Hyperscale OperatorInterested in this information?Contact us Issues Force Majeure Notice To Blue Owl Over Project Jupiter Data Center Setbacks
September 24, 2026 Oracle
Hyperscale OperatorInterested in this information?Contact us has issued a force majeure notice to Blue Owl Capital over delays and potential cost increases tied to Project Jupiter, a 2.5GW data center campus in New Mexico, according to Bloomberg. Hyperscale OperatorInterested in this information?Contact us became the project’s tenant in January 2026. The 1,400-acre campus is planned to include four...