Meta is building an AI-focused data center campus on farmland in Middleton Township, south of Bowling Green and Toledo. Its affiliate Liames LLC began buying the land in 2023, site work started in 2024, and Meta announced the $800 million project in April 2025. By mid-2026 the first two buildings had their roofs going on and work had begun on two more. JE Dunn is the general contractor.
FirstEnergy's transmission arm expanded its Dowling substation beside the campus in 2025 and built 138 kV lines to two customer substations for the data center. A dedicated natural-gas plant with battery storage, built by a Williams subsidiary on an adjacent parcel, will add on-site supply from mid-2027.
Site History
- In April 2026, Ohio EPA held a public hearing on the air permit for the on-site gas plant.
- In February 2026, the Ohio Power Siting Board approved the on-site gas plant, and its construction began.
- In November 2025, FirstEnergy finished the substation and transmission work for the campus.
- In April 2025, Meta announced the Bowling Green data center.
- In fall 2024, road work and site preparation began.
- In November 2023, Liames LLC bought its first land for the campus.