Overview
Dalarna lies in central Sweden, northwest of Stockholm. Google's purchase of 109 hectares at Horndal, in Avesta municipality, became public in October 2017. EcoDataCenter opened its first halls in Falun in 2018. Since 2024, AI demand has brought larger campuses on former industrial land.
The Market Today
EcoDataCenter leads the market. Its Falun campus hosts CoreWeave, DeepL and BMW. In September 2025 it broke ground in Borlänge on part of the former Kvarnsveden paper mill. Mistral AI plans to open its first AI infrastructure outside France there in 2027. Microsoft has agreed to rent Mistral capacity in Sweden. In August 2026 EcoDataCenter signed a land agreement in Smedjebacken, near Ludvika. Google broke ground at Horndal in June 2026 and targets completion in 2028.
Advantages
-
Grid room. Svenska kraftnät (Svk) maps more than 500 MW of free withdrawal capacity in Dalarna, its highest band.
-
Brownfield land. Former mill land at Kvarnsveden offers large plots near an existing regional grid station.
-
Heat reuse. Server heat from Falun feeds the town's district heating and dries wood pellets at a neighbouring plant.
Challenges
-
Grid works. Borlänge Energi is building two new 145 kV stations to connect the Borlänge campus.
-
Southern prices. The county's data centres sit in bidding zone SE3, where 2025 spot prices averaged more than twice those in SE2.
-
Long lead times. Google broke ground at Horndal nearly nine years after it bought the land.
Power and Policy
Svk runs the transmission grid and the connection queue. Ellevio and Vattenfall Eldistribution run the regional grids, and municipal companies such as Falu Elnät and Borlänge Energi distribute power in the towns.