The Armstrong County AI Data Center project, spearheaded by Crusoe Energy, has been redesigned from its original plan. The original 3.5 million-square-foot, seven-building complex will now consist of six buildings. Furthermore, site work is already underway on four pads. This revised plan specifies two smaller "Abilene-type" hyperscale structures, each measuring 484,954 square feet. The scope is rounded out by four substantially larger, rectangular "warehouse-style" buildings, each 805,380 square feet, designed to support roughly double the capacity of the smaller modules.

The new deal keeps the county’s total 10-year abatement value intact but shifts payments to $1.35 million per year for each building as soon as it becomes operational, with the first check possible by June or July 2026.

Crusoe spokesman Tyler Hunt told the court that construction on the four buildings should be finished within two years and that the company is in active negotiations with a prospective tenant, aiming to lease the entire campus to a single user.

The site will rely on the ERCOT grid, supplemented by the 265.5 MW Goodnight Wind Farm (already operating in Armstrong County) through a renewable-energy purchase agreement.

Map and Nearby Locations:

10001 Lima Rd
Crusoe Sites
Nearby Facilities

Sites within 15 miles of Crusoe: Goodnight Campus

Distance Site About
0.02 miles Hyperscale Data Center Request Dataset
The Armstrong County AI Data Center project, spearheaded by Crusoe Energy, has been redesigned from its original plan.
0.17 miles Crusoe: Goodnight 2
0.19 miles Hyperscale Data Center Request Dataset
This facility is part of a new Google data center campus in Armstrong County, West Texas.
0.35 miles Crusoe: Goodnight 6
0.35 miles Hyperscale Data Center Request Dataset
This facility is part of a new Google data center campus in Armstrong County, West Texas.
0.42 miles Crusoe: Goodnight 4
0.45 miles Hyperscale Data Center Request Dataset
This facility is part of a new Google data center campus in Armstrong County, West Texas.
0.46 miles Crusoe: Goodnight 3
0.48 miles Hyperscale Data Center Request Dataset
This facility is part of a new Google data center campus in Armstrong County, West Texas.
0.61 miles Crusoe: Goodnight 5
0.62 miles Hyperscale Data Center Request Dataset
This facility is part of a new Google data center campus in Armstrong County, West Texas.

Crusoe: Goodnight Campus Data Center Photos (See all)

Conceptual plan for Crusoe's Goodnight Campus in Armstrong County
Source: Armstrong County Tax Abatement Agreement GNDC1
Crusoe’s DFM system converts natural gas into electricity that powers wellsite digital operations
Source: Source: Crusoe Energy Systems

Operating Company

Operated by:

Crusoe is a privately held AI infrastructure developer and GPU cloud provider that builds AI data center campuses and offers GPU cloud services in the United States. The company began as Crusoe Energy Systems, a flare mitigation provider that powered onsite computing from stranded natural gas, with bitcoin mining as an early use case.

Crusoe is developing an AI campus at the Lancium Clean Campus in Abilene, Texas, planned for 1.2 GW, and in May 2025 it secured $11.6 billion in debt and equity to expand the site from two to eight buildings.

For this project, it is reported that Crusoe’s direct customer is Oracle and that OpenAI is Oracle’s customer; the Abilene campus is tied to OpenAI’s Stargate program;

OpenAI later announced an additional 4.5 GW Stargate partnership with Oracle that references the Abilene Stargate I site. Crusoe also expanded in-house manufacturing capability through the acquisition of Easter-Owens Electric in 2022.

Crusoe History:

  • In July 2025 announced a 1.8 GW AI data center campus with Tallgrass near Cheyenne, Wyoming.
  • In May, 2025, secured $11.6 billion in debt and equity to expand the Abilene, Texas campus to eight buildings, with Crusoe noting Oracle as the direct customer and OpenAI as Oracle’s customer for the site.
  • In March 2025 began construction on the second phase of the Abilene, Texas campus to bring total planned capacity to 1.2 GW.
  • In April 2022 raised Series C financing that included plans to launch the CrusoeCloud platform for high performance computing.
  • In June 2022 acquired Easter-Owens Electric to vertically integrate modular data center manufacturing.
  • Founded in 2018 as Crusoe Energy Systems to mitigate gas flaring by powering onsite computing, including bitcoin mining.
22
Facilities
0
Markets

News (See all)

Read More News

Podcasts (See all)

See More Podcasts

Documents (See all)

Ready to Level up Your
Data Center Strategy?