QTS Data Centers is developing up to 11 data center buildings on about 465 acres of Lancium's Clean Campus in Hall County, Texas, about four miles south of Turkey. QTS designs, builds and operates the buildings. Lancium owns the land and provides the electrical and civil infrastructure. The companies announced the project in July 2026 with an investment of more than $10 billion.
The campus sits on a 345 kV transmission line and is anchored by a 1 GW grid connection, with on-site solar and battery storage. QTS plans closed-loop cooling that does not draw on municipal water. Site grading began in May 2026, and the first building pad was graded by late August 2026.
Site History
- In October 2026, QTS and Lancium agreed to fund up to $15.5 million of infrastructure and community projects in Turkey.
- In August 2026, the first building pad was graded.
- In July 2026, QTS and Lancium announced the campus.
- In January 2026, Hall County added a second reinvestment zone for the project.
- In June 2025, Hall County approved tax abatements for the campus.