Crusoe: Goodnight 1

Latest Podcast 10001 Lima Rd
Under Construction
New facility under construction
Operated by:

Crusoe: Goodnight 1

Short Code: Building 1
Year Planned: 2026

Sites leasing space from Crusoe:

  • Hyperscale Data CenterInterested in this information?Contact us

The Armstrong County AI Data Center project, spearheaded by Crusoe Energy, has been redesigned from its original plan. The original 3.5 million-square-foot, seven-building complex will now consist of six buildings. Furthermore, site work is already underway on four pads. This revised plan specifies two smaller "Abilene-type" hyperscale structures, each measuring 484,954 square feet. The scope is rounded out by four substantially larger, rectangular "warehouse-style" buildings, each 805,380 square feet, designed to support roughly double the capacity of the smaller modules.

The new deal keeps the county’s total 10-year abatement value intact but shifts payments to $1.35 million per year for each building as soon as it becomes operational, with the first check possible by June or July 2026.

Crusoe spokesman Tyler Hunt told the court that construction on the four buildings should be finished within two years and that the company is in active negotiations with a prospective tenant, aiming to lease the entire campus to a single user.

The site will rely on the ERCOT grid, supplemented by the 265.5 MW Goodnight Wind Farm (already operating in Armstrong County) through a renewable-energy purchase agreement.

Map and Nearby Locations

10001 Lima Rd
Crusoe Sites
Nearby Facilities

Crusoe: Goodnight 1 Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Crusoe: Goodnight 1

Distance Site About
0.02 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
0.17 miles Crusoe: Goodnight 2
0.19 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
0.34 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
0.34 miles Crusoe: Goodnight 4
0.42 miles Crusoe: Goodnight 5
0.46 miles Crusoe: Goodnight 3
0.48 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
0.48 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
0.59 miles Crusoe: Goodnight 6
0.64 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us

Crusoe: Goodnight 1 Data Center Photos See all

Conceptual plan for Crusoe's Goodnight Campus in Armstrong County
Source: Armstrong County Tax Abatement Agreement GNDC1
Crusoe’s DFM system converts natural gas into electricity that powers wellsite digital operations
Source: Source: Crusoe Energy Systems

Operating Company

Operated by:

Crusoe is a privately held AI infrastructure developer and GPU cloud provider that builds AI data center campuses and offers GPU cloud services in the United States. The company began as Crusoe Energy Systems, a flare mitigation provider that powered onsite computing from stranded natural gas, with bitcoin mining as an early use case.

Crusoe is developing an AI campus at the Lancium Clean Campus in Abilene, Texas, planned for 1.2 GW, and in May 2025 it secured $11.6 billion in debt and equity to expand the site from two to eight buildings.

For this project, it is reported that Crusoe’s direct customer is Oracle and that OpenAI is Oracle’s customer; the Abilene campus is tied to OpenAI’s Stargate program;

OpenAI later announced an additional 4.5 GW Stargate partnership with Oracle that references the Abilene Stargate I site. Crusoe also expanded in-house manufacturing capability through the acquisition of Easter-Owens Electric in 2022.

Crusoe History:

  • In July 2025 announced a 1.8 GW AI data center campus with Tallgrass near Cheyenne, Wyoming.
  • In May, 2025, secured $11.6 billion in debt and equity to expand the Abilene, Texas campus to eight buildings, with Crusoe noting Oracle as the direct customer and OpenAI as Oracle’s customer for the site.
  • In March 2025 began construction on the second phase of the Abilene, Texas campus to bring total planned capacity to 1.2 GW.
  • In April 2022 raised Series C financing that included plans to launch the CrusoeCloud platform for high performance computing.
  • In June 2022 acquired Easter-Owens Electric to vertically integrate modular data center manufacturing.
  • Founded in 2018 as Crusoe Energy Systems to mitigate gas flaring by powering onsite computing, including bitcoin mining.
0
Facilities
0
Markets

News See all

Read Crusoe Takes 40MW Second Phase At Polar's Hydro-Powered Norway Campus
[Crusoe](https://baxtel.com/data-centers/crusoe) will take a second, larger building at [Polar Data Centers](https://baxtel.com/data-centers/polar-dc)' Tørdal campus in Norway. Polar announced the ...

Crusoe Takes 40MW Second Phase At Polar's Hydro-Powered Norway Campus

October 22, 2026 Crusoe

Crusoe will take a second, larger building at Polar Data Centers' Tørdal campus in Norway. Polar announced the expansion on Oct. 21 (announcement). The new building, DRA02, will add 40MW of liquid-cooled critical IT capacity on hydroelectric power and is due online in late 2027. Crusoe plans to...

Read more
Read 2026 Is the Year Texas Passes Virginia in Data Center Capacity
[Texas](https://baxtel.com/data-center/texas) now has more data center capacity operating and under construction than [Virginia](https://baxtel.com/data-center/virginia). Baxtel tracks 28.3 GW buil...

2026 Is the Year Texas Passes Virginia in Data Center Capacity

October 13, 2026 Texas

Texas now has more data center capacity operating and under construction than Virginia. Baxtel tracks 28.3 GW built or building in Texas, against 17.8 GW in Virginia. On capacity already online, Virginia still leads, 12.3 GW to 11.1 GW. If projects scheduled for this year deliver on time, Texas...

Read more
Read Crusoe Files For $4.8B Data Center Campus In Jayton, Texas
Crusoe has filed plans with the [Texas Department of Licensing and Regulation](https://www.tdlr.texas.gov/tabs/search) for a two-building data center campus in Jayton, in rural Kent County, Texas, ...

Crusoe Files For $4.8B Data Center Campus In Jayton, Texas

October 02, 2026 Crusoe

Crusoe has filed plans with the Texas Department of Licensing and Regulation for a two-building data center campus in Jayton, in rural Kent County, Texas, carrying an estimated investment of $4.8 billion. The filings, first reported by Data Center Dynamics, place the site along County Road 233...

Read more
Read Crusoe Plans $4.8bn Data Center Campus in Jayton, Texas
Crusoe has filed plans for two data center buildings in Jayton, Texas.
According to filings with the Texas Department of Licensing and Regulation, both facilities will be located along Country Roa...

Crusoe Plans $4.8bn Data Center Campus in Jayton, Texas

October 02, 2026 Crusoe

Crusoe has filed plans for two data center buildings in Jayton, Texas. According to filings with the Texas Department of Licensing and Regulation, both facilities will be located along Country Road 233 and P2390 at an unspecified address in Jayton, Kent County. Each data center will span 759,260...

Read more
Read Crusoe Confirms Google AI Campus In Texas With 531MW Wind Link
Crusoe is the developer behind Google's data center campus under construction in Armstrong County, Texas, the company [said on Sept. 28](https://www.crusoe.ai/resources/newsroom/crusoe-developing-d...

Crusoe Confirms Google AI Campus In Texas With 531MW Wind Link

October 01, 2026 Crusoe

Crusoe is the developer behind Google's data center campus under construction in Armstrong County, Texas, the company said on Sept. 28. The site sits outside Amarillo, and it pairs with 531 megawatts of adjacent West Texas wind, a design that puts generation rather than land at the center of the...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?