Imperial Valley Computer Manufacturing (IVCM) proposes the $10 billion Imperial Data Center outside the City of Imperial, as a hub for AI and high-performance computing. The design pairs a developer-funded substation with an 862 MWh battery system of 220 Tesla Megapacks and natural-gas backup generators. No tenant has signed, and Google has said it is not involved in the project.
The City of Imperial, residents and environmental groups oppose the project over its water demand and its environmental review. In September 2026, Imperial County Superior Court set aside the county's CEQA exemption and its approvals for the project. The court ordered a full environmental review before the county can process permits. IVCM has said it will challenge the ruling. It is also suing the Imperial Irrigation District, which turned down its request for Colorado River water.
Site History
-
2026-10: Imperial County repealed its data center moratorium under a court order, then adopted a new one.
-
2026-09: Imperial County Superior Court set aside the lot merger, road vacation and grading approval, and required full CEQA review.
-
2026-06: IVCM sued the Imperial Irrigation District after the district turned down its water application.
-
2026-04: Imperial County approved a lot merger for the site.
-
2025-11: Imperial County exempted the site's grading permit from CEQA review.