KALiNA Distributed Power proposed a gas-fired power and data centre park east of Lacombe, with Crusoe as the data centre partner. KALiNA also holds an option on about 290 more acres.

Site History

  • 2026: KALiNA cancels its data-centre grid request and files a new request for the gas plant alone.
  • 2024: Crusoe and KALiNA sign a framework to build AI data centres on KALiNA's Alberta power parks, including this site.
  • 2024: KALiNA proposes a gas-fired power plant with a data centre beside it in Lacombe County, east of Lacombe.

Map and Nearby Locations

Lacombe County, east of Lacombe ( LSD 10-26-40-26-W4M )
KALiNA Distributed Power Limited Sites
Nearby Facilities

Sites within 15 miles of KALiNA: Myers Energy Park

Distance Site About
10.44 miles Agritech Haven: Red Deer, AB
A major data center project by Agritech Haven International (AHI) has been approved for construction on a 120-acre site in Red Deer County, Alberta, with Phase 1 completion expected in 2026.
10.52 miles Tower ThreeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us

Operating Company

Operated by:

KALiNA Power Limited (“KPO”) is an ASX listed company dedicated to delivering cost effective power projects that incorporate technologies that generate constant baseload electricity with a low carbon footprint.

0
Facilities
0
Markets

News See all

Read FingerMotion, Genius Group Sign JV For 2.4MW HPC Campus In Alberta
Genius Group, [FingerMotion](https://baxtel.com/data-centers/fingermotion) and BlueFlare Energy Solutions signed [binding agreements](https://ir.geniusgroup.net/news-events/press-releases/detail/26...

FingerMotion, Genius Group Sign JV For 2.4MW HPC Campus In Alberta

October 28, 2026 FingerMotion

Genius Group, FingerMotion and BlueFlare Energy Solutions signed binding agreements on October 27 to form GENIUSpark Alberta Inc. and build high-performance computing campuses in Alberta, Canada. The first site, Hanna Campus No. 1, carries an estimated $24.3 million cost and 2.4 MW of computing...

Read more
Read Avax One Targets 10MW Behind-the-Meter Data Center in Alberta
Avax One Targets 10MW Behind-the-Meter Data Center in Alberta

Avax One Targets 10MW Behind-the-Meter Data Center in Alberta

April 11, 2026 Alberta

Cryptocurrency firm Avax One Technology has signed a front-end engineering and design (FEED) proposal for a 10MW off-grid, natural gas-powered AI and high-performance computing (HPC) data center at the 4-31 Battery site in Alberta, Canada. The FEED study will be led by BlueFlare Energy Solutions...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.