Meta is building a data center campus in the LEAP Research and Innovation District west of Lebanon, in Boone County, Indiana. The current plan has 13 buildings: 10 data center buildings plus network, logistics and administration buildings, built in several phases. Meta broke ground in February 2026 and expects the first buildings to come online in late 2027. Meta is paying for the new transmission lines and substations that connect the campus, and a temporary natural-gas plant will power the first buildings until the grid connection is complete. The data halls use a closed-loop liquid cooling system.
Site History
-
September 2026: Indiana issues air permits for the campus and its temporary gas plant.
-
February 2026: Meta breaks ground and raises its planned investment above $10 billion.
-
November 2025: Lebanon Utilities and Meta sign the campus water and wastewater agreement.
-
August 2025: The Lebanon Plan Commission approves the development plan.
-
December 2024: Meta agrees to build in the LEAP district.