DataOne: Frankfort, IN

Year Planned: 2028
Utility Provider: Frankfort Municipal Utilities
Lot Size: 115 acres

DataOne plans a single 800,000 sq ft building with 18 data halls on about 115 acres inside Frankfort city limits, east of the ConAgra plant and south of the railroad. The end user is an undisclosed publicly listed US company.

  • The Frankfort City Council approved DataOne's community enhancement agreement 5-2 in September 2026, including a 10-year, 50% real property tax rebate.
  • Power will come from IMPA grid supply through Frankfort Municipal Utilities plus on-site Bloom Energy fuel cells. DataOne is funding two new substations, one of which goes to Frankfort Municipal Utilities.

Map and Nearby Locations

W County Rd 0 N/S
DataOne Sites
Nearby Facilities

DataOne: Frankfort, IN Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of DataOne: Frankfort, IN

Distance Site About
0.64 miles Logistix: Frankfort 1
Frankfort 1 was the first planned building in Logistix Property Group's original data center plan on county farmland north of the railroad in Frankfort, Indiana. Clinton County denied the rezoning in January 2026.
0.79 miles Logistix: Frankfort Expansion
Frankfort Expansion held the later phases of Logistix Property Group's original data center plan on county farmland in Frankfort, Indiana. Clinton County denied the rezoning in January 2026.
15.19 miles Wintek Lafayette
15.35 miles ProInterested in this information?Contact us
This facility is part of Meta's Project Domino in Lebanon, Indiana.
15.53 miles PrimeInterested in this information?Contact us
This facility is part of Meta's Project Domino in Lebanon, Indiana.
15.67 miles CampusInterested in this information?Contact us
This facility is part of Meta's Project Domino in Lebanon, Indiana.
15.84 miles Hub ThreeInterested in this information?Contact us
This facility is part of Meta's Project Domino in Lebanon, Indiana.
15.94 miles Metro HubInterested in this information?Contact us
Project Domino is planned to include 12 data center buildings along with a dedicated AI-Network facility, providing over 4.6 million square feet of compute infrastructure.
16.12 miles Park PrimeInterested in this information?Contact us
This facility is part of Meta's Project Domino in Lebanon, Indiana.
16.32 miles MetroInterested in this information?Contact us
This facility is part of Meta's Project Domino in Lebanon, Indiana.
16.33 miles Campus MaxInterested in this information?Contact us
This facility is part of Meta's Project Domino in Lebanon, Indiana.
16.33 miles Point BetaInterested in this information?Contact us
This facility is part of Meta's Project Domino in Lebanon, Indiana.
16.35 miles AlphaInterested in this information?Contact us
This facility is part of Meta's Project Domino in Lebanon, Indiana.
16.37 miles CampusInterested in this information?Contact us
This facility is part of Meta's Project Domino in Lebanon, Indiana.
16.58 miles Prime ValleyInterested in this information?Contact us
This facility is part of Meta's Project Domino in Lebanon, Indiana.

Operating Company

Operated by:

Data One specializes in advanced data centers for AI, merging cutting-edge technology with proven expertise. Backed by BSO’s 20 years of operational excellence, it sets new benchmarks in efficiency and innovation. With 240+ Points of Presence and seamless integration across 30+ stock exchanges, it delivers unmatched performance and reliability to power the future of AI.

0
Facilities
0
Markets
0MW
Megawatts

News See all

Read New Jersey Fines DataOne $1.07M Over Unpermitted Vineland Generators
Newly obtained public records show that a 300-megawatt data center under construction in Vineland, New Jersey, ran 62 unpermitted natural gas generators for nearly a year and released an estimated ...

New Jersey Fines DataOne $1.07M Over Unpermitted Vineland Generators

October 04, 2026 DataOne

Newly obtained public records show that a 300-megawatt data center under construction in Vineland, New Jersey, ran 62 unpermitted natural gas generators for nearly a year and released an estimated 140 tons of smog-forming nitrogen oxides before state regulators intervened, according to an...

Read more
Read Indiana advocacy group calls for state data center moratorium
Indiana advocacy group calls for state data center moratorium

Indiana advocacy group calls for state data center moratorium

October 30, 2024 Indiana

Indiana consumer and environmental advocacy organization Citizens Action Coalition (CAC) has called for a pause on new hyperscale data center development in the state. The group this week called on the Indiana General Assembly to enact a moratorium on new hyperscale data centers used to power...

Read more
Read 1547 CSR and Harrison Street acquire carrier hotel in Indiana
1547 CSR and Harrison Street acquire carrier hotel in Indiana

1547 CSR and Harrison Street acquire carrier hotel in Indiana

September 06, 2024 Indiana

Fifteenfortyseven Critical Systems Realty (1547) and Harrison Street announced the acquisition of the Global Access Point Union Station data center located in Northern Indiana. This facility offers access to more than 20 telecommunication network service providers, totaling 75,000 sq ft (6,965...

Read more
Read Meta signs new renewable energy deal in Indiana
Meta signs new renewable energy deal in Indiana

Meta signs new renewable energy deal in Indiana

August 25, 2024 Indiana

Meta has signed a long-term Environmental Attributes Purchase Agreement with Arevon Energy, a renewable energy developer, owner, and operator for its Heirloom Solar Project in Pike County, Indiana. “Arevon is proud to once again partner with Meta and contribute to their sustainability goal of...

Read more
Read Provident Realty Advisors withdraws proposal for Indiana data center
Provident Realty Advisors withdraws proposal for Indiana data center

Provident Realty Advisors withdraws proposal for Indiana data center

June 14, 2024 Indiana

Provident Realty Advisors notified Chesterton officials on June 10 about its intention to withdraw its proposal for a $1.3 billion data center in Chesterton, Porter County, Indiana.The led to from residents regarding the development, with concerns surrounding negative impacts of air, water,...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?