Project Turbo
The original Project Turbo was a proposed $1.2 billion data center campus in Hall County, Georgia, that was officially withdrawn in December 2025 following intense community opposition.
The original Project Turbo was a proposed $1.2 billion data center campus in Hall County, Georgia, that was officially withdrawn in December 2025 following intense community opposition.
This facility is part of Project Azalea data center campus in McDuffie County, Georgia.
This facility is part of Project Azalea data center campus in McDuffie County, Georgia.
Project Azalea is a proposed $1 billion data center campus located on roughly 200 acres in McDuffie County, Georgia, near the city of Thomson.
This facility is part of Project Azalea data center campus in McDuffie County, Georgia.
This facility is part of Project Azalea data center campus in McDuffie County, Georgia.
This facility is part of Project Azalea data center campus in McDuffie County, Georgia.
November 19, 2026 Atlanta
DC BLOX filed a development of regional impact notice for a third building at its Atlanta West campus in Georgia, Data Center Dynamics reported. The filing with the Georgia Department of Community Affairs covers ATL1-C, a 500,000-square-foot data center at 1800 North River Road in Douglasville....
Read more
November 18, 2026 Atlanta
Microsoft filed for state review on October 20 of a three-building data center campus in Rome, Georgia, with 422MW of planned capacity. The Development of Regional Impact application covers 349 acres at 0 Huffaker Road and 1,659,000 square feet of floor space. Microsoft owns the land, bought in...
Read more
November 12, 2026 Georgia
Three residents of Effingham County, Georgia, sued OpenAI and county officials on Nov. 6 over a 3.2-gigawatt data center project. The 44-page complaint, filed in Effingham County State Court, seeks compensatory and punitive damages and three times actual damages from the defendants named in its...
Read more
November 10, 2026 Georgia
Dade County commissioners in Georgia approved a 90-day moratorium on new data center development after an Atlanta company explored a 300-megawatt project there. The Chattanooga Times Free Press reported that the board acted unanimously on Nov. 5 and that the pause gives officials time to draft...
Read more
November 04, 2026 Georgia
OpenAI is now calling its data centers compute campuses, a change that arrived with a policy package published two days after the midterms. The company released a National Community Compact and a Compute Campus Policy Blueprint on Nov. 5. The compact covers future campuses that OpenAI owns and...
Read more
October 26, 2026 Georgia
OpenAI has applied for a federal permit to fill 72 acres of wetlands at its Project Camellia data center campus in Georgia. The U.S. Army Corps of Engineers' Savannah District is taking public comments on the application through Nov. 4, the Savannah Morning News reported. The campus is...