Carrier-Neutral OperatorInterested in this information?Contact us is currently developing its second hyperscale campus in Wilmer, Texas, situated in South Dallas County. This new development, known as the DFWC campus, is being constructed on a vast 140-acre site. At full build-out, the campus is projected to encompass 1.4 million square feet of data center space. The entire project is designed to be supported by a dedicated, on-site 372 MW Oncor substation, ensuring robust power capacity for the facility.
The company recently filed a Texas Department of Licensing and Regulation (TDLR) application for the initial phase, DFWC1. This first facility involves a planned investment of $300 million for a two-story data center building spanning 360,750 square feet (33,514 square meters), as well as the construction of the substation and a campus entrance. The construction timeline for the DFWC1 building is scheduled to begin in April 2026 and conclude by October 2027.