QTS Glendale AZ

Latest Podcast
17501 W Bethany Home Rd
Planned
Future facility in planning stage
Operated by:

QTS Glendale AZ

Short Code: Phoenix 3
Lot Size: 375 acres

Sites on this Campus:

QTS bought the property consisting of 375 acres in July 2022 for $255 million.

  • QTS has filed plans for a this new data center campus known as QTS PHX 3 in the Glendale area of the city in Maricopa County.
  • The Blackstone-owned company aims to develop 16 buildings – each around 180,000 sq ft (16,720 sqm)– totaling around 3 million sq ft (278,710 sqm) on the property, located north of Camelback Road and west of the Loop 303 along Cotton Lane.

Map and Nearby Locations:

17501 W Bethany Home Rd
QTS Data Centers Sites
Nearby Facilities

Sites within 15 miles of QTS Glendale AZ

Distance Site About
0.13 miles QTS: Glendale Expansion
0.55 miles Vantage: Glendale AZ3
In 2023, Vantage acquired nearly 34 acres from Phoenix-based industrial developer Merit Partners for $50 million, at approximately $1.5 million per acre.
1.76 miles Hyperscale Data Center Request Dataset
Microsoft paid DRI FR Goodyear LLC $37 million for the 147 acre lot in Goodyear on April 15, 2019.
1.84 miles Hyperscale Data Center Request Dataset
3.95 miles Aligned: PHX 07-4
4.02 miles Aligned: PHX 07-3
This facility is part of Aligned's PHX07 campus in Phoenix.
4.10 miles Aligned: PHX-07
Aligned Data Centers celebrated the topping-out ceremony for its PHX-07 campus in 2024. Construction of the facility began in 2023, and it is expected to become operational in 2025.
4.17 miles Aligned: PHX 07-2
PHX 07-2 is the second phase of Aligned's PHX07 campus in Phoenix. The two-story, 214,078-square-foot facility spans across six data halls.
4.93 miles Takanock: Project Baccara
Backed by DigitalBridge, the Project Baccara development is an ambitious 160-acre industrial project spearheaded by Takanock, located near the Luke Air Force Base.
5.06 miles Takanock: Baccara Bldg2
The facility is part of Takanock's Project Baccara in Arizona.
5.57 miles Hyperscale Data Center Request Dataset
The facility is part of Microsoft's campus located at the northwest and northeast corners of Dysart Road and Northern Parkway in El Mirage.
5.60 miles Hyperscale Data Center Request Dataset
The tech giant purchased two parcels of land for over $258 million in cash on May 2024. These properties, situated at the northwest and northeast corners of North Dysart Road and West Northern Parkway, were sold by DPML Copperwing LLC.
5.71 miles Compass: Phoenix I DC7
Compass Datacenters is constructing a hyperscale campus in Goodyear, Arizona, a suburb of Phoenix. The DC7 is one of the data center buildings of this campus.
5.75 miles Compass: Phoenix I DC6
Compass Datacenters is constructing a hyperscale campus in Goodyear, Arizona, a suburb of Phoenix. The DC6 is one of the data center buildings of this campus.
5.78 miles Vantage: AZ13
In November 2024, Vantage Data Centers completed the topping out of the third data center building of its Phoenix Campus in Goodyear, Arizona.
5.81 miles Vantage AZ14
Located directly north of the AZ1 development, AZ14 features similar design and color elements to maintain visual continuity with its predecessor.
5.82 miles Hyperscale Data Center Request Dataset
The facility is part of Microsoft's campus located at the northwest and northeast corners of Dysart Road and Northern Parkway in El Mirage.
5.83 miles Compass: Phoenix I DC5
Compass Datacenters is constructing a hyperscale campus in Goodyear, Arizona, a suburb of Phoenix. The DC5 is one of the data center buildings of this campus.
5.84 miles Vantage: AZ15
This planned facility is a part of Vantage's Phoenix Data Center Campus in Arizona.
5.90 miles Compass: Phoenix I DC4
Compass Datacenters is constructing a hyperscale campus in Goodyear, Arizona, a suburb of Phoenix. The DC4 is one of the data center buildings of this campus.
5.92 miles Vantage Phoenix
In January 2019 Vantage announced it acquired 50 acres outside Phoenix in Goodyear, Arizona, to build a mega-scale data center campus. Construction began in early 2019, with the first phase coming online in 2022.
5.95 miles Vantage: AZ12
This facility is a part of Vantage's Phoenix Data Center Campus in Arizona.
6.11 miles Hyperscale Data Center Request Dataset
Known as PHX-83, the building will total 245,500 sq ft (22,808 sqm).
6.14 miles Compass: Phoenix I DC3
Compass Datacenters is developing a hyperscale campus in Goodyear, a suburb of Phoenix, Arizona. The project began in January 2019 when Compass acquired a 200-acre land parcel in the area.
6.14 miles Hyperscale Data Center Request Dataset
In April 2024, the El Mirage City Council approved a site plan amendment on the existing site in El Mirage Campus, allowing Microsoft to add another 245,000 sq ft (22,760 sqm), single-story data center.
6.18 miles Hyperscale Data Center Request Dataset
This Facility is a part of Microsoft's El mirage Campus in Arizona.
6.20 miles Compass: Phoenix I DC2
Compass Datacenters is constructing a hyperscale campus in Goodyear, Arizona, a suburb of Phoenix. The DC2 is one of the data center buildings of this campus.
6.24 miles Hyperscale Data Center Request Dataset
6.24 miles Compass Phoenix
Compass Datacenters is developing a hyperscale campus in Goodyear, a suburb of Phoenix, Arizona. The project began in January 2019 when Compass acquired a 200-acre land parcel in the area.
6.38 miles Compass: Phoenix I DC8
Compass Datacenters is constructing a hyperscale campus in Goodyear, Arizona, a suburb of Phoenix. The DC8 is one of the data center buildings of this campus.
7.08 miles Compass: El Mirage Bldg3
The facility is part of Compass El Mirage data center campus in Arizona.
7.24 miles Compass: El Mirage Bldg2
The facility is part of Compass El Mirage data center campus in Arizona.
7.28 miles Compass: El Mirage, AZ
The company plans to develop three single-story buildings on this property, each spanning 208,000 square feet.
7.41 miles DCX: Goodyear GYR1
7.92 miles Stream Goodyear AZ
Phoenix I is the first of five 40MW buildings.
8.04 miles Stream: PHX II
Stream Data Centers has topped out the second data center facility on its Goodyear Campus in August 2024.
8.14 miles Stream: PHX III
This facility is a part of Stream's Phoenix Data Center Campus in Goodyear, Arizona.
8.17 miles STACK Phoenix
Stack Infrastructure (Stack) is building a data center campus on a 100-acre site in Phoenix, Arizona.
8.17 miles Hyperscale Data Center Request Dataset
8.23 miles Stream: PHX IV
This facility is a part of Stream's Phoenix Data Center Campus in Goodyear, Arizona.
8.26 miles Hyperscale Data Center Request Dataset
8.32 miles Stream: PHX V
This facility is a part of Stream's Phoenix Data Center Campus in Goodyear, Arizona.
8.35 miles Hyperscale Data Center Request Dataset
8.40 miles Hyperscale Data Center Request Dataset
8.43 miles Stream: PHX VI
This facility is a part of Stream's Phoenix Data Center Campus in Goodyear, Arizona.
8.48 miles Hyperscale Data Center Request Dataset
In August 2018, Microsoft paid about $48 million for its 279-acre site near the Phoenix Goodyear Airport. The project already has three massive buildings, and Microsoft plans to construct two more buildings on the campus, for a total of five buildings.
9.77 miles QTS: Hermosa Ranch
US data center firm QTS has acquired 206 acres in the West Valley for $246.8 million in an all-cash deal in July, 2024 from TGV Investments LLC.
10.05 miles Prime Phoenix
The Phoenix Campus is expected to be 1.3 million square feet across 5 data center buildings. The first data center is expected to be completed by Q3 2025 and total 260,400 square feet.
10.09 miles Prime: PHX01-02
This facility is one of five planned data center buildings in Prime's Phoenix Campus.
10.14 miles Prime: PHX01-03
This facility is one of five planned data center buildings in Prime's Phoenix Campus.
10.18 miles Prime: PHX01-04
This facility is one of five planned data center buildings in Prime's Phoenix Campus.
10.22 miles Prime: PHX01-05
This facility is one of five planned data center buildings in Prime's Phoenix Campus.
12.33 miles Aligned: Peoria Logistics Park
Aligned Data Centers firm acquired nearly 80 acres at the Peoria Logistics Park for $43.2 million in Peoria.
13.42 miles Arizona Land: Buckeye, AZ
Arizona Land Consulting, the Valley's premier real estate consulting firm, finalized a $20 million acquisition in Buckeye, Arizona.
17.21 miles Hyperscale Data Center Request Dataset
Amazon Data Services has acquired land for a potential data center campus in Laveen, Phoenix. The 220-acre site, located near Loop 202 and Dobbins Road, was purchased for $277 million ($1.2 million per acre).
17.94 miles Arizona Land: Buckeye 2 Expansion
18.04 miles Arizona Land: Buckeye 2
Arizona Land Consulting purchased 160 acres in Phoenix's Buckeye area for $21.7 million, with plans to sell to a data center developer.
18.12 miles Tract: Buckeye, Arizona
Tract announced its acquisition of a 2,019-acre land parcel to build a gigawatt-scale data center park in Buckeye, Arizona.
18.29 miles Tract: Buckeye Expansion
18.66 miles Five 9s: Blue Shield Phoenix
In 2021, Five 9s Digital acquired the 45,000 sq ft data center located at 2475 West Townley Avenue in Phoenix, Arizona, which was previously owned by Blue Cross Shield.
18.68 miles Expedient Phoenix
In 2021, Five 9s Digital acquired the 46,000 sq ft data center located at 2475 West Townley Avenue in Phoenix, Arizona, which was previously owned by Blue Cross Shield, and subsequently leased it to Expedient.
19.45 miles Arizona Land: Tonopah Campus
Arizona Land Consulting (ALC) is planning to build a 1.5-gigawatt (GW) data center in Buckeye, Arizona, a city located west of Phoenix.
19.72 miles Arizona Land: Tonopah Expansion

QTS Glendale AZ Data Center Photos (See all)

Operating Company

Operated by:

QTS Data Centers is a privately held data center company owned by funds managed by Blackstone, with corporate headquarters in Overland Park, Kansas. It provides colocation, custom data center and managed services, along with carrier-neutral connectivity across its platform.

QTS operates sites in the United States and in the Netherlands. The company expanded its footprint with acquisitions in Chicago and Princeton in 2014, added government and managed hosting capabilities with the Carpathia acquisition in 2015, and entered the Netherlands market in 2019. QTS became a public company in 2013 and was taken private in 2021.

History:

  • On August 31, 2021 funds managed by Blackstone completed the acquisition of QTS Realty Trust.
  • April 30, 2019: Acquired two operating data centers in Groningen and Eemshaven, Netherlands, for approximately $44 million.
  • June 2015: QTS acquires Carpathis Hosting for $326 million. The transaction increases QTS's ability to serve IaaS and Government clients. Additionally the transaction provides a number of deployments within Equinix facilities.
  • July 8, 2014: Acquired the former Chicago Sun-Times printing plant for conversion to a data center.
  • June 30, 2014: Acquired the Princeton, New Jersey data center from McGraw Hill Financial.
  • 2013: Went public (IPO) and started trading under the symbol QTS on the NYSE.
  • 2010 Acquired their Richmond facility
  • 2005 QTS acquired Atlanta Suwanee data center
  • 2003: Company acquired its first data center in Overland Park, KS
  • 2003: QTS was founded by Chad Williams with its first data center in Overland Park in Kansas