Evroc, the Swedish sovereign cloud company, signed a memorandum of understanding with reactor developer Blykalla and Studsvik in October 2025 to study Sweden's first nuclear-powered data center at Studsvik's licensed nuclear site near Nyköping. The data center would need at least 200 MW when complete, with power from Blykalla's SEALER small modular reactors of about 55 MW each. The partners had not decided between island operation and a grid connection. No building application has been filed, and the partners' 2026 nuclear applications point elsewhere: Blykalla to Gävle and Tierp, and Studsvik to its own light-water reactor park at the site.
Site History
- 2026-05-25: Studsvik applied to build 600 to 1,400 MWe of new nuclear power at its Nyköping site, with other partners.
- 2025-10-06: Evroc, Blykalla and Studsvik signed an MoU to explore nuclear-powered data centers at Studsvik.