Overview
Västernorrland County runs along the Gulf of Bothnia in northern Sweden, with Sundsvall as its largest city. AI developers now plan large campuses in Sollefteå, Timrå and Sundsvall, drawn by spare grid capacity.
The Market Today
ServaNet's FRG5 site in Sundsvall hosts the city's Netnod and STHIX internet exchanges and offers colocation. Cygrids runs a colocation hall in Ljungaverk, Ånge, in a building it bought in 2018.
atNorth plans a large campus in Sollefteå. It signed a grid connection agreement with E.ON Energidistribution in May 2026, with power due in autumn 2028.
In August 2026 the Sundsvall and Timrå councils approved a conditional sale of the Torsboda industrial park to a Google company. It had not closed by mid-November. Verda, a Finnish GPU cloud company, plans an AI data centre at Almåsen, west of Sundsvall. Its zoning plan goes to a council vote in late November 2026.
Advantages
-
Grid room. Svenska kraftnät (Svk) maps more than 500 MW of free withdrawal capacity in Västernorrland for 2026.
-
Cheap power. The county sits in bidding zone SE2. In 2025 Stockholm's SE3 averaged nearly three times its spot price.
-
Tax deduction. Sollefteå, Ånge and Örnsköldsvik qualify for Sweden's northern energy tax deduction.
Challenges
-
Open deals. The Torsboda sale waits on an appeal, revised buyback terms and a power supply agreement with E.ON.
-
New lines first. E.ON and Svk plan a new Bandsjö station and a line to Torsboda. Svk's SE2 data-centre queue reached 1,650 MW on 1 November 2026.
-
Farmland. Verda's Almåsen site is productive farmland.
Power and Policy
Svk runs the transmission grid and the connection queue. E.ON Energidistribution connects the large campuses, Sundsvall Elnät serves central Sundsvall, and Härjeåns Nät serves Ånge.