CB-1 is building 1 of 4 on TeraWulf's Muskie Data Campus in EastPark Industrial Park (Site B) near Ashland, Kentucky. TeraWulf plans an AI and high-performance computing campus on the Boyd and Greenup county line and has not named a tenant.
Kentucky Power will build a new 765/345 kV substation, Venator, in western Boyd County, with two 345 kV lines to the campus. The first building is scheduled to energize in late 2028, and the full campus by October 2029. The Kentucky Public Service Commission is reviewing the service agreement and the new substation.
Site History
- In November 2026, TeraWulf signed a second amended electric service agreement with Kentucky Power.
- In October 2026, TeraWulf and Kentucky Power doubled the contracted load and moved the second phase from 2030 to 2029. Kentucky Power then filed for state approval of the agreement and the Venator substation.
- In August 2026, TeraWulf bought 144 more acres next to the site.
- In May 2026, TeraWulf closed its purchase of the first 164 acres from Industrial Equity Partners.