Under Construction
New facility under construction
Operated by:

Meta: Cheyenne

Year Planned: 2026
Lot Size: 960 acres

Sites on this Campus:

  • Edge CampusInterested in this information?Contact us

Meta is developing a 715,000 sq ft (66,425 sqm) data center campus in Cheyenne, Wyoming. The company plans to invest over $800 million in the 960-acre project, which it says will be optimized for AI workloads. The campus will include at least two buildings and on-site substations. Notably, these buildings will not follow Meta's traditional H design used in previous projects.

  • Construction on the first building started in early 2024 and the facility is scheduled to open by 2027.
  • Wyoming offers tax breaks for data center operators, which is said to have been a deciding factor in Meta pursuing the Cheyenne project.
  • A data center development on the site, dubbed ‘Project Cosmo’, was approved by Cheyenne City Council in November 2023. At the time, Meta was using the shell company Goat Systems LLC to conduct business. The social media firm was named as the company behind the project in May 2024.

Map and Nearby Locations

This Facility
Meta Sites
Nearby Facilities

South TowerInterested in this information?Contact us Power Growth Over Time

Operational
Construction
Planned
Prospective
In Doubt
Withdrawn
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of East TowerInterested in this information?Contact us

Distance Site About
NN milesInterested in this information?Contact us ParkInterested in this information?Contact us
Meta is building a 715,000 sq ft (66,425 sqm) data center campus in Cheyenne, Wyoming.
NN milesInterested in this information?Contact us South ParkInterested in this information?Contact us
Microsoft is building a data center campus at Bison Business Park to support its West Central US Azure region. The plan was Announced in 2021.
NN milesInterested in this information?Contact us South StationInterested in this information?Contact us
The facility is part of Microsoft's Bison Business Park Campus in Cheyenne, Wyoming.
NN milesInterested in this information?Contact us West HubInterested in this information?Contact us
Originally permitted as Project Jade, this $50 billion development near Cheyenne, Wyoming, was reflagged as Project Tembo after Google took direct control of the project from developer Crusoe.
NN milesInterested in this information?Contact us Hub OneInterested in this information?Contact us
The facility is part of Microsoft's Bison Business Park Campus in Cheyenne, Wyoming.
NN milesInterested in this information?Contact us PointInterested in this information?Contact us
The facility is part of Microsoft's Bison Business Park Campus in Cheyenne, Wyoming.
NN milesInterested in this information?Contact us Cloud ParkInterested in this information?Contact us
The facility is part of Microsoft's Bison Business Park Campus in Cheyenne, Wyoming.
NN milesInterested in this information?Contact us Related Digital: Cheyenne, Wyoming
Related Digital has started construction on a $1.2 billion data center campus in Cheyenne, Wyoming.

Data Center Photos

Facility photo

Campus exterior and data hall photography for this operator.

Facility photo

Campus exterior and data hall photography for this operator.

Facility photo

Campus exterior and data hall photography for this operator.

Operating Company

Operated by:

Founded in 2004, Facebook needs no introduction as the world's largest social network. All the status updates, family photos and videos add up and create a need for a massive amount of storage and compute. Facebook maintains a growing stable of data centers spread across the world.

0
Facilities
0
Markets

News See all

Read Meta’s $1.2B Data Center In Kuna, Idaho, Goes Live
Meta’s Kuna, Idaho Data Center Is Now Operational Meta has begun serving traffic from its data center in Kuna, Idaho. The company announced the campus in 2022, initially planning to invest $800 mil...

Meta’s $1.2B Data Center In Kuna, Idaho, Goes Live

September 04, 2026 Meta

Meta’s Kuna, Idaho Data Center Is Now Operational Meta has begun serving traffic from its data center in Kuna, Idaho. The company announced the campus in 2022, initially planning to invest $800 million in a 960,000 sq ft (89,187 sqm) facility. The project was later temporarily paused for redesign...

Read more
Read Meta Expands Louisiana Data Center Campus To 5GW
Meta plans to more than double its Richland Parish, Louisiana, data center campus to 5GW of capacity. The site, known as the Hyperion data center project, was previously planned as a 2GW developmen...

Meta Expands Louisiana Data Center Campus To 5GW

July 13, 2026 Meta

Meta plans to more than double its Richland Parish, Louisiana, data center campus to 5GW of capacity. The site, known as the Hyperion data center project, was previously planned as a 2GW development. Announced in late 2024, Hyperion was originally designed as a 4 million sq ft (372,000 sqm)...

Read more
Read Meta Plans $9.17 Billion Gigawatt-Scale Data Center in Alberta, Canada
Meta is planning a 1GW data center in Sturgeon County, Alberta, marking the company’s first facility in Canada. The project represents a CA$13 billion (US$9.17 billion) investment and could scale u...

Meta Plans $9.17 Billion Gigawatt-Scale Data Center in Alberta, Canada

July 09, 2026 Meta

Meta is planning a 1GW data center in Sturgeon County, Alberta, marking the company’s first facility in Canada. The project represents a CA$13 billion (US$9.17 billion) investment and could scale up to 1.8GW of capacity. The AI-focused facility will use a closed-loop liquid cooling system and is...

Read more
Read Meta Veteran Sham Parmar Joins Anthropic Supply Chain Operations
Meta’s Sham Parmar has joined generative AI company Anthropic.
Parmar previously served as senior manager for supply chain and engineering, overseeing electrical, mechanical, and fiber connectivit...

Meta Veteran Sham Parmar Joins Anthropic Supply Chain Operations

June 16, 2026 Meta

Meta’s Sham Parmar has joined generative AI company Anthropic. Parmar previously served as senior manager for supply chain and engineering, overseeing electrical, mechanical, and fiber connectivity systems. "I'm excited to share that I've joined Anthropic as a supply chain lead, power and cooling...

Read more
Read Private Equity Firm Acquires Croatia’s ‘Fort Knox’ Data Center
Gnomon Capital has acquired 100% of Croatian data center DC North, known as the “Fort Knox” facility, in a deal involving former owners Cratis and Muraplast. Court records show the transfer was com...

Private Equity Firm Acquires Croatia’s ‘Fort Knox’ Data Center

June 13, 2026 Meta

Gnomon Capital has acquired 100% of Croatian data center DC North, known as the “Fort Knox” facility, in a deal involving former owners Cratis and Muraplast. Court records show the transfer was completed in late May, with Gnomon now listed as the sole shareholder. DC North was launched by Cratis...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?