Google is building a data center campus, known during planning as Project BOSC, on farmland along North Cole Street in American Township, north of Lima. Its affiliate Bistrozzi LLC assembled the land in 2025 and 2026. The plan calls for two water-cooled buildings, a $500 million investment and about $50 million in public infrastructure. Google will also pay Elida schools $250,000 a year for 15 years. Turner Construction started site work in late 2025.
AEP Ohio will serve the campus from Lyka, a new 345 kV substation between North Cole Street and North West Street, linked by about four miles of new line and planned for service in summer 2028. Ohio EPA permitted 115 emergency generators and 36 cooling towers for the campus in May 2026.
Site History
- In May 2026, Ohio EPA issued the air permit for the campus generators and cooling towers.
- In April 2026, Google confirmed it is the company behind the project.
- In April 2026, AEP Ohio presented its plan for the Lyka substation.
- In November 2025, Ohio EPA granted Turner Construction stormwater coverage for site work.
- In August 2025, Bistrozzi LLC bought about 340 acres from three landowners.
- In July 2025, Allen County approved a 15-year, 75% property tax abatement for the project.
- In December 2024, an unnamed company first proposed a data center campus on North Cole Street.