Sentinel: Princeton Nurseries

Under Construction
New facility under construction
Operated by:

Sentinel: Princeton Nurseries

Year Planned: 2027
Utility Provider: PSE&G
Lot Size: 23 acres

Sites leasing space from Sentinel Data Centers:

Sentinel Data Centers is developing the data center, which includes about 79,600 sq ft of office space, on a 23-acre lot carved from the former Princeton Nurseries property. Bloomberg has confirmed it is the tenant, and says the building is not an AI or hyperscale facility and that its generators are for emergency backup only. The site sits beside an existing PSE&G substation, and the plans add a new substation owned by the applicant. The core and shell are scheduled for completion at the end of 2026. WRV, a partnership of Woodmont Properties, Russo Development and Vision Real Estate Partners, owns the land and plans further commercial development on the rest of the property.

Site History

  • October 2026: Bloomberg confirms it is the tenant.
  • September 2026: NJDEP holds a public hearing on the draft air permit for 12 diesel backup generators.
  • August 2026: A Superior Court judge rules for South Brunswick in a residents' challenge to the project; an appeal follows.
  • April 2025: The South Brunswick Planning Board grants preliminary site plan approval.
  • January 2024: WRV buys about 162 acres of the former Princeton Nurseries property.

Map and Nearby Locations

4405 US-1
Sentinel Data Centers Sites
Nearby Facilities

Sentinel: Princeton Nurseries Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Sentinel: Princeton Nurseries

Distance Site
0.02 miles Bloomberg: Princeton Nurseries
0.94 miles DataBridge: Princeton NJ
1.29 miles Lumen South Brunswick 1
1.53 miles Carrier-Neutral Data CenterInterested in this information?Contact us
4.45 miles Enterprise Data CenterInterested in this information?Contact us
6.62 miles QTS: East Windsor 1 DC2
6.75 miles QTS: East Windsor 1 DC1
12.18 miles BNY Mellon Somerset
12.33 miles Carrier Data CenterInterested in this information?Contact us
12.39 miles CyrusOne Somerset
12.56 miles Fintech Data CenterInterested in this information?Contact us
12.68 miles Rackspace: Somerset NYC2
12.68 miles Rackspace Belmont NYC2
12.92 miles Rackspace Somerset NYC1
13.64 miles Digital Fortress Piscataway
13.66 miles Chirisa: Piscataway
14.29 miles Carrier Data CenterInterested in this information?Contact us
14.65 miles QTS: Piscataway 1 DC2
14.72 miles Fintech Data CenterInterested in this information?Contact us
14.72 miles QTS: Piscataway 1 DC1
14.87 miles DataBank Piscataway EWR2
14.96 miles Open Data Centers Piscataway
15.05 miles 365 S Randolphville - Digital Realty
15.06 miles Centersquare: Piscataway EWR3-B
15.09 miles 365 Bridgewater NJ
15.13 miles Enterprise Data CenterInterested in this information?Contact us
15.14 miles 1115 Centennial Ave: Digital Realty
15.17 miles 3 Corporate - Digital Realty
15.18 miles Csquare: Piscataway EWR3
16.29 miles Keystone NAP
16.37 miles Central CampusInterested in this information?Contact us
16.38 miles Northpoint: Keystone Trade Campus
17.25 miles LexusNexis Edison NJ
17.25 miles Iron Mountain New Jersey

Operating Company

Operated by:

Sentinel Data Centers was founded in 2001.
Sentinel has developed approximately 1.6 million square feet of data center space.

0
Facilities
0
Markets

News See all

Read JGT2 Revives $550M Maine Paper Mill Data Center With Sentinel
JGT2 Redevelopment has revived a $550 million plan to convert a former paper mill in Jay, Maine, into an AI data center. The developer filed an amended site location permit and an air emissions lic...

JGT2 Revives $550M Maine Paper Mill Data Center With Sentinel

November 11, 2026 Sentinel Data Centers

JGT2 Redevelopment has revived a $550 million plan to convert a former paper mill in Jay, Maine, into an AI data center. The developer filed an amended site location permit and an air emissions license application with the Maine Department of Environmental Protection, the Bangor Daily News...

Read more
Read New Jersey Senate Passes 38-0 Bill Banning Data Center NDAs
The New Jersey Senate voted 38-0 on October 22 to make nondisclosure agreements around data center projects unenforceable in the state. [Senate Bill 4304](https://www.njleg.state.nj.us/bill-search/...

New Jersey Senate Passes 38-0 Bill Banning Data Center NDAs

November 09, 2026 New Jersey

The New Jersey Senate voted 38-0 on October 22 to make nondisclosure agreements around data center projects unenforceable in the state. Senate Bill 4304 has moved to the Assembly, where it was referred to the Science, Innovation and Technology Committee. The bill bars data center applicants and...

Read more
Read New Jersey Fines DataOne $1.07M Over Unpermitted Vineland Generators
Newly obtained public records show that a 300-megawatt data center under construction in Vineland, New Jersey, ran 62 unpermitted natural gas generators for nearly a year and released an estimated ...

New Jersey Fines DataOne $1.07M Over Unpermitted Vineland Generators

October 04, 2026 DataOne

Newly obtained public records show that a 300-megawatt data center under construction in Vineland, New Jersey, ran 62 unpermitted natural gas generators for nearly a year and released an estimated 140 tons of smog-forming nitrogen oxides before state regulators intervened, according to an...

Read more
Read Data Centre Developer Sues New Jersey Town for $300m
Data centre developer Hexa Builders is seeking $300 million in damages from Monroe Township, New Jersey, after officials rejected its proposed 1 million sq ft data centre in May. The lawsuit, filed...

Data Centre Developer Sues New Jersey Town for $300m

July 30, 2026 New Jersey

Data centre developer Hexa Builders is seeking $300 million in damages from Monroe Township, New Jersey, after officials rejected its proposed 1 million sq ft data centre in May. The lawsuit, filed in New Jersey Superior Court, alleges the township council and planning board violated multiple...

Read more
Read New Jersey Lawmakers Approve Bill Creating Large Load Data Center Tariff
New Jersey lawmakers have passed a bill directing the state’s Board of Public Utilities to create a dedicated tariff for data centers with capacities of 50MW or more, aimed at protecting other rate...

New Jersey Lawmakers Approve Bill Creating Large Load Data Center Tariff

July 03, 2026 New Jersey

New Jersey lawmakers have passed a bill directing the state’s Board of Public Utilities to create a dedicated tariff for data centers with capacities of 50MW or more, aimed at protecting other ratepayers from rising costs linked to new developments. The legislation, S731, replaces an earlier...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.