corsicana Campus.
This facility is part of Corsicana Campus.
Formely known as Whinstone Rockdale HPC. The site was acquired by Riot in 2021 from Northern Data.
Sep 04, 2025 Eric Bell Texas