This is building 1 of 2 on Meta's Beaver Dam campus. Meta is investing more than $1 billion in the 700,000-square-foot data center, its 30th worldwide. The building is designed for high-density AI workloads. It uses a closed-loop liquid cooling system that needs no water for most of the year. Meta plans to bring it online in 2027, and the project supports more than 1,000 construction jobs and more than 100 permanent roles.
Utility
Alliant Energy serves the campus under a 10-year electric service contract that the Public Service Commission of Wisconsin approved in June 2026. American Transmission Co. is building about 15 miles of new double-circuit 138 kV line to a new substation for the site.
Site History
- July 2026: A roof fire damages the building under construction.
- June 2026: The Public Service Commission of Wisconsin approves Alliant's electric service contract for the campus.
- December 2025: The Wisconsin DNR exempts the backup generators from an air permit.
- 2025: Meta's Beaver Dam plans become public, with Mortenson as general contractor.