Point PlusInterested in this information?Contact us

Latest Podcast Street AddressInterested in this information?Contact us, TX 75110
Under Construction
New facility under construction
Operated by:

Riot: Corsicana Campus

Short Code: Building 1
Year Planned: 2027
Lot Size: 858 acres

Riot Platforms initiated a large-scale development to expand its Bitcoin mining and hosting capabilities (“the Expansion”) in Corsicana, Navarro County, Texas.

Riot Platforms has acquired two additional parcels of land in 2025 for its Corsicana campus in Texas. The company announced the acquisition of 355 acres in May, followed by another 238 acres in July. The latest purchase brings the total size of the Corsicana data center campus to 858 acres.

Map and Nearby Locations

This Facility
Riot Platforms Sites
Nearby Facilities

EdgeInterested in this information?Contact us Power Growth Over Time

Operational
Construction
Planned
Prospective
In Doubt
Withdrawn
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of PlusInterested in this information?Contact us

Distance Site About
NN milesInterested in this information?Contact us Campus TwoInterested in this information?Contact us
This facility is part of Corsicana Campus.
NN milesInterested in this information?Contact us Station UltraInterested in this information?Contact us
This facility is part of Corsicana Campus.
NN milesInterested in this information?Contact us EdgeInterested in this information?Contact us
This facility is part of Corsicana Campus.
NN milesInterested in this information?Contact us Edge RidgeInterested in this information?Contact us
This facility is part of Corsicana Campus.
NN milesInterested in this information?Contact us Nexus: Apex DFW HB1
Nexus Data Centers is developing the first registered building at its Apex campus in Hubbard, Texas. The privately funded project is scheduled for completion in October 2027 and forms part of a larger AI-focused development supported by dedicated onsite energy infrastructure.
NN milesInterested in this information?Contact us Nexus: Apex DFW HB2
Nexus Data Centers has registered the second building at its Apex campus in Hubbard. The project matches the first building in size and construction value and is scheduled for completion in January 2028.
NN milesInterested in this information?Contact us EG AI: Rice, Texas
EG AI Rice is a planned immersion-cooled GPU data center in Navarro County, Texas, developed by EG AI Corp as a single-tenant facility for regulated mid-market enterprises.

Operating Company

Operated by:

Overview

Riot Platforms (NASDAQ: RIOT), headquartered in Castle Rock, Colorado, is a large-scale North American Bitcoin miner operating two flagship campuses in Texas: Rockdale (700 MW) and Corsicana (400 MW). CEO Jason Les leads the company.

Strategic pivot to AI/HPC data center operator (2026)

On the Q1 2026 earnings release (April 30, 2026), Les described the quarter as "a definitive inflection point for Riot, as we officially transitioned into an active, revenue-generating data center operator."

Key developments:

  • AMD AI/HPC tenancy at Corsicana. AMD doubled its contracted capacity at the Corsicana campus from 25 MW to 50 MW, establishing Riot's first material non-Bitcoin revenue line.
  • Terrestrial Energy MOU. Post-quarter, Riot signed a memorandum of understanding with Terrestrial Energy to co-locate Integral Molten Salt Reactor (IMSR) nuclear units alongside AI/HPC data centers. The framework contemplates multiple 390 MW reactors scaling to roughly 4 GW of nuclear-powered AI capacity across sites in Texas and Kentucky.
  • Capital reallocation. Riot sold 3,778 BTC for $289.5 million during the quarter to fund the data center buildout, while continuing to self-mine 1,473 BTC.

Q1 2026 financials

  • Revenue: $167.2 million, with the new data center segment contributing $33.2 million (~20%), the first quarter of material non-mining revenue.
  • Bitcoin mining remains the cash-generating foundation of the business while capacity is converted to higher-value HPC/AI hosting.

Capex direction

New capital is flowing to AI/HPC buildout at Corsicana and exploratory nuclear-AI development with Terrestrial Energy. Bitcoin mining is being treated as a cash flow source to fund the data center transition rather than a growth area for incremental hashrate.

0
Facilities
0
Markets

News See all

Read Texas Grid Audit Pauses New Data Center Approvals Across ERCOT
Texas Governor Greg Abbott has ordered an audit of every data center advancing through ERCOT's interconnection process before additional projects can move forward. ERCOT has paused its Batch Zero l...

Texas Grid Audit Pauses New Data Center Approvals Across ERCOT

August 06, 2026 Texas

Texas Governor Greg Abbott has ordered an audit of every data center advancing through ERCOT's interconnection process before additional projects can move forward. ERCOT has paused its Batch Zero large-load review, creating a new schedule risk for developers. The order is serious, but it is not a...

Read more
Read PowerPlay AI and Sharon AI Plan 400MW Gas-Powered Data Centre in Texas
PowerPlay AI has unveiled plans for a 400MW behind-the-meter natural gas-powered AI data centre near Abilene, Texas, through a joint venture with neocloud provider Sharon AI. The companies said sit...

PowerPlay AI and Sharon AI Plan 400MW Gas-Powered Data Centre in Texas

July 30, 2026 Texas

PowerPlay AI has unveiled plans for a 400MW behind-the-meter natural gas-powered AI data centre near Abilene, Texas, through a joint venture with neocloud provider Sharon AI. The companies said site planning and land acquisition have been completed, with work now focused on securing gas supply...

Read more
Read Rowan Plans Second Building at Temple, Texas Data Centre Campus
US data centre firm Rowan has filed plans to expand its Temple, Texas campus. The company is proposing AUS02 Building 2 at 1855 Bob White Road in Bell County. The $780 million project will deliver ...

Rowan Plans Second Building at Temple, Texas Data Centre Campus

July 29, 2026 Texas

US data centre firm Rowan has filed plans to expand its Temple, Texas campus. The company is proposing AUS02 Building 2 at 1855 Bob White Road in Bell County. The $780 million project will deliver a 500,000 sq ft (46,451 sqm) single-storey facility. Construction is scheduled from August 2026 to...

Read more
Read Flexential Acquires 110 Acres Near Dallas for 108MW Data Centre Campus
Flexential has acquired 110 acres in Kaufman County, Texas, for its fourth and largest data centre development in the Dallas-Fort Worth area. Located in Talty, the first phase will deliver a 375,00...

Flexential Acquires 110 Acres Near Dallas for 108MW Data Centre Campus

July 28, 2026 Texas

Flexential has acquired 110 acres in Kaufman County, Texas, for its fourth and largest data centre development in the Dallas-Fort Worth area. Located in Talty, the first phase will deliver a 375,000 sq ft (34,840 sqm) facility with 36MW of capacity, supporting wholesale and multi-tenant...

Read more
Read Lawsuit Targets Vantage, VoltaGrid Over San Antonio Off-Grid Data Centre Project
Several environmental groups have threatened to sue Vantage Data Centers and VoltaGrid over two planned natural gas-powered off-grid data centres near San Antonio, Texas. The Environmental Integrit...

Lawsuit Targets Vantage, VoltaGrid Over San Antonio Off-Grid Data Centre Project

July 24, 2026 Texas

Several environmental groups have threatened to sue Vantage Data Centers and VoltaGrid over two planned natural gas-powered off-grid data centres near San Antonio, Texas. The Environmental Integrity Project, the Sierra Club, and Public Citizen allege the companies failed to obtain the required...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?