Riot: Paducah Commerce Drive

Year Built: 2022
Utility Provider: Jackson Purchase Energy (Big Rivers, MISO)
░░░░ Request Dataset MW
Operational Power

Site History

  • Jun 2021 — Blockware Mining announces a $50M Bitcoin mining facility on five acres in Paducah's Industrial Park West.
  • Oct 2021 — Electric service agreement with Jackson Purchase Energy filed with the Kentucky PSC.
  • 2022 — First phase energized; Blockware opens its flagship Paducah facility.
  • Jul 2024 — Riot Platforms acquires Block Mining (ex-Blockware) for $92.5M, adding the Paducah operation to its portfolio.
  • 2025 — Buildout continues under Riot as part of its Kentucky expansion.

Project Profile

  • Operator: Riot Platforms (ex-Block Mining / Blockware Mining)
  • Location: Industrial Park West, Paducah, McCracken County, KY
  • Workloads: Bitcoin self-mining and hosting; air-cooled infrastructure
  • Sister sites: Coleman Road (Paducah) and Blue Steel (Calvert City)

Map and Nearby Locations

This Facility
Riot Platforms Sites
Nearby Facilities

Park PrimeInterested in this information?Contact us Power Growth Over Time

+186% since 2022
Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Valley OneInterested in this information?Contact us

Distance Site About
NN milesInterested in this information?Contact us Crypto Mining Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
NN milesInterested in this information?Contact us Brookfield: Paducah AI Campus
Brookfield is developing a major AI data center campus at the Department of Energy’s former Paducah Gaseous Diffusion Plant in McCracken County, Kentucky.
NN milesInterested in this information?Contact us Core Scientific: Calvert City
The facility was previously an old Gerdau steel rolling mill before being converted into a bitcoin mining facility.
NN milesInterested in this information?Contact us OneInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us

Operating Company

Operated by:

Overview

Riot Platforms (NASDAQ: RIOT), headquartered in Castle Rock, Colorado, is a large-scale North American Bitcoin miner operating two flagship campuses in Texas: Rockdale (700 MW) and Corsicana (400 MW). CEO Jason Les leads the company.

Strategic pivot to AI/HPC data center operator (2026)

On the Q1 2026 earnings release (April 30, 2026), Les described the quarter as "a definitive inflection point for Riot, as we officially transitioned into an active, revenue-generating data center operator."

Key developments:

  • AMD AI/HPC tenancy at Corsicana. AMD doubled its contracted capacity at the Corsicana campus from 25 MW to 50 MW, establishing Riot's first material non-Bitcoin revenue line.
  • Terrestrial Energy MOU. Post-quarter, Riot signed a memorandum of understanding with Terrestrial Energy to co-locate Integral Molten Salt Reactor (IMSR) nuclear units alongside AI/HPC data centers. The framework contemplates multiple 390 MW reactors scaling to roughly 4 GW of nuclear-powered AI capacity across sites in Texas and Kentucky.
  • Capital reallocation. Riot sold 3,778 BTC for $289.5 million during the quarter to fund the data center buildout, while continuing to self-mine 1,473 BTC.

Q1 2026 financials

  • Revenue: $167.2 million, with the new data center segment contributing $33.2 million (~20%), the first quarter of material non-mining revenue.
  • Bitcoin mining remains the cash-generating foundation of the business while capacity is converted to higher-value HPC/AI hosting.

Capex direction

New capital is flowing to AI/HPC buildout at Corsicana and exploratory nuclear-AI development with Terrestrial Energy. Bitcoin mining is being treated as a cash flow source to fund the data center transition rather than a growth area for incremental hashrate.

0
Facilities
0
Markets

News See all

Read Meta Named on 400MW Kentucky Campus With 40-Year Local Tax Break
Mason County Fiscal Court voted unanimously on Oct. 13 to approve a development and community revenue agreement with Meta, ending two years in which the company behind a planned hyperscale campus n...

Meta Named on 400MW Kentucky Campus With 40-Year Local Tax Break

October 16, 2026 Meta

Mason County Fiscal Court voted unanimously on Oct. 13 to approve a development and community revenue agreement with Meta, ending two years in which the company behind a planned hyperscale campus near Maysville, Kentucky was kept unnamed (Mason County Fiscal Court announcement). The site covers...

Read more
Read Mason County Approves 40-Year Tax Deal for Meta's 400MW Kentucky Campus
The Mason County Fiscal Court voted unanimously on Oct. 13 to approve three agreements that clear the way for [Meta](https://baxtel.com/data-centers/meta) to build a hyperscale data center campus o...

Mason County Approves 40-Year Tax Deal for Meta's 400MW Kentucky Campus

October 16, 2026 Meta

The Mason County Fiscal Court voted unanimously on Oct. 13 to approve three agreements that clear the way for Meta to build a hyperscale data center campus on nearly 3,000 acres near Maysville in northeastern Kentucky. The approvals, set out in the county's news release, cover a 40-year...

Read more
Read Off-Grid Data Center Planned for Letcher County, Kentucky
A new data center could be coming to Kentucky. WYMT reports that the Appalachian Industrial Development Authority (AIDA) has signed an agreement with Diversified Gas and Oil Corporation and Maveric...

Off-Grid Data Center Planned for Letcher County, Kentucky

July 20, 2026 Kentucky

A new data center could be coming to Kentucky. WYMT reports that the Appalachian Industrial Development Authority (AIDA) has signed an agreement with Diversified Gas and Oil Corporation and Maverick Holdings to potentially acquire a 100-acre site at Gateway Business Park in Letcher County. The...

Read more
Read SBI Crypto sues Riot-owned data center
SBI Crypto sues Riot-owned data center

SBI Crypto sues Riot-owned data center

April 12, 2023 Riot Platforms

SBI Crypto Co. is reportedly pursuing litigation against the Riot Blockchain-owned-Whinstone US data center based in Rockdale, Texas. The bitcoin mining company outlined in its lawsuit, filed April 6th, that the data center breached its Hosting Service Agreement, alongside other charges including...

Read more
Read Kentucky GE Data Facility For Sale or Lease
Kentucky GE Data Facility For Sale or Lease

Kentucky GE Data Facility For Sale or Lease

February 20, 2023 Kentucky

GE Appliances is offering its data center in Louisville, Kentucky, for purchase or lease. General Electric has hired JLL, according to a report this week, to market the data center at 4000 Buechel Bank Road in the 1,000-acre GE Appliance Park in Jefferson District for sale or lease. The GE Data...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?